| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.3 CrAccepted-AOC | ₹1.3 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹1.4 Cr+₹3.9 L (2.95%)Rejected-Finance | ₹1.4 Cr+₹3.9 L (2.95%) | L2 | Rejected-Finance Highest amount |
| 3 | Not Admitted-Fee/PreQual/Technical 214 1 POONTHOTTA STREET SANKARNAGAR TIRUNELVELI 7 | TIRUNELVELI | TAMIL NADU | 627001 | - | - | Not Admitted-Fee/PreQual/Technical EMD Not Furnished |
| 4 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical EMD Not Furnished |
| 5 | Not Admitted-Fee/PreQual/Technical DOOR NO 5A SOUTH STREET THENNIMALAI NANGUNERI TIRUNELVELI | - | - | Not Admitted-Fee/PreQual/Technical EMD Not Furnished |
Tender Value
Refer Docs
EMD Value
₹1.4 L
Closing Date
15 May 2023, 3:00 pmClosed
Project Director
DRDA ,Tirunelveli
Tirunelveli District Nanguneri Block Renewal of 1 roads in Package No 28 under MGSMT 2022 23
2023_RDTN_308148_9
DIPR/2018/Tender/2023 MGSMT 2022 23 rev tender dat
Open Tender
Civil Works
Item Rate
90 days
Tirunelveli District
As per eligibility criteria of the Technical bid
4 documents required · 4 mandatory
₹0
₹1.4 L
DRDA ,Tirunelveli
12 Jul 2023
29 Apr 2023
15 May 2023
29 Apr 2023
15 May 2023
9 May 2023
8 May 2023
Amount
Clearing andGrubbing road landing uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300mm,removal of the stumps such trees cut earlier and disposal of unserviceable materials and stacking of servicable materialsto be used or auctioned,upto lead of 1000m including and disposal of top organic soil not exceeding 150mm thicknes as per Technical specification Claus 201,(i) (A) -Scrub Jungle Clearance
Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structure graded and compacted to to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 301.5. (Gravel shoulder)
Advance patch work for making up the undulation in the existing B.T surface to an average thickness of of 50mm using 45mm IRC size HBG metal
Providing and laying Tack coat over BT surface using 3Kg of bitumen Emulsion for 10sqm area including cost and conveyance of bituminous binder including labour charges for preparing the surface and applying the required quantity of bitumen as tack coat
Providing and laying Bituminious concrete to 25mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Providing and laying of hot applied thermoplastic compound 2.50mm thick including refletorising glass beads @ 250 gms per sqm area, thickness of 2.5mm is exclusive of surface applied glass beads as per IRC:35, The finished surface to be level uniform and free from streaks and holes etc., complete as per MORTH&H specification No.803.
Providing and fixing Name Board cum citizen board
Providing and erecting of Retro - Refectories cautionary, Mandatory and Informatory signs (with definition board) made out of High intensity Prismatic grade sheeting confirming to type – IV standards of IRC – 67 2012 and ASTM D 4956-09, specification and fixed over 2mm thick aluminum sheet fixed over a back supporting frame of 25mm x 25mm 3mm mild steel angle and supported on a mild steel angle post 75x756mm with a clear height of not less than 2.10m from the ground level to the bottom of the sign board and 0.60m below ground level. The sign post should be painted as per IRC 67-2012 and firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 45cmx45cmx60cm size including cost and conveyance of all materials, equipment, machinery and labour with all leads and lifts, loading charges necessary for satisfactory completion of the work as directed by the engineer in charge. High intensity Retro – Reflector sheet shall consist of minimum coefficient of Retro reflection as per table 6.6 of IRC 67-2012. The Retro – reflective sheeting shall be covered under 7 years warranty issued for field performance and a certified copy of three years outdoor exposure report shall be obtained as per IRC 67:2012 (as per Morth&H specification No.801)
60Cm Equilateral Triangle (Cautinary) Sign board
Providing and fixing of retro – refectoriesed cautionary star sign made out of high intensity prismatic grade reflective sheeting sticked over CR sheet 0.20 mm / 32 G thickness with black enamel paint firmly fixed on the trees with 1 ½” x 14G wire nails of size 100mm x 100 mm
Reflector
Provision for Hectametre Stone
Provision for KM Stone
Construction of Deck Slab Culvert 3.00m Span @ CH 4310
Earth work excavation in all clauses of soil with initial lead and lift except hard rock requiring blasting as per SS 20B for foundation etc., complete.
For foundation
Cement concrete 1:4:8 mix using 40m ISS HBG metal including cost and conveyance of all materials and all labour charges etc., complete.
Centering charges for all concrete works including all cost and conveyance of all materials and all labour charges etc., complete.
For Shuttering - Below Sill Level
For Shuttering - Above Sill Level
For Deck Slab Centering
Cement concrete 1:3:6 mix using 40mm ISS HBG metal including all cost and conveyance and all labour charges etc., complete.
Cement concrete 1:1.5:3 mix using 20mm ISS HBG metal including all cost and conveyance and all labour charges etc., complete.
Supplying, Fabricating and placing in position of MS steel or Ribbed Tor Steel for all Reinforced Cement Concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with standard specification.
Cement concrete 1:2:4 mix using 20mm ISS HBG metal including all cost and conveyance and all labour charges etc., complete.
Supplying and filling with excavated earth including all cost and conveyance and all labour charges for watering, ramming etc., complete.
Tarpad arrangements as expansion joints
Weep holes arrangements using PVC pipe 63mm dia
Maintenance Towards the charges for routline maintenance of the road work executed under MGSMT including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRC-SP-20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost
For the First Year from the date of completion of work
For the Second Year from the date of cpmpletion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
M MOHAMMED HAKKIM
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .