| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.8 CrAccepted-AOC | ₹1.8 Cr | L1 | Accepted-AOC Lowest rate |
| 2 | L2₹1.8 Cr+₹5.4 L (3.06%)Rejected-Finance | ₹1.8 Cr+₹5.4 L (3.06%) | L2 | Rejected-Finance Above L1 rate |
Tender Value
₹1.8 Cr
EMD Value
₹3.6 L
Closing Date
2 Dec 2020, 3:00 pmClosed
Project Director
DRDA Office, 2nd floor, New Collectorate Thanjavur
Thanjavur District - PMGSY III BATCH I (2020-21)- Package No. TN-17-109 MRL 29 Edaiiruppu Manakal Road Neducheri Thirukarukkavur Road in Ammapettai Block
2020_RDTN_101432_1
TN17109
Open Tender
Civil Works - Roads
Piece-work
270 days
Ammapettai
As per Technical bid Tender document
9 documents required · 9 mandatory
₹0
₹3.6 L
DRDA Office, 2nd floor, New Collectorate Thanjavur
18 Feb 2021
23 Oct 2020
2 Dec 2020
23 Oct 2020
2 Dec 2020
23 Oct 2020
12 Nov 2020
Amount
Upgradation and Five Year Maintenance of MRL29 - Edaiiruppu Manakal Road Neducheri Thirukarukkavur Road Km 0/0-3/150.
Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per Technical Specification Clause 201.
Picking the existing BT surface by Mechanical means , Scarifying the existing bituminous road surface to a depth of 150 mm and disposal of scarified material with a lift upto 3 m and lead upto 1000 m as per Technical Specification Clause 301.4.
Excavation for Road Work in soil with Hydrallic Excavator of 0.9 Cum bucket Capacity of including cutting and loading in tippers, trimming bottom and side slopes in accordance With Requirements of line ,grades and cross section and transporting to the embakement location with a lift ipto 1.5 m and lead upto 1000 m as per Technical specification clause 302.3
Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause(FIlling With Cut Earth)
Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1.( Carted Earth)
Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause 301.5 (Gravel shoulder)
Construction of Subgrade for 300 mm Depth by using picked materaials obtained from the Existing surface by machanical means and then adding 50% of deflict materials by usig stone dust obtained from industries with all lifts and leads transporting to site, spreading and grading to Required slope and compacted to meet requirement taple 300.2 with lead upto 1000 m as per technical Specification clause 303.1.(subgrade using Stone dust to improve CBR 7 TO 9)
Construction of granular sub - base by providing well graded materials Spreading in uniform layers with motor grader on prepared surface ,mixing by mix in place method with rotavator at OMC and compacting with three wheel 80-100 KN static roller Capacity to Achive the Desired density .complete as per Technical Specification Clause 402 Grading C
Providing, laying, spreading and compacting stone aggregates To wet mix macadeam Specification including premixing the material With water at OMC in mechanaical mix plant carriage of mixed material by tipper to site ,laying in uniform layers with paver in sub base /base course on a well preared surface and compacting with vibratory roller to achive the desired density
Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.85 kg/sqm (0.70-1.0) using mechanical means as per Technical Specification Clause 502
Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.275 kg per sqm (0.25 to 0.30) on the prepared granular surface treated with Primer cleaned with Hydraulic broom as per Technical Specification Clause 503.
Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or emulsion to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 80-100 kN static roller capacity, finished to required level and grades to be followed by seal coat of either Type A or Type B or Type C as per Technical Specification Clause 508.
Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type A, Type B and Type C as per Technical Specification Clause 510
Provision of Rumple strips with Premix Bituminous Carpet,15-20mm high at centre to centre approved locations to controle speed ,marked with while strips of road marking paint
Construction of 1.5 m RCC Slab culvert @ Chainage 612m,925m
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202.Foundation.
Dismantling of Culvert @ Ch.612m,925m
Dismantling of existing structures like culverts, bridges, retaining walls and other structures comprising of brick masonry including disposal of unserviceable material and stacking the serviceable material with all lift and lead of 1000 m as per Technical Specification Clause 202. Substructure.
Dismantling of Culvert @ Ch.612m,925m
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202.Reinforced Cement concrete pipe.
Dismantling of Culvert @ Ch.612m,925m
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Construction of culvert @ Ch.612m,925m
Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
Construction of culvert @ Ch.612m,925m
Cement concrete 1 : 2.5 : 5 mix using 40mm, 20mm & 10mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Construction of culvert @ Ch.612m,925m
Cement concrete 1 : 2 : 4 mix using 40mm, 20mm & 10mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. (Below sill)
Construction of culvert @ Ch.612m,925m
Cement concrete 1 : 2 : 4 mix using 40mm, 20mm & 10mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. (Above sill)
Construction of culvert @ Ch.612m,925m
Cement concrete 1 : 2 : 4 mix using 20mm & 10mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.(Bed Block and Dirt wall)
Construction of culvert @ Ch.612m,925m
Cement concrete 1:1.5:3 using 20mm & 10mmISS HBG metal for all RCC item of works excluding cost of Rein forcement and fabricating charges, centering and shuttering but including curing and shall be finished smooth with cement mortar 1:3, 12mm thick. and with kraft paper without claiming extra as directed by the departmental officers complete complying with standard specifications.
Construction of culvert @ Ch.612m,925m
Supplying and Fabricating and placing in position MS steel or Ribbed Tor Steel for all Reinforced Cement Concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.(MS rod or RTS bar will be supplied departmentally at section stores and cost will be recoverd at issue rate). the binding wire shall supplied by the contactor.
Construction of culvert @ Ch.612m,925m
Providing and fixing 6mm Bitumen felt for expansion joint Between Dirtwall & Deck slab
Construction of culvert @ Ch.612m,925m
Providing and fixing Tar Paper for bearing Between Bed Block & Deck slab.
Construction of culvert @ Ch.612m,925m
Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 614, 709, 1204.3.7
Construction of culvert @ Ch.612m,925m
Gravel filling between body wall including cost and conveyance of gravel, labour for filling, watering and compacting etc complete complying with standard specification and as directed by the departmental officer.
Construction of culvert @ Ch.612m,925m
Construction of 2.0m RCC Slab culvert Km. 1/0 to 2/0 Chainage @ 1910
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202.Foundation.
dismantling of Culvert @ Ch.1910
Dismantling of existing structures like culverts, bridges, retaining walls and other structures comprising of brick masonry including disposal of unserviceable material and stacking the serviceable material with all lift and lead of 1000 m as per Technical Specification Clause 202. Substructure.
dismantling of Culvert @ Ch.1910
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202.Reinforced Cement concrete
dismantling of Culvert @ Ch.1910
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Construction of culvert @ Ch.1910
Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
Construction of culvert @ Ch.1910
Cement concrete 1 : 2.5 : 5 mix using 40mm, 20mm & 10mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Construction of culvert @ Ch.1910
Cement concrete 1 : 2 : 4 mix using 40mm, 20mm & 10mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. (Below sill)
Construction of culvert @ Ch.1910
Cement concrete 1 : 2 : 4 mix using 40mm, 20mm & 10mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. (Above sill)
Construction of culvert @ Ch.1910
Cement concrete 1 : 2 : 4 mix using 20mm & 10mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.(Bed Block and Dirt wall)
Construction of culvert @ Ch.1910
Cement concrete 1:1.5:3 using 20mm & 10mmISS HBG metal for all RCC item of works excluding cost of Rein forcement and fabricating charges, centering and shuttering but including curing and shall be finished smooth with cement mortar 1:3, 12mm thick. and with kraft paper without claiming extra as directed by the departmental officers complete complying with standard specifications.
Construction of culvert @ Ch.1910
Supplying and Fabricating and placing in position MS steel or Ribbed Tor Steel for all Reinforced Cement Concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.(MS rod or RTS bar will be supplied departmentally at section stores and cost will be recoverd at issue rate). the binding wire shall supplied by the contactor.
Construction of culvert @ Ch.1910
Providing and fixing 20 mm thick compressible fibre board for expansion joint Between Dirtwall & Deck slab
Construction of culvert @ Ch.1910
Providing and fixing Tar Paper for bearing Between Bed Block & Deck slab.
Construction of culvert @ Ch.1910
Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 614, 709, 1204.3.7
Construction of culvert @ Ch.1910
Gravel filling between body wall including cost and conveyance of gravel, labour for filling, watering and compacting etc complete complying with standard specification and as directed by the departmental officer.
Construction of culvert @ Ch.1910
Construction of 1.5m RCC Slab culvert Km. 2/0 to 3/0 Chainage @ 2498
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202.Foundation.
dismantling of Culvert @ Ch.2498
Dismantling of existing structures like culverts, bridges, retaining walls and other structures comprising of brick masonry including disposal of unserviceable material and stacking the serviceable material with all lift and lead of 1000 m as per Technical Specification Clause 202. Substructure.
dismantling of Culvert @ Ch.2498
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202.Reinforced Cement concrete
dismantling of Culvert @ Ch.2498
Removal of Hume Pipes @ Ch.2498
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Construction of culvert @ Ch.2498
Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
Construction of culvert @ Ch.2498
Cement concrete 1 : 2.5 : 5 mix using 40mm, 20mm & 10mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Construction of culvert @ Ch.2498
Cement concrete 1 : 2 : 4 mix using 40mm, 20mm & 10mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. (Below sill)
Construction of culvert @ Ch.2498
Cement concrete 1 : 2 : 4 mix using 40mm, 20mm & 10mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. (Above sill)
Construction of culvert @ Ch.2498
Cement concrete 1 : 2 : 4 mix using 20mm & 10mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.(Bed Block and Dirt wall)
Construction of culvert @ Ch.2498
Cement concrete 1:1.5:3 using 20mm & 10mmISS HBG metal for all RCC item of works excluding cost of Rein forcement and fabricating charges, centering and shuttering but including curing and shall be finished smooth with cement mortar 1:3, 12mm thick. and with kraft paper without claiming extra as directed by the departmental officers complete complying with standard specifications.
Construction of culvert @ Ch.2498
Supplying and Fabricating and placing in position MS steel or Ribbed Tor Steel for all Reinforced Cement Concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.(MS rod or RTS bar will be supplied departmentally at section stores and cost will be recoverd at issue rate). the binding wire shall supplied by the contactor.
Construction of culvert @ Ch.2498
Providing and fixing 20 mm thick compressible fibre board for expansion joint Between Dirtwall & Deck slab
Construction of culvert @ Ch.2498
Providing and fixing Tar Paper for bearing Between Bed Block & Deck slab.
Construction of culvert @ Ch.2498
Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 614, 709, 1204.3.7
Construction of culvert @ Ch.2498
Gravel filling between body wall including cost and conveyance of gravel, labour for filling, watering and compacting etc complete complying with standard specification and as directed by the departmental officer.
Construction of culvert @ Ch.2498
Construction of 900mm Dia RCC Pipe culvert at Chainage @ 2729,2996
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202.Foundation.
dismantling of Culvert @ Ch.2729m,2996m
Dismantling of existing structures like culverts, bridges, retaining walls and other structures comprising of brick masonry including disposal of unserviceable material and stacking the serviceable material with all lift and lead of 1000 m as per Technical Specification Clause 202. Substructure.
dismantling of Culvert @ Ch.2729m,2996m
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Construction of culvert @ Ch.2729m,2996m
Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
Construction of culvert @ Ch.2729m,2996m
Cement concrete 1 : 3 : 6 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Construction of culvert @ Ch.2729m,2996m
Cement concrete 1 : 2.5 : 5 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc.,complete complying with standard specifications and as directed.
Construction of culvert @ Ch.2729m,2996m
Providing and Laying Reinforced cement concrete pipe NP3 for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation,Protection works,backfilling,Concrete and masonry works in head walls and parapets Clause 1106
Construction of culvert @ Ch.2729m,2996m
Gravel filling between body wall including cost and conveyance of gravel, labour for filling, watering and compacting etc complete complying with standard specification and as directed by the departmental officer.
Construction of culvert @ Ch.2729m,2996m
Construction of 900mm Dia RCC Pipe culvert at Chainage @ 3085 m.
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202.Foundation.
dismantling of culvert @ Ch. 3085
Dismantling of existing structures like culverts, bridges, retaining walls and other structures comprising of brick masonry including disposal of unserviceable material and stacking the serviceable material with all lift and lead of 1000 m as per Technical Specification Clause 202. Substructure.
dismantling of culvert @ Ch. 3085
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Construction of culvert @ Ch.3085
Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
Construction of culvert @ Ch.3085
Cement concrete 1 : 3 : 6 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Construction of culvert @ Ch.3085
Cement concrete 1 : 2.5 : 5 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc.,complete complying with standard specifications and as directed.
Construction of culvert @ Ch.3085
Providing and Laying Reinforced cement concrete pipe NP3 for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation,Protection works,backfilling,Concrete and masonry works in head walls and parapets Clause 1106
Construction of culvert @ Ch.3085
Gravel filling between body wall including cost and conveyance of gravel, labour for filling, watering and compacting etc complete complying with standard specification and as directed by the departmental officer.
Construction of culvert @ Ch.3085
Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign as per IRC:67 made of encapsulated lens type reflective sheeding vide Clause 1701.2.3 fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground levels as per drawings and Technical Specification Clause 801
Provision for Name board
Provision for Logo board
Provision for Citizen board
Provision for PMGSY Maintenance board
Provision for 90 cm Triangle Sign board
Provision for 60 cm Circular Sign board
Provision for octagon Sign board
Provision for Reflector
Provision for Kilometre Stones
Provision for Hectametre Stones
Guard Stone
Towards the charges for routline maintenance of the road work executed under PMGSY including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRC-SP-20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost for carriageway width of 3.00m & 3.75m
For the First Year from the date of completion of work
For the Second Year from the date of completion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
V GNANAPRAKASAM
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .