Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹78,029.01Accepted-Finance | L1 | Accepted-Finance Accepected |
| Sl No | Description | Qty | Unit | PRIME INFRA L1 |
|---|---|---|---|---|
| 1.00 | Excavation of pole pit for pole above 8.00m length by using JCB/Manual | 12 | Per Pit | 600 ₹7,200 Lowest |
| 2.00 | Erection of RCC, REC, PSC poles above 8.00m length by using Crane / Manual | 12 | Per Pole | 650 ₹7,800 Lowest |
| 3.00 | Fixing of Tapping X-Arm/Guarding X-Arm/V cross arm | 20 | Per | 210 ₹4,200 Lowest |
| 4.00 | Fixing of HT/LT TI Fittings | 14 | Per | 60 ₹840 Lowest |
| 5.00 | Fixing of 11 KV pin insulator | 45 | Per | 60 ₹2,700 Lowest |
| 6.00 | Fixing of 11 KV Strain Disc with Metal Parts | 12 | Per | 110 ₹1,320 Lowest |
| 7.00 | Excavation of Stay pit of 4.5 ' to 5 ' depth using JCB / Manual | 2 | Per Pit | 500 ₹1,000 Lowest |
| 8.00 | Erection of stay set complete with fixing up stay wire Eye, Bow, Guy Shackle, Binding etc.. | 2 | Each Set | 500 ₹1,000 Lowest |
| 9.00 | Paving and stringing of conductors of sizes 7/4.09 mm ACSR | 1.42 | Per KM | 3,300 ₹4,679.4 Lowest |
| 10.00 | Fixing of LT 3 Phase Cross Arm | 13 | Per | 120 ₹1,560 Lowest |
Tender Value
Refer Docs
Closing Date
4 Aug 2025, 2:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
EE Arcot
110KV SS Arcot Campus Thazhanur
Improvement proposal for new DTs proposed single pole structure 1 Nos 63 KVA existing Varadharajaperumal Nagar SS 63 KVA
2025_EB_582631_1
EE3/S.037
Limited
Electrical Works
Works
Arcot
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
Exempted
8 Aug 2025
19 Jul 2025
5 Aug 2025
19 Jul 2025
4 Aug 2025
19 Jul 2025
Amount
Excavation of pole pit for pole above 8.00m length by using JCB/Manual
Erection of RCC, REC, PSC poles above 8.00m length by using Crane / Manual
Fixing of Tapping X-Arm/Guarding X-Arm/V cross arm
Fixing of HT/LT TI Fittings
Fixing of 11 KV pin insulator
Fixing of 11 KV Strain Disc with Metal Parts
Excavation of Stay pit of 4.5 ' to 5 ' depth using JCB / Manual
Erection of stay set complete with fixing up stay wire Eye, Bow, Guy Shackle, Binding etc..
Paving and stringing of conductors of sizes 7/4.09 mm ACSR
Fixing of LT 3 Phase Cross Arm
Fixing of LT Shackle
Fixing of LT Pin Insulator
Fixing of Alu Knob
Erection of 11 KV Single Pole Structure including erection of DT complete with centre support including fixing of MCD box
Loading and Unloading of Distribution Transformer (i) Upto 100 KVA
Transporting of Distribution Transformer from stores to office /site upto 10 KM distance by engaging 1 Ton Capacity Minidor (Lorry)
Loading and Unloading of line materials
Transportation of all type of poles by bullock cart or other vehicle (i) For a lead upto 5 KM
Transportation of all type of poles by bullock cart or other vehicle (ii) Above 5 KM (10 X 75 = Rs.750)
Transporting of conductors of all sizes from road side to pit locations upto one KM of Conductor
(i) Transporting of Line materials from stores to office / site upto 10 KM distance by engaging 1 Ton capacity Minidor (Lorry)
G.S.T. @18% should be Entered by the Bidder
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .