| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹10.3 LAdmitted-Finance | -44.51% | ₹10.3 L | L1 | Admitted-Finance |
| 2 | L2₹11.0 L+₹74,191.34 (7.23%)Admitted-Finance | -40.50% | ₹11.0 L+₹74,191.34 (7.23%) | L2 | Admitted-Finance |
| 3 | L3₹12.0 L+₹1.7 L (16.5%)Admitted-Finance | -35.35% | ₹12.0 L+₹1.7 L (16.5%) | L3 | Admitted-Finance |
| 4 | L4₹12.6 L+₹2.3 L (22.5%)Admitted-Finance | -32.00% | ₹12.6 L+₹2.3 L (22.5%) | L4 | Admitted-Finance |
| 5 | L5₹14.0 L+₹3.7 L (36.0%)Admitted-Finance | -24.51% | ₹14.0 L+₹3.7 L (36.0%) | L5 | Admitted-Finance |
Tender Value
₹18.5 L
EMD Value
₹37,004
Closing Date
27 Aug 2026, 3:00 pmClosed
EXECUTIVE ENGINEER
CGD 1 SEED BED PARK SHAKARPUR NEW DELHI 110092
M/O Various scheme under NA-II (EZ)S.H.- Urgent Repair of Internal Road at CWG Village
2026_DDA_922683_1
09/EE/CGD-1/DDA/2026-27
Open Tender
Civil Works
Percentage
45 days
CGD 1 SEED BED PARK SHAKARPUR NEW DELHI 110092
Please refer Tender documents.
12 documents required · 12 mandatory
₹0
₹37,004
3 Sept 2026
19 Aug 2026
28 Aug 2026
19 Aug 2026
27 Aug 2026
19 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 50 metres lead.
a) For thickness of tiles 10 mm to 25 mm | 387 | sqm | 73.4 | ₹28,405.8 |
| 2 | Chequerred precast cement concrete tiles 15 to 22mm in footpath & courtyard, jointed with neat cement slurry mixed with pigment to match the shade of tiles, including rubbing and cleaning etc. complete, on 20mm thick bed of cement mortar 1:4 (1 cement: 4 coarse sand) a)Dark shade pigment using ordinary cement. | 387 | sqm | 1,119.5 | ₹4,33,246.5 |
| 3 | Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer -in - charge.
Nominal concrete 1:3:6 or richer mix (including equivalent
design mix) | 18 | cum | 2,434.25 | ₹43,816.5 |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level: a) 1:1½:3 (1 Cement: 1½ coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) | 18 | cum | 8,340.85 | ₹1,50,135.3 |
| 5 | Taking out existing CC interlocking paver blocks from footpath/ central verge, including removal of rubbish etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 metre lead as per direction of Engineer-in-Charge. | 766 | sqm | 131.75 | ₹1,00,920.5 |
| 6 | Laying old cement cocrete interlocking paver blocks of any design/ shape laid in required line, level, curvature, colour and pattern over and including 50 mm thick compacted bed of coarse sand, filling the joints with fine sand etc. all complete as per the direction of Engineer-in-charge. (Old CC paver blocks shall be supplied by the department free of cost). | 383 | sqm | 402.95 | ₹1,54,329.85 |
| 7 | Providing and laying 60 mm thick faciory made cement concrete interlocking paver block of M -30 grade made by block making machine with strong vibratory compaction, of approved size, design & shape, laid in required colour and pattern over and including 50 mm thick compacted bed of coarse sand, filling the joints with line sand etc. all complete as per the direction of Engineer-in-charge. | 383 | sqm | 972 | ₹3,72,276 |
| 8 | Clearing grass and removal of the rubbish up to a distance of 50 m outside the periphery of the area cleared. | 1,200 | sqm | 8.95 | ₹10,740 |
| 9 | Taking out existing kerb stones of all types from footpath/ central verge, including removal of mortar etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 metre lead as per direction of Engineer-in-Charge. | 54 | metre | 39.35 | ₹2,124.9 |
| 10 | Providing and laying at or near ground level factory made kerb stone of M-25 grade cement concrete in position to the required line, level and curvature, jointed with cement mortar 1:3 (1 cement: 3 coarse sand), including making joints with or without grooves (thickness of joints except at sharp curve shall not to more than 5 mm), including making drainage opening wherever required complete etc. as per direction of Engineerin-charge (length of finished kerb edging shall be measured to calculate volume for payment) (Precast C.C. kerb stone shall be approved by Engineer-in-charge). | 2.4 | cum | 10,117.6 | ₹24,282.24 |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.57 MB
td9.pdf
Tender Documents • 3.07 MB
BOQ_969597.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .