| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.4 LAccepted-AOC AT BALU BANKER COLONY PO DHORI BERMO DIST BOKARO JHARKHAND | BOKARO | JHARKHAND | 825102 | L1 | Accepted-AOC awarded | |
| 2 | Rejected-Technical AT KARGALI BAZAR PO BERMO DIST BOKARO PIN 829104 | BERMO | BOKARO | JHARKHAND | 829104 | - | Rejected-Technical not evaluated | |
| 3 | Rejected-Technical 00 KIWADI SAFEDABAD BARABANKI BARABANKI UTTAR PRADESH 225001 | BARABANKI | UTTAR PRADESH | 225001 | - | Rejected-Technical not evaluated |
Tender Value
₹3.5 L
EMD Value
₹4,400
Closing Date
29 Feb 2024, 10:00 amClosed
PE EnM AADOCM
PE EnM AADOCM
A. Erection of 220 volt OH line for illumination of newly built parking area in respect of AADOCM, Dhori Area. B. Diversion and Erection of 220V OH line near 9 no. and 11 no. coal stock area for proper lighting around the stock w.r.t. AADOCM.
2024_CCL_302393_4
AADOCM/EnM/2023-24/23
Open Tender
Electrical and Maintenance Works
Item Rate
12 days
AADOCM
Please refer Tender documents.
2 documents required · 2 mandatory
₹4,400
9 Apr 2024
23 Feb 2024
1 Mar 2024
24 Feb 2024
29 Feb 2024
24 Feb 2024
24 Feb 2024 - 27 Feb 2024
Amount
Part A (enter zero for this row)
Erection of steel tubular pole of length exceeding 10 mtrs but not exceeding 12 mtr in cement concrete 1:3:6 (1 cement :3 coarse sand :6 graded stone aggregate 40 mm nominal size ) foundation including excavation and refilling etc as required.
Erection of ACSR conductor of 7/3.35 mm to 7/4.0 diameter and above including binding etc as required 7 span x 50 m x 2 wire = 0.7 km x 214 kg/ km = 149.80 kg
Supplying and erection of Stay set complete ( glavnised ) with 19/20 mm dia x 1.8 mtr long stay rod , anchor plate of size 45 cm x 7.5mm, thimble, stay clamps,turn buckle ( 20mm x 60 cm ) 7/3.15 mm dia GI stay wire and strain insulator etc in cement concrete 1:3:6 (1 cement :3 coarse sand :6 graded stone aggregate 40 mm nominal size ) foundation including excavation and refilling etc as required.
Supply of channel 75 mm x 40 mm x 6 mm 7.14 kg / mtr cross arm for 2 wire OH Line complete with clamps bolts and nuts etc including drilling of holes of insulators pins and painting with primer and finish paint as required.
Supply of channel 75 mm x 40 mm x 7.14 kg / mtr cross arm for 4 wire OH Line complete with clamps bolts and nuts etc including drilling of holes of insulators pins and painting with primer and finish paint as required
Supply and erection of 220V grade shackle insulators 100 mm x 110 mm with GI bolts and nuts strap setc as required
Supplying and erection of 220V grade 100 x 80 mm Pin insulator complete with GI spindle and nuts etc. as required.
Supply of 8 SWG GI wire for cradling. Cradling 120 m x 3 wire = 360 mtr x 0.131 kg/mtr = 47.16 kg + lacing 40 nos x 3 span = 120 nos x 3 mtr = 360 mtr x 0.131 kg/mtr = 44.80 kg, Total = 139.12 kg
Erection of cradle guard 3 span x 40 nos = 120 nos
Erection of cross arm on single pole
Transporting of pole from store to working site.
Supply and fixing of 32 mm dia x 2 mtr long GI pipe ( medium class 0 bracket for mounting of street light / LED with bending the pipe to the required shape, 2 nos 40 mm x 3 mm flat iron clamps with nuts, bolts and washers, painting and finish paint etc as required.
Supplying and drawing of 2 x 2.5 sqmm size of FRLS PVC insulated copper conductor, single core cable on existing surface/ recessed steel / PVC conduit as required.
Fitting and fixing of LED light fittings on pole
Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth upto 30 cm measured at a height of 1m above ground level and removal of rubbish upto a distance of 50 m outside the periphery of the area cleared.
Applying priming coat : With ready mixed red oxide zinc chromate primer of approved brand and manufacture on steel galvanized iron With ready mixed red oxide zinc chromate primer of approved brand and manufacture on steel work (second coat)/steel works.
Painting of pole with cross arm from aluminium paint of approved brand and manufacture to give an even shade.
Part B (enter zero for this row)
Erection of steel pole tubular or rail pole strut concrete 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 40 mm nominal size) foundation including excavation and re-filling and secured with holding clamps, bolts, nuts, etc. as required.
Erection of all aluminium conductor of 7/1.96mm to 7/3.10 diameter and above including binding etc. as required. 13 span x 40 x 2 wire = 1040 mtrs. x 0.214 = 222.56 Kgs.
Supplying and erection of stay set complete (galvanised) with 19/20 mm dia x 1.8 metres long stay rod, anchor plate of size 45 cm x 45 cm x 7.5 mm, thimble, stay clamps, turn buckle (20 mm x 60 cm), 7/3.15 mm dia G.I. stay wire and strain wire and strain insulator etc in cement concrete 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 40 mm nominal size) foundation including excavation and refilling etc. as required.
Supplying and erection of 100 mm x 80 mm pin insulator complete with G.I. spindle and nuts etc. as required.
Supplying and erection of galvanised ‘D’ iron clamps complete with shackle insulator (100 mm x 110 mm), G.I. bolts, nuts and washers, coach screw etc. as required.
Supply of 6 SWG G.I. wire (4.00mm dia) 8 span x 40 x 3 wire = 960 mtr. x 0.132 = 126.72 Kgs.
Erection of G.I. wire no. 8 SWG including binding etc. as required.
Supplying of channel iron 75 mm x 40 mm x 6 mm (7.14 kg per metre) cross arm for 4 wire over head line complete with clamps, bolts, nuts and washer etc including drilling of holes for insulator pins etc (as per drawing) and painting with primer and finished paint as required.
Supplying of channel iron 75 mm x 40 mm x 6 mm (7.14 kg per metre) cross arm for 2 wire over head line complete with clamps, bolts, nuts and washer etc including drilling of holes for insulator pins etc (as per drawing) and painting with and finished paint as required.
Erection of angle iron/ channel iron cross arm on wood/RCC/PCC/ steel tubular/ rail pole etc. as required.
Transportation of pole tubular pole/rail pole.
Dismantling of overhead lines comprising of copper/aluminium overhead conductor, G.I. wire cross arms, insulators etc. as required.
Fitting and fixing light on the pole.
Dismantling of light.
Total impact of GST for the purpose of CTC
M/S KUMAR ENTERPRISES
M/S A N TRADERS
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .