| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹12.7 CrAccepted-AOC | ₹12.7 Cr Quoted ₹13.3 Cr | L1 | Accepted-AOC Bond No. 269/SE
Bond date 23.01.2024 |
| 2 | L2₹13.3 CrRejected-Finance GRAM AND POST MAJHARA THANA WAZIRGANJ DISTRICT GONDA UTTAR PRADESH | MAJHARA | GONDA | UTTAR PRADESH | ₹13.3 Cr | L2 | Rejected-Finance Not Lowest |
| 3 | L3₹14.2 CrRejected-Finance | ₹14.2 Cr | L3 | Rejected-Finance Not Lowest |
Tender Value
₹18 Cr
EMD Value
₹30 L
Closing Date
14 Dec 2023, 12:00 pmClosed
Superintending Engineer Deoria Circle, PWD Deoria.
Office of The Superintending Engineer Deoria Circle, PWD Deoria.
Widening and Strengthening of remaining portion of Padrauna Mansachapar Balkudiya Pipra link road under scheme RSN in dist Kushinagar in FY 2023-24
2023_CEGKP_864771_1
3942/76Yat-Deo Circle/2023 Date 17.11.2023
Open Tender
Civil Works
180 days
Kushinagar
Please refer Tender documents.
3 documents required · 3 mandatory
₹2,950
₹30 L
Superintending Engineer Deoria Circle, PWD Deoria.
24 Feb 2024
2 Dec 2023
14 Dec 2023
2 Dec 2023
14 Dec 2023
2 Dec 2023
11 Dec 2023
Amount
Clearing and grubbing road land including uprooting rank vegetation, grass, bushes,shrubs, saplings and trees. girth upto 300mm removal of stumps of trees cut earlier and disposal of unseviceble materials and stacking of serviceable material to be used of auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150mm in thickness.
Excavation in Soil using Hydraulic Excavator CK 90 and Tippers with Disposal upto 1000 metres.Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m
Construction of Embankment with Material obtained from Borrowpits -Construction of embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2.(Carted Upto 6.0 km)
GSB :- Construction of granular sub-base by providing Close graded material, mixing in a mechanical mix plant at OMC, carriage of mixed material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete As perSr No. 4.1 & MoRT&H Specification Ref. No. 401(B) (GST will be paid extra as applicable) including labour cess.
WMM :- Providing, laying, spreading and compacting stone aggregates from approved quarry to Wet Mix macadam specification including premixing the material with water at OMC in machanical mix plant,, carriage of mixed material by tipper to site laying in uniform layer with paver in sub basae/base course on well prepared surface and compacting with vibratory roller to achieve the desired density. as per MORTH specification 406. (GST will be paid extra as applicable) including labour cess.
Construction of un-reinforced, dowel jointed, plain cement concrete pavement over a prepared sub base with 43 grade cement @ 400 kg per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing compound, finishing to lines and grades as per drawing
ETA :- Providing, laying and spreading of graded stone aggregate (WMM) after mixing with water at OMC in mechanical mix plant carriage of mixed material by tipper to site. Laying with 1% OPC cement and 3.5% Emulsion in uniform single layer on sub base/subgrade and compacting with the road roller to achieve the desire density (ETA) As perSr No. 4.12 & MoRT&H Specification Ref. No. 406 (GST will be paid extra as applicable) including labour cess.
DBM :- Providing and laying dense graded bituminous macadam with 60-90 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder VG-40 @ 4.50 percent by weight of total mix and filler, fransporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects.. As per Sr No. 5.6 & MoRT&H Specification Ref. No. 507 (GST will be paid extra as applicable) including labour cess.
Tack Coat-II:- Providing and applying tack coat ( over bituminous surface) with bitumen (VG-10) using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous/granular surface cleaned with mechanical broom. As perSr No. 5.2 & MoRT&H Specification Ref. No. 503 (GST will be paid extra as applicable) including labour cess.
BC:- Providing and laying bituminous concrete with 60-90 TPH batch type hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder (VG 40) @ 5.4 percent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction As per Sr No. 5.8 & MoRT&H Specification Ref. No. 509 (GST will be paid extra as applicable) including labour cess.
Construction of sub-grade and erthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2. As perSr No. 3.18 MoRT&H Specification Ref. No. 305 (For Pateri Work) (GST will be paid extra as applicable) including labour cess. (Cartage Earth)
U-DRAIN- Excavation for Foundation in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m
Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.
R.C.C. M-20, work with cement approved coarse sand and 2 cm (3/4") gauge approved stone grit including supply of all materials, labour and T&P etc. required for proper completion of the work. Binding wire cost being included in the item. As per Clause 12.08 Case-II
Supplying, fitting and placing HYSD bar reinforcement in foundation complete as per drawing and technical specifications As per SI no 504.
Construction of minor Bridge 1X3.00m Span Excavation for Foundation in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m
Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.
Brick Masonry Work in Cement Mortar 1:3 in Foundation complete excluding Pointing and Plastering, as per Drawing and Technical Specifications.
R.C.C. M-20, work with cement approved coarse sand and 2 cm (3/4") gauge approved stone grit including supply of all materials, labour and T&P etc. required for proper completion of the work. Binding wire cost being included in the item. As per Clause 12.08 Case-II
Supplying, fitting and placing HYSD bar reinforcement in foundation complete as per drawing and technical specifications As per SI no 504.
Pointing with cement mortar(1:3) on brick work in sub structure as per technical specification As per Clause 1300 & 2200
Providing and laying of weephole in brick massaonary in abutment with 100 mm dia PVC pipe extending through the full width of the structure with slope of 1v:20 h toward drawing force complete as per drawing and technical specification ( MORTH & H - 13.8/2706&2200)
Construction of minor Bridge 1X6.00m Span Excavation for Foundation in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m
Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.
Brick Masonry Work in Cement Mortar 1:3 in Foundation complete excluding Pointing and Plastering, as per Drawing and Technical Specifications.
R.C.C. M-20, work with cement approved coarse sand and 2 cm (3/4") gauge approved stone grit including supply of all materials, labour and T&P etc. required for proper completion of the work. Binding wire cost being included in the item. As per Clause 12.08 Case-II
Supplying, fitting and placing HYSD bar reinforcement in foundation complete as per drawing and technical specifications As per SI no 504.
Pointing with cement mortar(1:3) on brick work in sub structure as per technical specification As per Clause 1300 & 2200
Providing and laying of weephole in brick massaonary in abutment with 100 mm dia PVC pipe extending through the full width of the structure with slope of 1v:20 h toward drawing force complete as per drawing and technical specification ( MORTH & H - 13.8/2706&2200)
Construction of 1000mm hume pipe Excavation for Foundation in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m
Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.
Brick Masonry Work in Cement Mortar 1:3 in Foundation complete excluding Pointing and Plastering, as per Drawing and Technical Specifications.
Providing, Laying & fixing of 1000 mm dia Hume pipe NP-3 type. As per S.I.No. 458 -2003 Sr. No. 9
Pointing with cement mortar(1:3) on brick work in sub structure as per technical specification As per Clause 1300 & 2200
Construction of 600mm hume pipe Excavation for Foundation in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m
Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.
Brick Masonry Work in Cement Mortar 1:3 in Foundation complete excluding Pointing and Plastering, as per Drawing and Technical Specifications.
Pointing with cement mortar(1:3) on brick work in sub structure as per technical specification As per Clause 1300 & 2200
Providing, Laying & fixing of 600 mm dia Hume pipe NP-3 type. As per S.I.No. 458 -2003 Sr. No. 7
Providing, Laying & fixing of collar 600 mm dia. As per S.I.No. 458 -2003 Sr. No. 7