EO, Paradeep Municipality
Paradeep Municipality
Construction of CC road and drain slab at badapadia Vegetable Market, Badapadia in ward no 15
2026_ORULB_140912_1
EO/ PDPM/ W_08/ 2026-27
Open Tender
Civil Works - Others
Percentage
90 days
Paradeep Municipality
Please refer Tender documents.
2 documents required · 2 mandatory
₹6,000
₹26,325
Yes
14 Sept 2026
14 Sept 2026
25 Sept 2026
14 Sept 2026
24 Sept 2026
14 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| - | Earth work in ordinary soil within 50 m initial lead and 1.5m initial lift including rough dressing and bracking clods to maximum 5cm to 7cm and laying in layers to not exceeding 0.3m in depth and as per direction of the department. 08 | 10.41 | %cum | 17,543.3 | ₹1,82,625.75 |
| - | Providing spreading, filling in foundation and plinth with sand watered and rammed as per OPWD specification including cost of materials, labour, conveyance, royalty, Tools and Plants etc.all complete required for the work to finished items of work. 18 | 225.8 | cum | 1,107.75 | ₹2,50,129.95 |
| - | PCC (1:3:6) with 40 mm size HG metal including all cost of materials, labour, conveyance, royalty, T&P, water for curing etc all complete. 37 | 114.63 | cum | 7,064.79 | ₹8,09,836.88 |
| - | PCC/ RCC (1:2:4) with 12 mm size CBHGC including hosting and laying all cost of materials, labour, conveyance, royalty, Tools and Plants water for curing etc.all complete. 54 | 160 | cum | 8,682.41 | ₹13,89,185.6 |
| - | RCC work of M20 grade with 20 mm and down grade CBHGC including hosting and laying all cost of materials, labour, conveyance, royalty, T & P, water for curing etc.all complete. 57 | 10.5 | cum | 7,147.62 | ₹75,050.01 |
| - | Requirement of HYSD/ MS rod and labour for cutting, bending,binding, straighting and laying the grills and placing in position including cost of rod & binding weir 18 to 20 gauge. 62 | 7.35 | qtl | 8,543.93 | ₹62,797.89 |
| - | Rigid and smooth centering and shuttering for PCC/ RCC works including false works and dismantling them after casting including cost of materials complete in ground floor. 64
RCC foundation, plinth band and footings bases of columns mass concrete pre-cast slabs etc. 67 | 166.7 | sqm | 249.73 | ₹41,629.99 |
| 8 | Cost of Primer,Paint,Painting & Letter writing over Disply board 303 | 1 | no | 2,000 | ₹2,000 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.41 MB
BOQ_609549.xls
BOQ • 0.32 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .