Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹16.8 LAccepted-AOC | ₹16.8 L Quoted ₹17.3 L | 1 | Accepted-AOC AOC |
| 2 | 2₹18.0 LRejected-Finance | ₹18.0 L | 2 | Rejected-Finance Being other than L-1 |
| Sl No | Description | Qty | Unit | Balaji Associate L2 | M/s S.M. Construction L1 |
|---|---|---|---|---|---|
| 1.00 | Collecting and carryout samples for testing of treated water of STP, from NABL approved laboratory with following parameters and submission of detailed test report to the Engineering -in-charge.(a) Carrying out minimum essential testing of water as per IS 10500 of 1991 mandatory for chemicals colour, odour, PH valve, TSS TDS, COLOUR,BOD,COD, total residual chlorine, total nitrogen (NH3-N), SO4, OIL GREASE, CHU, ODOUR, E.COIL, FECAL COLIFORM, TOTAL PHOSPHOROUS. Note :- (i)Rate quoted shall deemed to be included cost of sterilized bottle as reqd.
(ii) Transportation charge for collection of sample.
(iii) Completion certificate will be issued only after production of performance test certificate from NABL or any Govt approved agency. | 22 | Each Job | 3,400 ₹74,800 | 4,500 ₹99,000 |
| 2.00 | Material and labour for cleaning of sewage and removing of settled down sewage sludge cum mud/de-silting etc at 900 KLD STP for equalisation tank complete all as specified and directed. | 2 | Each Job | 24,000 ₹48,000 | 20,000 ₹40,000 |
| 3.00 | Material & Labour for dewatering, desludging and cleaning of wet and dry sewage from followng sumps (outer and inner) of well up to bottom of sumps by any method (manually or mechanically) by closing of all inlets of sumps and pumping out from near by manholes and opening all inlets after necessary cleaning works of sump well including flushing out the inlet pipes by suction of the pump sets installed sludge disposed of out of defence land (AF Station Complex) complete all as specified and directed for the following sumps:-
(a)Sewage well No 1 sinking dia 7.29 Mtr and depth 6.70 mtr approx below ground level | 1 | Each Job | 25,000 ₹25,000 | 30,000 ₹30,000 |
| 3.01 | (b) Sewage well No 2 & 3 sinking dia 10.75 Mtr and depth 7.30 mtr approx below ground level | 2 | Each Job | 25,000 ₹50,000 | 25,000 ₹50,000 |
| 3.02 | (c)Sewage well No 9 & 10 sinking dia 10.75 Mtr and depth 7.30 mtr approx below ground level | 2 | Each Job | 25,000 ₹50,000 | 25,000 ₹50,000 |
| 3.03 | (d) Sewage well No 4 & 5 sinking dia 6.70 Mtr and depth 7.30 mtr approx below ground level | 2 | Each Job | 22,000 ₹44,000 | 20,000 ₹40,000 |
| 3.04 | (e) Sewage well No 6 & 7 sinking dia 6.00 Mtr and depth 6.50 mtr approx below ground level | 2 | Each Job | 21,000 ₹42,000 | 20,000 ₹40,000 |
| 4.00 | Labour for dismantling, disconnecting the Air Blower including from channel frame and electrical panel for repair of Gear Box, refitting of gear box after toping up oiling, greasing, alignment of pump set and re-fixing/ assembling testing to make it functional complete including cleaning of all dirt, dust and including transportation to civil workshop for repair work and back to working site etc. complete all as specified and directed.
Note:- Worn out spares shall be replaced with existing make and measured and paid separately as under:- | 2 | Each Job | 8,500 ₹17,000 | 20,000 ₹40,000 |
| 4.01 | Supply of Pulley V Belt SPB-1800 | 2 | Each | 1,000 ₹2,000 | 500 ₹1,000 |
| 4.02 | Supply of Suction air filter | 2 | Each | 1,000 ₹2,000 | 500 ₹1,000 |
Updated dates
Tender Value
₹25 L
EMD Value
₹50,000
Closing Date
25 Apr 2026, 6:00 pmClosed
GE AF Adm Area Agra
GE (AF) Adm Area Agra UP 282008
ANNUAL MAINT CONTRACT OF STP AND SEWAGE NETWORK WORKS UNDER GE (AF) ADM AREA AGRA AT AF STN AGRA
2026_MES_757345_1
8000-2331/E8
Open Tender
Electrical and Maintenance Works
GE AF Adm Area Agra
Please refer Tender documents.
4 documents required · 4 mandatory
₹500
GE (AF) Adm Area Agra
₹50,000
24 Jun 2026
23 Mar 2026
27 Apr 2026
23 Mar 2026
25 Apr 2026
6 Apr 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
Collecting and carryout samples for testing of treated water of STP, from NABL approved laboratory with following parameters and submission of detailed test report to the Engineering -in-charge.(a) Carrying out minimum essential testing of water as per IS 10500 of 1991 mandatory for chemicals colour, odour, PH valve, TSS TDS, COLOUR,BOD,COD, total residual chlorine, total nitrogen (NH3-N), SO4, OIL GREASE, CHU, ODOUR, E.COIL, FECAL COLIFORM, TOTAL PHOSPHOROUS. Note :- (i)Rate quoted shall deemed to be included cost of sterilized bottle as reqd.
(ii) Transportation charge for collection of sample.
(iii) Completion certificate will be issued only after production of performance test certificate from NABL or any Govt approved agency. | - | Each Job | - | - | |
Material and labour for cleaning of sewage and removing of settled down sewage sludge cum mud/de-silting etc at 900 KLD STP for equalisation tank complete all as specified and directed. | - | Each Job | - | - | |
Material & Labour for dewatering, desludging and cleaning of wet and dry sewage from followng sumps (outer and inner) of well up to bottom of sumps by any method (manually or mechanically) by closing of all inlets of sumps and pumping out from near by manholes and opening all inlets after necessary cleaning works of sump well including flushing out the inlet pipes by suction of the pump sets installed sludge disposed of out of defence land (AF Station Complex) complete all as specified and directed for the following sumps:-
(a)Sewage well No 1 sinking dia 7.29 Mtr and depth 6.70 mtr approx below ground level | - | Each Job | - | - | |
(b) Sewage well No 2 & 3 sinking dia 10.75 Mtr and depth 7.30 mtr approx below ground level | - | Each Job | - | - | |
(c)Sewage well No 9 & 10 sinking dia 10.75 Mtr and depth 7.30 mtr approx below ground level | - | Each Job | - | - | |
(d) Sewage well No 4 & 5 sinking dia 6.70 Mtr and depth 7.30 mtr approx below ground level | - | Each Job | - | - | |
(e) Sewage well No 6 & 7 sinking dia 6.00 Mtr and depth 6.50 mtr approx below ground level | - | Each Job | - | - | |
Labour for dismantling, disconnecting the Air Blower including from channel frame and electrical panel for repair of Gear Box, refitting of gear box after toping up oiling, greasing, alignment of pump set and re-fixing/ assembling testing to make it functional complete including cleaning of all dirt, dust and including transportation to civil workshop for repair work and back to working site etc. complete all as specified and directed.
Note:- Worn out spares shall be replaced with existing make and measured and paid separately as under:- | - | Each Job | - | - | |
Supply of Pulley V Belt SPB-1800 | - | Each | - | - | |
Supply of Suction air filter | - | Each | - | - |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.43 MB
TenderT77.pdf
Tender Documents • 1.03 MB
BOQ_848328.xls
BOQ • 1.52 MB
Download all tender documents and submit your bid