EXECUTIVE ENGINEER (SDW) IX
RITHALA STP SEC-11 ROHINI DELHI-110085
Repair Renovation of 315 HP AEI Make motor installed at S 2 at Haiderpuri SPS.
2022_DJB_215174_7
NIT NO. 10 EE(SDW)IX (2021-22)
Open Tender
Miscellaneous Works
Works
45 days
EXECUTIVE ENGINEER (SDW) IX
please refer tender document
4 documents required · 4 mandatory
₹500
Account no. 50448339804
₹12,000
17 Feb 2022
21 Jan 2022
28 Jan 2022
21 Jan 2022
28 Jan 2022
21 Jan 2022
Dismantling the complete motor, removing the rotor from the stator and both side cover
ROTOR- Removing the old overheated old sockets connections in safe condition. P Fixing new copper sockets both side, brazing the sockets with silver rod, pocketing the sockets with F class insulation, replacement of 3 Nos. fiber glass Teflon copper flexible leads with copper lugs. Varnishing of complete rotor with Dr. Beck varnish and baking the same in all respect.
STATOR- Cutting the old stator burnt winding and insulations and cleaning by solvent. P Fixing of new F class insulation, rewinding the stator winding with new electrolyte super enameled copper wire, making the connection, brazing the same with sliver rod, pocketing the connection with F class insulation, replacement of stator winding Fiber glass Teflon copper flexible leads, varnishing of stator winding with Dr. Beck Varnish and baking the same.
Repair of rotor shaft DE and NDE side and replacement of both side bearing cover plate duly finished size as per existing
Providing fixing of both sides bearing NU-224 6320 Make SKF FAG
PFixing of new slip ring unit suitable for the motor as per exiting
P Fixing of suitable size fiber glass teflon copper flexible leads from carbon brush holder to rotor connection box
P Fixing of heavy duty carbon holder
P Fixing of carbon brush
Assembling the complete motor, re-install with existing pump on foundation and making zero-zero balancing and painting with enamel paint after scrubbing the old pain oily component . Testing of motor after making all the connection on full load at site
Gupta Brothers
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .