Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹12 LAccepted-AOC | L1 | Accepted-AOC ALL TERMS AND CONDITIONS ACCEPTED | |
| 2 | L2₹13.5 L+₹1.5 L (12.8%)Rejected-Finance NO 23 SECOND MAIN ROAD RAJAMMAL NAGAR MADAMBAKKAM CHENNAI 600 126 | CHENNAI | CHENGALPATTU | TAMIL NADU | 600126 | L2 | Rejected-Finance Rejected being not the lowest | |
| 3 | L3₹14.8 L+₹2.8 L (23.5%)Rejected-Finance 16 176 A BHARATHI PURAM NAGAI NAGAR DINDUGUL 3 | DINDUGUL | DINDIGUL | TAMIL NADU | L3 | Rejected-Finance Rejected being not the lowest | |
| 4 | L4₹17.4 L+₹5.4 L (44.6%)Rejected-Finance C 234 ADG P CHENNAI | L4 | Rejected-Finance Rejected being not the lowest | |
| 5 | L5₹17.7 L+₹5.7 L (47.6%)Rejected-Finance C 150 ADG P CHENNAI | L5 | Rejected-Finance Rejected being not the lowest |
Tender Value
₹11.0 L
EMD Value
₹22,000
Closing Date
1 Apr 2021, 6:00 pmClosed
Garrison Engineer (I)(CG) Chennai
Garrison Engineer (I)(CG) Military Engineer services Second Floor CG DHQ No 5(TN) No 4 and 4 A Clive Battery complex Rajaji Salai Chennai 600001
REPAIR/MAINTENANCE OF ELECTRICALLY OPERATED AND GOODS LIFTS INSTALLED IN TYPE II AND TYPE III QUARTERS AND OUTSOURCING SERVICES FOR ELECTRICALLY OPERATED LIFTS AT CGRA TUTICORIN UNDER GE (I) (CG) CHENNAI
2020_MES_384932_4
8813/GE(I)CG
Open Tender
Civil Works
Item Rate
365 days
Garrison Engineer (I)(CG) Chennai
All as per tender documents
8 documents required · 8 mandatory
₹500
Garrison Engineer (I)(CG) Chennai
₹22,000
Yes
16 Jun 2021
19 Mar 2021
3 Apr 2021
19 Mar 2021
1 Apr 2021
20 Mar 2021
Amount
Replacement of the following unserviceable spare parts from M/S Johnson Goods Lift, L-L5614) and old items removed taken as credit complete all as specified and as directed before entering AMC to Johnson Lifts : (Location :Type-IIQtrs: M/S Johnson Goods Lift, L-L5614) (i) Logic Board (C)ARD 25 Pin - 1No (ii) ARD Battery (12V - 18AH) - 4 Nos Note:The above items shall be procured and fixed by OEM M/s Johnson Lifts only.
Replacement of the following unserviceable spare parts from M/S Johnson Passenger Lift, L-K6975 and old items removed taken as credit complete all as specified and as directed before entering AMC to Johnson Lifts : (Location :Type-III Qtrs :M/S Johnson Passenger Lift, L-K6975) (i) Door contact without Projection -AZ 061K 3487 - 4 Nos (ii) POD Latch LH - 3 Nos (iii) Door Spring C.O.- 900 mm - 7 Nos (iv) Break Stopper Rubber Bush (POD) - 8 Nos (v) Rope Oil - 1 Litre (vi) Metal Roller 'V' Assembly - 4 Nos (vii) Door Slipper (POD) - 4 Nos (vii) Door Slipper (POD) - 4 Nos (viii)FRLS PVC copper Cable of size 2 Core 1 sqmm of required length (ix) Apolomea F6 - 6mm Standard Nylon Plug - 6 Nos (x) Wooden Screw No. 8 X30 (1") - 6 Nos (xi) GI Clamp size19mm - 2 Nos (xii) Grip Expansion Bolt with Nut -M10 X 100 mm Single Wedge Type - 1 No (xiii) Fischer Plug with Screw 10 mm X 80 mm - 2 Nos (xiv) Plate Washer M9 X40 X 2.5 mm - 2 Nos (xv) POD Latch LH - 4 Nos Note:The above items shall be procured from OEM M/s Johnson Lifts only.
Replacement of the following unserviceable spare parts from M/S JohnsonGoods Lift, L-K6976 and old items removed taken as credit complete all as specified and as directed before entering AMC to Johnson Lifts (Location :Type-III M/S Johnson Goods Lift, L-K6976) (i) Door Spring (side opening) 1200 mm - 4 Nos (ii) Door Belt (Small) - 1 No (iii) Door Contact without Projection -AZ 061K 3487 - 4 Nos (iv) Break Stopper Rubber Bush (POD) - 9 Nos (v) Metal Roller 'V' Assembly - 4 Nos (vi) Door Slipper (POD) - 4 Nos (vii) Charger Battery (12V - 2.5AH) - 1 No (viii) Rope Oil - 1 Litre (ix) )FRLS PVC copper Cable of size 2 Core 1 sqmm of required length (x) Apolomea F6 - 6mm Standard Nylon Plug - 6 Nos (xi) GI Clamp size 19mm - 2 Nos (xii) Fischer Plug with Screw 10 mm X 80 mm - 2 Nos (xii) Grip Expansion Bolt with Nut -M10 X 100 mm Single Wedge Type - 1 No (xiv) Plate Washer M9 X40 X 2.5 mm - 2 Nos (xv) Wooden Screw No. 8 X30 (1") - 6 Nos Note:The above items shall be procured from OEM M/s Johnson Lifts only.
Note for Item no 4 to 7: (i) The rate is inclusive of all items as required at site to keep the lift operational round the clock including cleaning and greasing all moving parts on monthly basis complete all as specified and as directed by Engr-in-Charge. (ii)The Contractor will conclude AMC with Johnson Lifts and copy of the agreement will be submitted to Engr-in-charge and GE before commencement of AMC. No payment will be made to contractor without submission of valid AMC agreement (iii) The contractor should attend any complaint / breakdown immediately on call basis. (iv) Contractor should submit the inspection / maintenance report of every visit inspite of no of visits during breakdown calls including mentioning the status of lift and spares any replaced.
Out sourcing for Operation of electrically operated passenger lift of 02 Nos , Make :JOHNSON LIFTS with a capacity of 13 PERSONS ,884 Kg for 09 stops/ 09 landings 1.25 M/Sec and electrically operated goods lift of 02 Nos , Make :JOHNSON LIFTS with a capacity of 1000 Kg for 09 stops/ 09 landings 1.25 M/Sec speed installed at Coast Guard Residential Accommodation (Type II and III) to be operated in two shifts per day (each shift timings :08 hrs) (0600 to 1400 hrs : 1st shift, 1400 to 2200 hrs : 2nd Shift) in all working days including sundays and holidays by deploying One No of Semi skilled Operator/Lift Attender per shift complete all as specified and as directed
Note for item No 9- (i) One operator has to operate both the passenger lift and goods lift at a time in one shift (ii) The Shift timing Shall be 0600 hrs to 1400 hrs for first shift and 1400 hrs to 2200 hrs for second shift. (iii) In case of fault in the lifts the operator should register the complaint register of lifts at the complaint cell in substation immediately. (iv) Each shift consits of 08 hrs including sunday & holidays.The Rate quoted by the contractor shall be deemed to be inclusive for each shift of 08 hrs only.
(v) The contractor shall employ one semi skilled operator for each shift who shall possess ITI Certificate for Electric OR Mechanical Trade and the Certificate should be submitted within seven days from the date of issue of work order. (vi) The contractor shall prepare duty Roster well in advance and get it approved by Engineer-in-Charge and one copy of the Roster shall be displayed in the Notice Board. (vii) Consumable items such as cotton waste etc shall be deemed to be included in the rate quoted by the contractor.
(viii) The tradesman shall wear approved uniforms as directed by Engineer-in-Charge. (ix) The stationary required to maintain log sheets, attendance registers, log book and other registers as required shall be procured by the contractor as directed by the Engr-in-Charge. The rate quoted shall be deemed to be included the same and log sheet to be submitted daily basis to concerned JE before 1500 Hrs of the succeeding day otherwise absent report will be initiated for those shifts for which log sheet are not submitted. (x) The operator should keep the lift Cabin neat and Clean. (xi) The lift operator should have the knowledge to rescue the passengers in case the lift gets struck in between the floors.
(xii) The payment shall be made to the employees by the contractor through AADHAAR linked bank account. In case any employee insist for payment in cash or by cheque an undertaking be obtained from such employee and shall be produced to the Department for Records and proof of payment shall be produced for each payment made. (xiii) The following details shall be displayed in each lift:- (i) Name of firm operating the lift. (ii) Name of person to be contacted. (iii) Land line /Mob No. The Bidders quoted rate shall be deemed to be include for the above aspects.
iv)Incase of semi skilled lift operator is found absent from duty at any time from the above mentioned shifts,recovery of Rs 1000 per person shall be made in the RAR/FB claimed by the contractor. (v) The contractor should obtain signature from the User concrened from CGRA Tutocorin for the staff employed before claming RAR in GEs office. (vi) The payment shall be made to the employees by the contractor through AADHAAR linked bank account and remittance of EPF/ESIC details should be submitted before claming RAR payment to GEs office. (vii) The contractor should not quote less than the minimum fair wage in rupees for a semi skilled supervisory staff and contribution towards EPF,ESIC ,Bonus ,LWC as fixed under any Law,Statutory rule or Order as on the last due date of receipt of tender. Incase if any tenderer quoted less than the above rate,the tender considered as NON BONAFIDE and summarily rejected. (IX) The payment towards EPF,ESIC ,Bonus remitted by the contractor will be paid only after production of documetary evidence of payment proof to the workers employed by him. Otherwise necessary recovery will be effected in the RAR Claimed by the contractor. (X) The contractor will be required to submit copy of valid labour licence from the Labour Commissioner within 15 days of commencement of work .If the contractor fails to submit the same within the stipulated period mentioned above ,the contract shall be liable to be cancelled and the Performance Security of the firm shall be forfeited.
PREMIER ENGINEERING SYSTEMS
S KUMARAN
GMS Builders
S.RAMACHANDRAN
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .