| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹1.9 LAdmitted-Finance | L1 | Admitted-Finance | ||
| 2 | L2₹2.0 L+₹1,967.05 (1.01%)Admitted-Finance | L2 | Admitted-Finance | ||
| 3 | L2₹2.0 L+₹1,967.05 (1.01%)Admitted-Finance | L2 | Admitted-Finance |
Tender Value
₹2.0 L
EMD Value
₹3,920
Closing Date
11 Aug 2026, 6:00 pmClosed
XEN REW JAMMU
XEN REW JAMMU
Construction of Boundary Wall at Peer Baba Lower Orak W.no. 7 Pyt. Keri Block Mathwar Under scheme PRIS Component District Capex Budget For the Year 2026-27 (PYT LEVEL)
2026_RDPR_318232_9
e-NIT No. 289 REWJ of 2026-27 dated 28-07-2026
Open Tender
Civil Works
Percentage
30 days
JAMMU
Please refer Tender documents.
2 documents required · 2 mandatory
₹500
MH0515
₹3,920
7 Sept 2026
28 Jul 2026
12 Aug 2026
28 Jul 2026
11 Aug 2026
28 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (hydraulic excavator) in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed, within a lead of 50 metres: All kinds of soil : | 11 | cum | 256.85 | ₹2,825.35 |
| 2 | Providing and laying in position cement concrete (1:5:10) 1 cement:5fine sand:10 graded crushed stone aggregates 40mm size.excludingthe cost of centring and shuttering all work upto plinth Level | 0.9 | cum | 4,826.5 | ₹4,343.85 |
| 3 | Providing and laying in position of cement concrete of specified grade excluding the cost of centring and shuttering - all work upto plinth level. 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregates 20mm nominal size) | 8.9 | cum | 5,733.6 | ₹51,029.04 |
| 4 | Supply and Dumping stone including cost of stones in Horizontal on level. | 3.8 | cum | 700 | ₹2,660 |
| 5 | Brick work with brick of class designation 75 in foundation and plinth in cement mortar 1:6 mix. | 8.5 | cum | 7,571.55 | ₹64,358.18 |
| 6 | Extra for brick work with common burnt clay bricks/cement concrete bricks in superstructure above plinth level upto floor five level | 8.5 | cum | 1,455.65 | ₹12,373.03 |
| 7 | Centering and shuttering including strutting, propping etc. and removal of form work for: Foundation and footings etc | 18.59 | sqm | 286.35 | ₹5,323.25 |
| 8 | 12mm Cement plaster of mix: 1 : 6 ( 1 cement : 6 fine sand) | 74 | sqm | 266.2 | ₹19,698.8 |
| 9 | White washing with lime to give an even shade on New Work (three or
more coats) | 74 | sqm | 98.75 | ₹7,307.5 |
| 10 | Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. 10.25.2 In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works. | 80 | Kg | 181.6 | ₹14,528 |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.35 MB
BOQ_1047366.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .