| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L 1₹36.3 LAccepted-AOC | L 1 | Accepted-AOC WORK INCLUDES SOME BREAKDOWN AMOUNT | |
| 2 | L 2₹29.0 L+₹17,395.25 (0.60%)Rejected-Finance | L 2 | Rejected-Finance L 2 BIDDER | |
| 3 | L 3₹30.7 L+₹1.9 L (6.51%)Rejected-Finance | L 3 | Rejected-Finance L 3 BIDDER | |
| 4 | Not Admitted-Finance | - | Not Admitted-Finance Others-NOT QUALIFIED FOR OPENING OF FIN BID |
Tender Value
₹36.9 L
EMD Value
₹50,000
Closing Date
9 Aug 2023, 12:00 pmClosed
SE OMC-IV
O/o SE OMC-IV BTPS PTPP
Routine Breakdown Maintenance of lighting/illumination systems of main plant and BOP area, Chimney , Plant boundary wall lighting and offices lighting their switching on/off of BTPS PTPP Parichha
2023_RVUNL_818592_1
N-PAR////6000002606_00
Open Tender
Electrical Works
Lump-sum
731 days
2X210 MW BTPS PTPP
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,180
Dy. CAO, CFA BO, PTPP, Parichha
₹50,000
28 Oct 2023
7 Jul 2023
9 Aug 2023
7 Jul 2023
9 Aug 2023
7 Jul 2023
Amount
Routine & Breakdown Maintenance of lighting/illumination systems of main plant and BOP area including 210 MW Chimney as per scope of work part B serial no. 01 to 29. 365 jobs for Morning shift(06:00 to 14:00 hrs) & 365 jobs for evening shift (14:00 hrs to 22:00 hrs ) & 70 jobs for night emergency.
Routine & Breakdown Maintenance&Upkeeping of boundry wall lighting,plant and offices lighting and their switching ON/OFF of lighting fixtures and panels,cables,DG set,Dewatering pump of 2x110 MW PTPP Parichha as per scope of work
Re-sagging of old conductor, 3 phase & 4 wires per meter.
Stringing & sagging of new ACSR weasel conductor along-with supply of conductor.
Chopping & cutting of tree branches.
Removing the bird nest & waste material from pole.
Supply & fixing /replacement of phase separator.
Straightening & strengthening of poles with grouting & plinth making at required level.
Dismantling of single pole as per scope of work.
Erection of single pole as per scope of work.
Supply & fixing / grouting of stay at the end pole / required pole.
Digging & laying of underground armoured PVC / XLPE insulated cable of 3 ½ x50 mm2 / 3 ½ x35 mm2 / 3 ½ x16 mm2 etc for illumination as per scope of work.
Over-head laying of LT, PVC cable 3 ½ x16 mm2 /2x16 mm2 / 2x8 mm2 / 2x6 mm2 etc for illumination as per scope of work.
Supply & fixing of shackle insulators.
Supply & fixing of U-clamps of MS for mounting insulators & lighting brackets.
Supply & installation of 4pole MCCB 100A
Overhauling of Lighting transformer (Isolation Transformer)
Overhauling of Main Lighting distribution board (MLDB) .
Overhauling of NLP(Normal Lighting panel).
Installation and commissioning of Normal Lighting panel (NLP) with cable connection.
Repairing/servicing/overhauling of Dewatering pump 3.7 KW Mono-block pump/3.7 KW Trolly pump.
Repairing/servicing/overhauling of Dewatering pump 7.5 KW horizontal pump.
Repairing/servicing/overhauling of Dewatering pump 10KW Submersible Pump/9.0 KW horizontal pump.
Repairing/servicing/overhauling of Dewatering pump 15.0 KW horizontal pump.
Repairing/servicing/overhauling of Dewatering pump Repairing of foot valve.
Repairing/servicing/overhauling of Dewatering pump Replacement of coupling.
M/S R.P. CONSTRUCTION CO.
M/S INSTRUMENT CARE GROUP
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .