Loading…
Loading…
Tender Value
₹3.1 Cr
EMD Value
₹6.1 L
Closing Date
4 Jun 2026, 2:00 pmClosed
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Capital (Works)
TENDER SEC
14 conditions · 3 needing a document upload
For works costing more than Rs.50 lakhs - The tenderer must have minimum average annual contractual turnover of V/N or 'V' which ever is less; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderers shall submit requisite information as per Annexure-VIB, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet.
Similar Nature of Work:- Any track work
41 conditions · 3 needing a document upload
Whether required test certificates/ samples, if any have been uploaded?
The tenderer shall clearly specify whether the tender is submitted on his own (Proprietary Firm) or on behalf of a Partnership Firm / Company / Joint Venture (JV) / Registered Society/ Registered Trust / Hindu Undivided Family( HUF) / Limited Liability Partnership (LLP) etc. The tenderer(s) shall enclose the attested copies of the requisite documents (including Power of Atorney, if opted) for constitution of their concern as per Cl.14 of GCC-Part-l and as per a) Clause 17 of GCC - Part-1, for JV b) Clause 18 of GCC - Part 1, for Partnership Firm
Copies of the following documents are to be uploaded: (i) Details such as Name of the tenderer/ Contractor, Validity of DSC, Complete address with pin code, Contact Number (ii) Copy of PAN Card (iii) Copy of GSTIN card
A copy of NEFT form duly filled in the details as necessary to be uploaded. (The Tenderer/ Contractor not having NEFT form may down load the empty NEFT form available in document site)
Submission of Annexure-V under Document Verification Certificate- As per Advance Correction Slip No.4 dt.07/08/2023 to GCC - 2022, the tenderers shall submit copy of certificate stating that they are not liable to be disqualified and all their statements/documents submitted along with bid are true and factual. Standard format of the certificate to be submitted by the bidder in form of Annexure V. Non-submission of the above Certificate(s) by the bidder shall result in summarily rejection of his/their bid.
Submission of Annexure-V(A) under Document Verification Certificate : In case of other than Company/Proprietary firm, Annexure-V(A) shall also be submitted by the each member of a Partnership Firm/Joint Venture (JV) /Hindu Undivided Family (HUF) / Limited Liability Partnership (LLP) etc., as the case may be. Non-submission of the above Certificate (s) by the bidder shall result in summarily rejection of his/their bid.
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
ADEN/Dindigul Sub division:- SW I:- Through Fittings Renewal on plain track of various station yards (Loop lines) for a length of 38.165 km in SSE/Pway/MPA, DG & PLNI Section [ MPA_11.902km ,DG-7.408km & PLNI-18.855km] SWII: - TPJ-DG Section (Up/Dn line):-Through Fittings Renewal on plain track (Main line) for a length of 56.50 km at isolated location in SSE/Pway/MPA & DG Section [ MPA- 48.80km ,DG-7.700km] SW III:- DG station :- Upgradation of major yard work in connection with TRR(S), SEJ renewal and Deep screening of loop line & Pt & crossing in DG yard. SW IV:- Proposed Conversion of SWP into LWR of various yards in SSE/Pway/PLNI section. S W V:- Deep screening by BCM/Manual on loop lines at various station yard in SSE/Pway/MPA &DG Section. SW VI:- TPJ-DG (Up Line):- Deep screening by BCM from km 408/600 to 425/100 between AYR-TMP stations for a length of 16.50km."
MDU-W-06-2026-11
MDU-W-06-2026-11
Open
Works - General
12 Months
Madurai, Tamil Nadu
₹0
₹6.1 L
4 Jun 2026
13 May 2026
21 May 2026
45 items across 3 schedules
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| — | — | — | 60,77,506.3 | ||
| — | 86500.00 | — | — | ||
| Destressing of LWR / CWR track consisting of PSC sleeper duly removing the fastening, lifting rails on roller and (as per the procedure laid down in the latest manual for fusion welding of rails by Alumino Thermic process and lowering rails and driving back the rail fittings, released or new fittings correctly to maintain the uniform gauge and alignment with contractor's Hydraulic rail tensor and contractor's consumable stores, labours, etc., at the locations as identified by the Engineer - in - charge with all lead, lift, track crossing,etc,. (Rollers and HYDRAULIC RAIL TENSOR to besupplied by Contractor) | — | — | — | 40,65,500 | |
| — | 2351.00 | — | — | ||
| Collection and transportation of all guardrails, P.way fittings such as ERC' s liners, rubber pads, fish plates etc., available in road approach able place of station yard/ LCs to works pot by dip lorry with alead of 2km, unloading and stacking neatly at specified locations in countable manner with alllead and lift etc., complete including crossing of track wherever required and as directed by the Engineer-in-charge with all lead and lift etc., complete (All labour and tools for trucking out of materials are to be supplied by the Tenderer/ contractor except diplorry if required will be supplied free by the Railway) | — | — | — | 13,63,580 | |
| — | 92.00 | — | — | ||
| Collection and transportation of all guardrails, P.way fittings such as ERC's liners, rubber pads, fish plates etc., available in road approach able place of station yard/ LCs to work spot by dip lorry with alead of 2km, unloading and stacking neatly at specified locations in countable manner with all lead and lift etc., complete including crossing of track wherever required and as directed by the Engineer-in-charge with all lead and lift etc., complete (All labour and tools for trucking out of materials are to be supplied by the Tenderer/ contractor except dip lorry if required will be supplied free by the Railway | — | — | — | 53,360 | |
| — | 6875.00 | — | — | ||
| — | 24.00 | — | — | ||
| Casting, Supplying and fixing RCC Hectometer posts as per Drg.no CBE/TP/175/98 in M25 mix with 20mm graded size metal and fixing at various locations adjacent torunning track in the formation with cement concrete foundation of size 0.30x0.30x0.40m with 1:2:4 mix including earthwork excavation and applying one coat of whitesynthetic enamel paint of approved quality on one side and writing numbers on other side of posts with black synthetic enamel paint duly plastering the surface for 12mm thickness with alllead and lift etc., complete and as directed by the Engineer-In-Charge. (All labour, materials, tools and plants are to be supplied by theTenderer/contractor only a this own cost including cement and steel) Taking survey as per CE's CircularNo.4/99 and transferring level storail post supplied by Railways free of cost, leading the same by Dip-lorry/ road vehicle, Earth work to required depth, concreting curing with contractor's own cement,s and, Coarse aggregate and water, synthetic enamel paints, steel measuring tapes, Nylonchords, labours,Tool sandplants, consumables etc., after computer solution legibly as per the instruction of Engineer incharge. (Rail posts have to be transported from the nearest station in the section) | — | — | — | 28,828.8 | |
| — | 23.41 | — | — | ||
| Marking of chainage in web of rail at every 10m and with letter in gat30m interval with contractor's own yellow enamel paint of best approved quality and other consumables, labour, tranportation, toolsandplant, lead, lift, track crossing etc.,complete and as directed by the Engineer in charge | — | — | — | 23,410 | |
| — | 23.41 | — | — | ||
| Taking Fly levels of rail at every 10m and cess at every 30m on both sides (LHS and RHS ) chainage interval with contractor's own precision levelling instrument, technical person, transportation, tools and plant, lead,lift,track crossing etc.,complete and as directed by the Engineer incharge | — | — | — | 35,115 | |
| — | 23.41 | — | — | ||
| Erection of railway's steel pegs at 10m interval and marking of existing rail levels with contractor's own enamel paint of best approved quality and other consumables, labour, tranportation, tools and plant, lead, lift, track crossing etc., complete and as directed by the Engineer in charge | — | — | — | 35,115 | |
| — | 23.41 | — | — | ||
| Submission of Reduced Levels of Rail and Cess on both sides (LHSandRHS) in good quality of paper along with softcopy with contractor's ownlabour, materials,tools&plants,tranportation,consumables and other ancillary requirements for the completion of the work,etc.,complete as specified and directed by the Engineer - in - charge. | — | — | — | 5,852.5 | |
| — | 23.41 | — | — | ||
| Marking of proposed rail levels inpegs already erected with contractor's own enamel paint of best approved quality and colour, other consumables, labour, tranportation, toolsandplant, lead,lift,track crossingetc.,complete and as directed by the Engineer in charge | — | — | — | 17,557.5 | |
| — | 135.00 | — | — | ||
| Shifting Engineering indicator boards from one location to another location with Contractor's own labour, tools, plants including all lead, lift, track crossing etc., and as directed by the Engineer incharge.(Engineering indicators have to be transported from SSE/P.WAY/Depot /nearest station by contractor's own vehicle at the first occasion and to be returned on completion of work) | — | — | — | 60,750 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
BankGuaranteeBond-Modelform.pdf
ATTACHMENT
GCCApr2022withCorrectionSlip1to11.pdf GCC April 2022 with correction slip
ATTACHMENT
RulesandRegulations-Aug2023.pdf
ATTACHMENT
SpecialconditionoftrackworkGL.pdf
ATTACHMENT
GCCApr2022withCorrectionSlip1to11.pdf
ATTACHMENT
SpecialconditionforTRR.pdf
ATTACHMENT
SpecialconditionforTSR.pdf
ATTACHMENT
Siteweldingcondition.pdf
ATTACHMENT
Conditionforrailpainting.pdf
ATTACHMENT
Contidionsformovementofvehicle.pdf
ATTACHMENT
Quantitybreakup-Sch-A1-a.pdf
ATTACHMENT
SWITFRonLooplineAnnexure.pdf
ATTACHMENT
SWIITFROnmainLineAnnexure.pdf
ATTACHMENT
SWIIItoSWVIAnnexure.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .