| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹137.3 CrAccepted-AOC | ₹137.3 Cr | L1 | Accepted-AOC Agreement done as per attached letter. |
| 2 | L2₹142.0 CrRejected-Finance | ₹142.0 Cr | L2 | Rejected-Finance BEING L2 |
| 3 | L3₹142.7 CrRejected-Finance INDORE | ₹142.7 Cr | L3 | Rejected-Finance BEING L3 |
Tender Value
₹138.5 Cr
EMD Value
₹50 L
Closing Date
26 Oct 2022, 5:30 pmClosed
EE WR Survey Division, Balaghat
EE WR Survey Division, Balaghat
On Turnkey Basis Construction of Lamta Pressurised Pipe Irrigation Network Project Hose System, as per details in scope of work but not limited to that.
2022_WRD_214358_1
916/2022-23/ENC/ete/Lamta Dt. 01.08.22
Open Tender
Civil Works - Others
1080 days
Balaghat
Please refer tender document
29 documents required · 29 mandatory
₹50,000
₹50 L
Bhopal
1 Feb 2023
23 Sept 2022
28 Oct 2022
23 Sept 2022
26 Oct 2022
26 Sept 2022
30 Sept 2022
Amount
Construction of a Pressurised Pipe irrigation network system to supply water from submergence of Dhuty Weir in Distt Balaghat near head regulator of Dhuty L.B.C. through Rising/ gravity mains for hose irrigation to deliver at farmer’s field up to 5 HA Chak Field with a duty of 0.45 lit/sec/Ha and maintained up to 5.00 ha chak, keeping the discharge of minimum 10 times the duty at 5.00 hectare and at least 8 Meter Residual Head at the highest point of each 5.00 ha chak by rotation with a total power requirement of 4.68 MW in the Culturable Command Area of 9630 Hectare for Kharif (Paddy) out of GCA 12250 Ha, fully covering the entire compact and contiguous possible arable area as per the index map covering 55 villages as per attached list, for Micro Irrigation System under LAMTA PRESSURISED PIPE IRRIGATION PROJECT (HOSE SYSTEM) of distt Balaghat (M.P.). it includes all activities starting from survey, investigations, Land Acquisition of private and Forest land, designing, preparation and submission of drawings, estimates and its approval from competent authorities including procurement, construction, laying, installing and testing of Piped Irrigation Network (PIN) consisting of gravity main, main lines, branch lines with all allied inline structures, distribution network including controlling and regulation systems, including construction of cross drainage work and aqueduct on major river, for supply of water for irrigation under pressure with SCADA and automation. The work also includes Watch and ward, Management, Operation and Maintenance (MOM) for the period of 60 months after completion and further extendable for another 60 months, and 60 months of defect liability period running simultaneously, with formation of WUAs and establishment of Farmers Service Centre on turnkey basis
Construction of a Pressurised Pipe irrigation network system to supply water from submergence of Dhuty Weir in Distt Balaghat near head regulator of Dhuty L.B.C. through Rising/ gravity mains for hose irrigation to deliver at farmer’s field up to 5 HA Chak Field with a duty of 0.45 lit/sec/Ha and maintained up to 5.00 ha chak, keeping the discharge of minimum 10 times the duty at 5.00 hectare and at least 8 Meter Residual Head at the highest point of each 5.00 ha chak by rotation with a total power requirement of 4.68 MW in the Culturable Command Area of 9630 Hectare for Kharif (Paddy) out of GCA 12250 Ha, fully covering the entire compact and contiguous possible arable area as per the index map covering 55 villages as per attached list, for Micro Irrigation System under LAMTA PRESSURISED PIPE IRRIGATION PROJECT (HOSE SYSTEM) of distt Balaghat (M.P.). it includes all activities starting from survey, investigations, Land Acquisition of private and Forest land, designing, preparation and submission of drawings, estimates and its approval from competent authorities including procurement, construction, laying, installing and testing of Piped Irrigation Network (PIN) consisting of gravity main, main lines, branch lines with all allied inline structures, distribution network including controlling and regulation systems, including construction of cross drainage work and aqueduct on major river, for supply of water for irrigation under pressure with SCADA and automation. The work also includes Watch and ward, Management, Operation and Maintenance (MOM) for the period of 60 months after completion and further extendable for another 60 months, and 60 months of defect liability period running simultaneously, with formation of WUAs and establishment of Farmers Service Centre on turnkey basis
Karan Development Services PVT. LTD.
PHALOUDI CONSTRUCTIONS AND INFRASTRUCTURE PVT LTD
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid