Loading…
Loading…
Tender Value
₹11.0 L
EMD Value
₹11,100
Closing Date
17 Jul 2026, 5:00 pm7d left
Executive Engineer
RURAL WORKS DIVISION, MOHANA
PWD road to Bithala_Road_WBM at stretches,PMC,SC,Jungle clearance, clearance of vents of CD works _0.000 to 0.750
2026_CERWI_134743_1
03/MOHANA/2026-27
National Competitive Bid
Civil Works - Roads
60 days
Mohana
2 documents required · 2 mandatory
₹6,000
₹11,100
Yes
8 Jul 2026
8 Jul 2026
18 Jul 2026
8 Jul 2026
17 Jul 2026
8 Jul 2026
8 Jul 2026 - 14 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Road Work
Clearing and grubbing road land including uprooting wild vegetations, grass, bushes, shurbs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable materials to be used etc. complete including cost. , conveyance, royalty, Cess & taxes of all materials & cost of all labour & T&P required for the work etc complete as per specification & direction of Engineer-in Charge. | 2,160 | Sqm | 8.63 | ₹18,640.8 |
| 2 | Construction of embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site by mechanical means within a lead of 5kms, spreading, grading to required slope and compacting to meet requirement of table 300-2 & Clause 305 of MoSRT&H specifications for Road and Bridge works (4th Revision) with cost of all labour, T&P and with cess, royality and as per direction of Engineer-in-charge. | 236.7 | Cum | 271.82 | ₹64,339.79 |
| 3 | Clearing the existing black topped surface with removal of foreign materials with brooms or soft brushed and finally dusting with old gunny bags and /or compressed air to receive bituminous including all labour, T&P, Cess articles required for the work etc complete as per direction of Engineer-in-charge. | 64.8 | Sqm | 5.59 | ₹362.23 |
| 4 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam IRC Grade-III (53mm to 22.4mm) specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density as per Technical Specification Clause 404 of MoRD by manual means including all labour, T&P and cost, conveyance, royality, DMF (10% over Royality), EMF (5% over Royality), Addl Charges, Cess & taxes of all materials required for the work complete in all respect as per direction of the Engineer-in-Charge. | 12.96 | Cum | 3,736.76 | ₹48,428.41 |
| 5 | Providing & applying primer coat with Bitumen Emulsion (SS-1) using emulsion distributor @ 4 Kg per 10 Sqm on the prepared granular surface treated with primer and cleaned with mechnial broom as per technical specification Clause 503 of MoRD & as per direction of Engineer-in-Charge. | 172.8 | sqm | 43.02 | ₹7,433.86 |
| 6 | Providing & applying tack coat with Bitumen Emulsion (RS-1) using emulsion distributor @ 3 Kg per 10 Sqm on the prepared granular surface treated with primer and cleaned with mechnial broom as per technical specification Clause 503 of MoRD & as per direction of Engineer-in-Charge. | 172.8 | sqm | 35.1 | ₹6,065.28 |
| 7 | Providing & applying tack coat with Bitumen Emulsion (RS-1) using emulsion distributor @ 2 Kg per 10 Sqm on the bituminous surface and cleaned with mechnial broom as per technical specification Clause 503 of MoRD & as per direction of Engineer-in-Charge. | 1,987.2 | Sqm | 27.2 | ₹54,051.84 |
| 8 | Providing and laying semi dense bituminous concrete with batch type hot mix plant using crushed aggregates of speficied grading premixed with bituminous binder of 60/70 penetration grade of bitumen , transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheelede, vibratory and tandem rollers to achieve the desired compaction as per clause 508 of MoSRT&H specification for Road & Bridge works and all other T&P articles including cost, conveyance, royality, DMF (10% over Royality), EMF (5% over Royality), Addl Charges, Cess, taxes of chips and bitumen & other required materials etc. complete as per specification and direction of the Engineer in charge. | 54 | cum | 14,377.48 | ₹7,76,383.92 |
| 9 | Providing and fixing 15 cm dia and 1 m long guard post of RCC (1:2:4) including cost, conveyance royality, Cess, taxes of all materials, labour, T&P required for the work etc. complete as per specification and direction of the Engineer in charge. | 44 | No | 949.96 | ₹41,798.24 |
| 10 | Maintenance of Hume pipe Culvert by way of Clearing, Cleaning, Erosion repair, repairs to cracks, parapet wall and protection work as per drawing and technical specification Clause 1908 | 2 | No | 1,771.29 | ₹3,542.58 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_3.pdf
PDF • 0.91 MB
Tendernotice_2.pdf
PDF • 1.07 MB
Tendernotice_1.pdf
PDF • 1.08 MB
BOQ_600154.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid