Tender Value
₹6.4 L
EMD Value
₹63,546
Closing Date
8 Apr 2026, 2:00 pmClosed
EXECUTIVE OFFICER
NAGAR PANCHAYAT ATSU
Construction of Public Toilet near Purwa ka Taal (Pond) in Shree Nagar Ward of Nagar Panchayat Atsu under SBM 2.0
2026_DOLBU_1127101_1
779/ E.-N.A.S./N.P.A./2025-26 Dt. 13-03-2026-01
Open Tender
Civil Works
Lump-sum
90 days
NAGAR PANCHAYAT ATSU
Please refer Tender documents.
2 documents required · 2 mandatory
₹767
EXECUTIVE OFFICER
₹63,546
NAGAR PANCHAYAT ATSU
29 Apr 2026
20 Mar 2026
8 Apr 2026
20 Mar 2026
8 Apr 2026
20 Mar 2026
7 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Excavation in foundation in ordinary soil (Lome clay, or sand ) including filling lift upto 1.5 metre and lead 30 meters & including filling, watering and ramming of excavated earth into the tremches or into the plinth and removal and disposal of surplush earth upto distance of 30 mt. from the foundation trances As per S.I. No. 251 | |||||
| 2Earth Work in cutting or in embankment in ordinary soil excvation to be in the form of regular pits not exceeding half mt. in depth and earth work embankment to be in 20cm layer including ramming and addreding the surface to required labels and stop and also including 1.5mt. lift and 30mt. lead As per S.I. No. 253 with cartage 2 km | |||||
| 3Cement Concrete with 4cm guage B/ball., fine local sand of 1.25 F.M. and cemecnt in 12:6:1 in foundation and under floor including supply of all materials labour etc. required for the proper completion of the work As per S.I. No. 273 | |||||
| 4First class brick work in 1:6 cement and coarse sand mortar in foundation and plinth labour only required for proper complition of the work as per S.I. No. 303 | |||||
| 5First class brick work in 1:6 cement and Coarse Sand mortar in Super structre in one brick thick labour only required for proper complition of the work as per S.I. No. 310 | |||||
| 6R.C.C. work with cement approved coarse sand and 2 cm gauge approved stone ballast in the proportion of 1:2:4 in lintels of doors and window excluding supply of reignforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.I. binding wire and i/c necessary centering and shuttering etc. and also i/c supply of all material labour T&P etc. rquired for proper completion of the work. binding wire cost being included inthe item.S.I. No -283 | |||||
| 7R.C.C. work with cement approved coarse sand and 2 cm gauge approved stone ballast in the proportion of 1:2:4 in slabs excluding supply of reignforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.I. binding wire and i/c necessary centering and shuttering etc. and also i/c supply of all material labour T&P etc. rquired for proper completion of the work. binding wire cost being included inthe item.S.I. No -284 | |||||
| 8MS or iron in plane work such as reinforced concrete or reinforced brick work (when not included in an over all rates) wrought to required shape as necessary including bending for proper completion of the work and including supply of all steel and wastage &over lapping & hooks (labour only) as per S.I. No.504 | |||||
| 912 mm thick Cement plaster in single coat on out side of single or half brick wall for interior plastering including arises interior rounded angles chamfers and of rounded angle not exeeding 80 mm in girth and finished even and smooth.1:6 with cement and F/sand mortar as per New Item | |||||
| 10Cement Concrete with 2 cm guage approved stone Ballast, C/sand and cement in the proportin of 4:2:1 including supply of all materials labour etc. required for the proper completion of the work As per S.I. No. 279 (a) | |||||
stage.html
html • 0.02 MB
tech_bid_open.pdf
tech_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 4.13 MB
BOQ_2103862.xls
BOQ • 0.26 MB
Corrigendum.pdf
PDF • 0.50 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .