| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹11.6 LAccepted-AOC | ₹11.6 L Quoted ₹11.7 L | L1 | Accepted-AOC L1 |
| 2 | L2₹12.4 LRejected-AOC | ₹12.4 L | L2 | Rejected-AOC L2 |
| Sl No | Description | Qty | Unit | DURAIMANI ENGINEERING CONTRACTOR | SMU ENTERPRISES |
|---|---|---|---|---|---|
| 1.00 | Charges for transportation of required size M.S plate, MS angle, I beams fabrication, erection and welding of guard plate for neck bolts, providing cliff plates and angles at four corners for strengthening the bunker and extra supports with I beams to avoid bulging including charges for transporting cost of consumables like cutting gas, welding electrodes and hire charges for T&Ps. | 1.3 | Tons | 1,49,500 ₹1.8 L | 1,42,612.6 ₹1.7 L |
| 2.00 | Charges for providing required scaffolding and temporary platform on both sides inside the bunker and outside the bunker at the elevation of 19 EL to 30 EL for providing neck bolts, providing & welding the guard plate, providing cliff plates, angle & welding, providing corner angles & welding and providing extra supports with I beam and dismantling after completion of work including charges for T&Ps hire charges for scaffolding, temporary platform and cost of consumables. | 4 | Nos | 3,72,000 ₹4.4 L | 3,57,852 ₹4.2 L |
| 3.00 | Charges for pushing the east, west, south & north sides bunker portion walls closer enough by providing clamps, hooks and pushing by hydraulic jack, cutting and removing of damaged portion of the bunker plates, angles etc, | 4 | Nos | 5,12,000 ₹6.0 L | 4,81,632 ₹5.7 L |
| 4.00 | Charges for painting of bunker with one coat of red oxide primer and two coat of gray enamel paint including cost of paint & consumables. | 250 | SqM | 57,500 ₹67,850 | 53,750 ₹63,425 |
| 5.00 | Cost of materials Contractors Scope: 12 mm Thick MS Plate | 0.59 | Tons | 44,327.5 ₹52,306.45 | 43,044.09 ₹50,792.03 |
| 6.00 | Cost of materials Contractors Scope : MS Angle 100 x 100 x 8mm | 0.3 | Tons | 13,635 ₹16,089.30 | 12,037.28 ₹14,203.99 |
| 7.00 | Cost of materials Contractors Scope : I Beam 150 x 75 | 390 | Kg | 23,010 ₹27,151.80 | 22,101.3 ₹26,079.53 |
| 8.00 | Cost of materials Contractors Scope : HT Bolt M 30 x 120 mm, with 1 No. Nut & 1 No washer. | 214 | Nos | 70,620 ₹83,331.60 | 53,654.08 ₹63,311.81 |
Tender Value
Refer Docs
EMD Value
₹10,400
Closing Date
19 Feb 2026, 2:00 pmClosed
CE/TTPS
O/o CE/TTPS
TTPS Operation Circle MPM I Unit II Strengthening of mill 2A bunker by renewal of eroded neck bolts, provision of guard plate for bolts inside the bunker, renewal of corroded corner angles, provision of clip plates, provision of side wall support on
2026_EB_656574_1
CE/SE/O/TTPS/Spec.No.298/25-26
Open Tender
Miscellaneous Works
30 days
TTPS
Please refer Tender documents.
5 documents required · 5 mandatory
₹0
₹10,400
Yes
25 Mar 2026
14 Feb 2026
20 Feb 2026
14 Feb 2026
19 Feb 2026
14 Feb 2026
Charges for transportation of required size M.S plate, MS angle, I beams fabrication, erection and welding of guard plate for neck bolts, providing cliff plates and angles at four corners for strengthening the bunker and extra supports with I beams to avoid bulging including charges for transporting cost of consumables like cutting gas, welding electrodes and hire charges for T&Ps.
Charges for providing required scaffolding and temporary platform on both sides inside the bunker and outside the bunker at the elevation of 19 EL to 30 EL for providing neck bolts, providing & welding the guard plate, providing cliff plates, angle & welding, providing corner angles & welding and providing extra supports with I beam and dismantling after completion of work including charges for T&Ps hire charges for scaffolding, temporary platform and cost of consumables.
Charges for pushing the east, west, south & north sides bunker portion walls closer enough by providing clamps, hooks and pushing by hydraulic jack, cutting and removing of damaged portion of the bunker plates, angles etc,
Charges for painting of bunker with one coat of red oxide primer and two coat of gray enamel paint including cost of paint & consumables.
Cost of materials Contractors Scope: 12 mm Thick MS Plate
Cost of materials Contractors Scope : MS Angle 100 x 100 x 8mm
Cost of materials Contractors Scope : I Beam 150 x 75
Cost of materials Contractors Scope : HT Bolt M 30 x 120 mm, with 1 No. Nut & 1 No washer.
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.25 MB
BOQ_787369.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid