| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹9.6 LAdmitted-Finance | -20.00% | ₹9.6 L | L1 | Admitted-Finance |
| 2 | L2₹10.6 L+₹98,462.89 (10.2%)Admitted-Finance 502 D MELLOWADDO ARADI SOCORRO PORVORIM GOA | -11.80% | ₹10.6 L+₹98,462.89 (10.2%) | L2 | Admitted-Finance |
| 3 | L3₹10.8 L+₹1.2 L (12.5%)Admitted-Finance | -10.00% | ₹10.8 L+₹1.2 L (12.5%) | L3 | Admitted-Finance |
Tender Value
₹12.0 L
EMD Value
₹24,015
Closing Date
30 Jul 2026, 3:00 pmClosed
Executive Engineer
WD.II, DDW, PORVORIM GOA
Repairs to pipeline network of various types in Khorlim, Angod, Mapusa Market and Ansabhat in Mapusa Constituency under SDII, WDII, DDW, Mapusa
2026_DDW_30543_1
DDW/ WD.II/ ASW/ F.24-E/ 16/ 2026-27/ L-6
Open Tender
Pipe Laying Works
Percentage
120 days
Mapusa
Please refer Tender documents.
8 documents required · 8 mandatory
₹5,000
₹24,015
27 Aug 2026
23 Jul 2026
31 Jul 2026
23 Jul 2026
30 Jul 2026
23 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Repairs to pipeline network (leakage / breakdown) of various types including cost of materials (pipe, joints
etc.), all tools / accessories, labour, transportation, valve operations, traffic management, providing barricading,
danger lighting, guarding etc. complete as per the direction of engineer incharge.
A) Repairs to PVC pipeline
I) 63mm | 30 | Nos. | 1 | ₹29.97 |
| 2 | Repairs to pipeline network (leakage / breakdown) of various types including cost of materials (pipe, joints etc.), all tools / accessories, labour, transportation, valve operations, traffic management, providing barricading, danger lighting, guarding etc. complete as per the direction of engineer incharge.
A) Repairs to PVC pipeline
II) 75mm | 20 | Nos. | 3,528.26 | ₹70,565.2 |
| 3 | Repairs to pipeline network (leakage / breakdown) of various types including cost of materials (pipe, joints etc.), all tools / accessories, labour, transportation, valve operations, traffic management, providing barricading, danger lighting, guarding etc. complete as per the direction of engineer incharge.
A) Repairs to PVC pipeline
III) 90mm | 20 | Nos. | 3,660.3 | ₹73,206 |
| 4 | Repairs to pipeline network (leakage / breakdown) of various types including cost of materials (pipe, joints etc.), all tools / accessories, labour, transportation, valve operations, traffic management, providing barricading, danger lighting, guarding etc. complete as per the direction of engineer incharge.
A) Repairs to PVC pipeline
IV) 110mm | 20 | Nos. | 3,920.26 | ₹78,405.2 |
| 5 | Repairs to pipeline network (leakage / breakdown) of various types including cost of materials (pipe, joints etc.), all tools / accessories, labour, transportation, valve operations, traffic management, providing barricading, danger lighting, guarding etc. complete as per the direction of engineer incharge. A) Repairs to 160mm dia. PVC pipeline | 10 | Nos. | 7,596.78 | ₹75,967.8 |
| 6 | Repairs to pipeline network (leakage / breakdown) of various types including cost of materials (pipe, joints etc.), all tools / accessories, labour, transportation, valve operations, traffic management, providing barricading, danger lighting, guarding etc. complete as per the direction of engineer incharge.
B) Repairs to 80mm dia. AC pipeline | 8 | Nos. | 4,134.96 | ₹33,079.68 |
| 7 | Repairs to pipeline network (leakage / breakdown) of various types including cost of materials (pipe, joints etc.), all tools / accessories, labour, transportation, valve operations, traffic management, providing barricading, danger lighting, guarding etc. complete as per the direction of engineer incharge.
B) Repairs to 100mm dia. AC pipeline | 10 | Nos. | 4,574.96 | ₹45,749.6 |
| 8 | Repairs to pipeline network (leakage / breakdown) of various types including cost of materials (pipe, joints etc.), all tools / accessories, labour, transportation, valve operations, traffic management, providing barricading, danger lighting, guarding etc. complete as per the direction of engineer incharge.
B) Repairs to 150mm dia. AC pipeline | 10 | Nos. | 8,945.92 | ₹89,459.2 |
| 9 | Repairs to pipeline network (leakage / breakdown) of various types including cost of materials (pipe, joints etc.), all tools / accessories, labour, transportation, valve operations, traffic management, providing barricading, danger lighting, guarding etc. complete as per the direction of engineer incharge. B) Repairs to 200mm dia. AC pipeline | 3 | Nos. | 10,759.92 | ₹32,279.76 |
| 10 | Repairs to pipeline network (leakage / breakdown) of various types including cost of materials (pipe, joints etc.), all tools / accessories, labour, transportation, valve operations, traffic management, providing barricading, danger lighting, guarding etc. complete as per the direction of engineer incharge.
C) Repairs to 80mm dia. DI/CI pipeline | 8 | Nos. | 4,166.96 | ₹33,335.68 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.55 MB
Tendernotice_2.pdf
PDF • 0.63 MB
BOQ_30955.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .