| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹1.8 LAdmitted-Finance | -35.51% | ₹1.8 L | L1 | Admitted-Finance |
| 2 | L2₹2.3 LAdmitted-Finance 1849 JUGRAJPUR SACHENDI KANPUR KANPUR NAGAR UTTAR PRADESH 208023 UDYAM UP 43 0012110 | KANPUR NAGAR | UTTAR PRADESH | 208023 | -15.00% | ₹2.3 L | L2 | Admitted-Finance |
| 3 | L3₹2.7 LAdmitted-Finance | -1.51% | ₹2.7 L | L3 | Admitted-Finance |
Tender Value
₹25 L
EMD Value
₹50,000
Closing Date
6 Apr 2026, 6:00 pmClosed
Commissioner,
Nagar Nigam Bikaner.
ARC for naala, naali, cross, cover, sewerage repair etc at various places of ward No. 31, 51, 53, 56, 63, 64, 65, 66 Bikaner.
2026_DLB_548959_1
E-NIT No. 209/2025-26/Nirman arc w3151
Open Tender
Civil Works
365 days
Bikaner
as per tender
2 documents required · 2 mandatory
₹1,000
Commissioner, Nagar Nigam Bikaner.
₹50,000
Yes
20 Apr 2026
28 Mar 2026
7 Apr 2026
28 Mar 2026
6 Apr 2026
28 Mar 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Earth work in excavation in foundation, trenches etc. including dressing of sides and ramming of bottoms, including getting out the excavated material, refilling after laying pipe/ foundation and disposal of surplus excavated material at a lead upto 50m suitable site as per direction of Engineer for following depths, below natural ground / Road top level. In all types soils/ saturated soil such as moorum, sand, sandy silt, clay, black cotton soil, kankar, etc. | |||||
| 2Earth work in excavation for roadway, including trimming bottom and side slopes in accordance with requirement of line, grades and cross sections, including disposal of surplus material with all lift and lead upto 1000 metre as per MoRT&H specification clause 301. In all type of soil | |||||
| 3Dismantling of flexible pavements and disposal of dismantled materials up to a lead of 50 metres as directed by Engineer. Granular Course | |||||
| 4Bituminous Courses | |||||
| 5Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-incharge. In cement Mortar | |||||
| 6Dismantling old plaster or skirting raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 50 metres lead. | |||||
| 7Construction of embankment with approved material obtained from borrow pit with all lifts and leads, transporting to site, spreading, grading to required slope and compacting by vibratory roller 8-10 tonne to meet requirement of table 300-2 including cost of compensation for earth taken from private land complete as per MoRT&H specification clause 305. (Lead taken upto 5 km) | |||||
| 8Dismantling of existing structures like culverts, bridges, retaining walls, CC road and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 50 metres as directed by Engineer. | |||||
| 9Lime Concrete, cement concrete grade M-10 (1:5:10) and below | |||||
| 10Earth work for Sewer line and Manhole in excavation in foundation, trenches manholes, road side chambers etc. including dressing of sides and ramming of bottoms, including getting out the excavated material, refilling after laying pipe/ foundation and disposal of surplus excavated material at a lead upto 50m suitable site as per direction of Engineer for following depths, below natural ground / Road top level including allowances for any additional excavation beyond the drawings (measurement for payment to be as per standard drawings), re-handling of material/earth to complete the task. In all types soils/ saturated soil such as moorum, sand, sandy silt, clay, black cotton soil, kankar, etc. Depth up to 1.5 m | |||||
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 5.03 MB
nit209nallaARC3151636466.pdf
Tender Documents • 5.02 MB
BOQ_978617.xls
BOQ • 0.41 MB
Download all tender documents and submit your bid