Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹6.3 LAccepted-AOC ALKAPURI ETAWAH | ETAWAH | UTTAR PRADESH | 206001 | L1 | Accepted-AOC AOC | |
| 2 | L2₹6.7 L+₹35,124.32 (5.55%)Rejected-Finance | L2 | Rejected-Finance Financial Bid not Qualified By Bidder |
Tender Value
₹8.2 L
EMD Value
₹17,000
Closing Date
16 Nov 2023, 3:00 pmClosed
Executive Engineer
Executive Engineer Irrigation Division Ist karwi Chitrakoot
Construction of Precast RCC Ready made Boundry Wall at f JEs Quarters Tahsil Mau Distt Chitrakoot Lot 3
2023_UPIDC_858883_1
04/E.E./2023-24 Dt. 18-10-2023
Open Tender
Civil Works
Item Wise
30 days
Mau
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,154
₹17,000
Yes
2 Mar 2024
2 Nov 2023
16 Nov 2023
2 Nov 2023
16 Nov 2023
2 Nov 2023
2 Nov 2023 - 16 Nov 2023
Amount
Cutting heavy undergrowth and bushes upto 7.50 cm dia including removal all cost of labour T&P and etc completion of the work.
Earth work in M.K.R. and kankar mixed soil in excavation in foundation with Disposal with in lead upto 30M & lift upto 1.50 m including labour, T&P and etc. completion of the work.
P.C.C. in 1:3:6 (M-10) with cement coarse sand, stone grit Including all cost of materials, its carriage, labour, T&P and etc completion of the work.
C.C. in 1:1.5:3 (M-20) with cement coarse sand, stone grit Including all cost of material, its carriage, labour, T&P and etc completion of the work.
Reinforcement for R.C.C. work I/c cutting, placing, bending, binding, with G.I. wire with it's cost, its carriage, labour, T&P and etc required completion of the work.
Centring and shuttering I/c all cost of labour, T&P and etc required completion of the work.
R.C.C. in 1:2:4 (M-15) with cement, coarse sand, stone grit including all cost of materials, its carrriage labour, T&P and etc completion of the work. But execluding all cost of reinforcement and C/S.
R.C.C. in 1:1½:3 (M-20) with cement, coarse sand, stone grit including all cost of materials, its carrriage labour, T&P and etc completion of the work. But execluding all cost of reinforcement and C/S.
Providing and fixing of Precast R.C.C (M-25) post size(2400x150x150)mm,I-section reinforced with 7 nos 4 mm dia H.T.S. wire and R.C.C (M-25) Pannel (2100x300x50) mm steel reinforced with 4 nos 4 mm high tensile steel wire etc. i/c all cost of material, its carriage , labour, T&P and etc, completion of the work and direction of Engineer in charge.
12 mm thick cement plaster in 1:3 with cm I/c all cost of materials ,its carriage, labour, T&P and etc completion of the work.
Providing and applying white cement based putty of average thickness 1 mm of approved brand and manufacturer over the plastered wall surface to prepare the surface even and smooth complete. I/c all cost of materials, its carriage, labour, T&P and etc completion of the work.
Painting two coats including primer coat after filling the surface with sythetic enamel paint in all shades on pastered/concrete surfaces all cost of materials, its carriage, labour, T&P etc completion of the work.
Fabrication of steel gate and gate frame I/c cutting, drilling, welding, riveting and hinges where necessary and fixing in position I/c all cost of materials,its carriage one coat of red oxide primer, labour T&P and required proper completion of the work.
Painting Sign board Including Writting the letters and cost of materials (paint), labour, T&P and etc completion of the work.
Painting of Iron/ Wood work two coats over one coat of primer Including all cost of materials (paint), labour, T&P and etc completion of the work.
M/S MANOJ KUMAR THEKEDAR
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .