Tender Value
₹5.8 L
EMD Value
₹5,800
Closing Date
15 Apr 2025, 3:00 pmClosed
Block Development Officer (V.Pt) Viralimalai
Block Development Office Viralimalai
Constructon of Samathuvapuram Burial ground Waiting Shed at Sokkalingapuram Village in Mathoor Panchayat
2025_RDTN_538334_1
AGAMT_25_26_Mathur_2
Open Tender
Civil Works
Item Rate
180 days
Viralimalai
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹5,800
16 Apr 2025
5 Apr 2025
15 Apr 2025
5 Apr 2025
15 Apr 2025
5 Apr 2025
Amount
Earth work excavation and depositing on bank with initial lead and lift in hard gravelly soil as per SS20 B for foundation etc complete
Cement Concrete in 1 :4:8 mix using 40 mm metal including cost and conveyance of all materials to site and labour charges etc complete
sand and filling in to the basement including cost and conveyance to the siteand all labour charges for filling as per standard speecifications
Brickwork in Cement mortar 1 : 5 mix using new II class bricks including cost and conveyance of all materials to site and labour charges etc complete.
Supplying and errecting shuttering including necessary support for plane surface in Foundation Basement and Roof slabs strutting upto 3.29 M height for plane surfaces for floors for RCC column footings columns plinth beam and connected with foundations grade beams, raft slabs stair case steps, bed blocks, critical pier, etc beams roof slabs, using mild steelsheets of size 90 x 60 cm and 10 gouge stiffened, welded with steel angles of size 25 mm x 25 mm x 3mm for boarding laid over silver oak (country wood) joists of 10 cm size x 6.5 cms size spaced at about 90 cms center to center and supported causorina props of 10 cm to 13 cms spaced at 75 cms to center to center etc., complete complying with standard specification and as directed (SI - 155) for column
Supplying, fabricating and placing in position mild steel or ribbed tor steel and all reinforced cement Concrete works as per the design given including cost of steel and binding wire in all floors etc complete complying with Standard (MS rods or RTS rods) which will be supplied departmentally at section stores and cost will be recovered at issue rate. The binding wire shall be supplied by the Contractor.
R.C.C. 1:1.5:3-using 20mm ISS HBGS metal including cost and conveyance of materials and labour charges etc. complete
Ceiling Plastering with C. M 1:3 mix, 10 mm thick including cost and conveyance of all materials to site and labour charges etc complete.
Plastering with C. M 1:5 mix, 12 mm thick including cost and conveyance of all materials to site and labour charges etc complete.
Painting two coats with Exterior Emulsion including cost and conveyance of all materials to site and all labour charges etc., complete.
GST Amount for providing Service to Government Contract Works for the above RENEWAL Works. { GST Amount is the Total GST Amount for overall quoted amount above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
PUGAL CONSTRUCTION (BID ID -1296465)
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .