| 1 | L1₹175.9 CrAccepted-AOC | ₹175.9 Cr | L1 | Accepted-AOC L1 BIDDER |
| 2 | L2₹244.4 CrRejected-AOC CRYSTAL TOWER 4TH FLOOR TELIBANDHA RAIPUR | RAIPUR | RAIPUR | CHHATTISGARH | ₹244.4 Cr | L2 | Rejected-AOC L2 BIDDER |
Tender Value
₹227.7 Cr
EMD Value
₹4.6 Cr
Closing Date
30 Aug 2018, 4:00 pmClosed
SE (AUTOMATION, N/M SP), RVPN
VIDYUT BHAWAN, JYOTI NAGAR, JAIPUR
DESIGN, SUPPLY AND IMPLEMENTATION OF RENEWABLE ENERGY INTEGRATION- REAL TIME DATA ACQUISITION SYSTEM FOR MONITORING AND CONTROL OF TRANSMISSION GRID UNDER SMART TRANSMISSION NETWORK AND ASSET MANAGEMENT SYSTEM (PART-A1)
2018_RRVPN_113684_1
RVPN/EHV/ASP/TN-14
Open Tender
Electrical Works
540 days
RAJASTHAN
Please refer Tender documents.
4 documents required · 4 mandatory
₹29,500
SR ACCOUNTS OFFICER (EA-CASH), RVPN, JAIPUR
₹4.6 Cr
JAIPUR
30 Mar 2020
27 Jun 2018
30 Aug 2018
27 Jun 2018
30 Aug 2018
3 Aug 2018
12 Jul 2018
MATERIAL/ EQUIPMENT/ ITEM
Field Infrastructure
Type-I Substations
765kV GSS
Transducers/ Sensors, CMR, Interposing Relays (to be quoted in Item A1,5)
Power & Control Cabling (to be quoted in Item A1,5)
Communication Cables (to be quoted in Item A1,5)
RAS & AFAS System Component (Substation end)
Data Concentrator Unit (DCU) at Substation for RAS with sutiable enclosure/ panels fully wired
24 Port Ethernet Switch
Media Converters
400kV GSS
Transducers/ Sensors, CMR, Interposing Relays (to be quoted in Item A1,5)
Power & Control Cabling (to be quoted in Item A1,5)
Communication Cables (to be quoted in Item A1,5)
RAS & AFAS System Component (Substation end)
Data Concentrator Unit (DCU) at Substation for RAS with sutiable enclosure/ panels fully wired
24 Port Ethernet Switch
Media Converters
220kV GSS
Transducers/ Sensors, CMR, Interposing Relays (to be quoted in Item A1,5)
Power & Control Cabling (to be quoted in Item A1,5)
Communication Cables (to be quoted in Item A1,5)
RAS & AFAS System Component (Substation end)
Data Concentrator Unit (DCU) at Substation for RAS with sutiable enclosure/ panels fully wired
24 Port Ethernet Switch
Media Converters
132kV GSS
Transducers/ Sensors, CMR, Interposing Relays (to be quoted in Item A1,5)
Power & Control Cabling (to be quoted in Item A1,5)
Communication Cables (to be quoted in Item A1,5)
RAS & AFAS System Component (Substation end)
Data Concentrator Unit (DCU) at Substation for RAS with sutiable enclosure/ panels fully wired
24 Port Ethernet Switch
Media Converters
Type-II Substations
400kV GSS
Transducers/ Sensors, CMR, Interposing Relays (to be quoted in Item A1,5)
Power & Control Cabling (to be quoted in Item A1,5)
Communication Cables (to be quoted in Item A1,5)
RAS & AFAS System Component (Substation end)
Data Concentrator Unit (DCU) at Substation for RAS with sutiable enclosure/ panels fully wired
24 Port Ethernet Switch
Media Converters
220kV GSS
Transducers/ Sensors, CMR, Interposing Relays (to be quoted in Item A1,5)
Power & Control Cabling (to be quoted in Item A1,5)
Communication Cables (to be quoted in Item A1,5)
RAS & AFAS System Component (Substation end)
Data Concentrator Unit (DCU) at Substation for RAS with sutiable enclosure/ panels fully wired
24 Port Ethernet Switch
Media Converters
132kV GSS
Transducers/ Sensors, CMR, Interposing Relays (to be quoted in Item A1,5)
Power & Control Cabling (to be quoted in Item A1,5)
Communication Cables (to be quoted in Item A1,5)
RAS & AFAS System Component (Substation end)
Data Concentrator Unit (DCU) at Substation for RAS with sutiable enclosure/ panels fully wired
24 Port Ethernet Switch
Media Converters
Type-III Substations
RTU complete with accessories/ items
220 kV Substation (New Location)
220 kV Substation (Replacement Location)
132 kV Substation
Analog Input (AI) [ Inbuilt Points and Additional cards shall be considered in RTUs in i (a,b & c) above as per Survey & approval of Nigam]
Digital Input (DI) [ Inbuilt Points and Additional cards shall be considered in RTUs in i (a,b & c) above as per Survey & approval of Nigam]
Digital Output (DO) [ Inbuilt Points and Additional cards shall be considered in RTUs in i (a,b & c) above as per Survey & approval of Nigam]
GPS/Time Synchronizing Unit
RAS & AFAS System Component (Substation end)
Data Concentrator Unit (DCU) at Substation for RAS with sutiable enclosure/ panels fully wired
24 Port Ethernet Switch
Media Converters
WAMS System Component (Substation End)
Phasor Measurement Unit (PMU) alongwith all associated accessories mounted on Panel fully wired including required software
Other associated Items
SIC Panel
Multifunction Panel Meter
Transducers/ Sensors
Substation Auxiliary Supply Monitoring Related
DC Voltage Transducer
220 V DC System
110 V DC System
48 V DC System
DC Current Transducer
220 V DC System
110 V DC System
48 V DC System
Transformer Related
Tap Indicator Transducer
Winding Temprature Transducer
Oil Temprature Transducer
Weather Related
Weather Sensor
Isolator Related
Mechanical Key Interlock Box (1 NO, 1 NC Contact)
Contact Multiplier Realy
2 NO+NC Non Latching Type CMR
Interposing Relays
Heavy Duty Control Output Interposing Relays
Cables
Power & Control Cables (Armoured)
3 C x 2.5 Sq. mm
5 C x 2.5 Sq. mm
7 C x 2.5 Sq. mm
Power & Control Cable (Unarmoured)
4 C x 4 Sq. mm
3C x 2.5 Sq. mm
4 C x 2.5 Sq. mm
7C x 2.5 Sq. mm
10 C x 2.5 Sq. mm
3 C x 1.5 Sq. mm
Copper Coil for Panel Wiring
Cable accessories for Installation
Cable Conduits, tags, trays, joint boxes etc. as required for laying of cables as per standard installation requirements at substations
Miscellaneous Communication Cables
Ethernet CAT6A, Armoured fiber, Co-axial Cable etc. as required for connecting all data acquistion Devices and equipments/ items for completing the work on substations
Earthing
Earthing Strips / Electordes and other items for Earthing of supplied Equipments/ Panels at Substations
Smart Grid Command & Control Center (s) (Main, Back-up & Regional)
Main Control Center (including Regional Control Center for Jaipur Zone)
Hardware
Server
Blade Server Chassis
Blade Servers (each with minimum two CPUs)
Archive Storage
SAN & NAS
External Storage Disk (DAT/MO)
Workstation
Remote Video Display Unit
Printers
A3 Size B&W Laser Printer
A3 Size Color Printer
A4 Size B&W Laser Printer
A4 Size Color Printer
GPS/TSE
24 Port Ethernet Switch
Test Equipment for RTU Configuration and Testing
Power & Control Cables (to be quoted in Item A1,5)
Cable Accessories for Installation
Miscellaneous Communication Cables
Earthing Items/ Material
Software
System & Application Software
Operating System for Blade Servers
Relational Data Base System
Data Historian (for SCADA System)
Data Historian (for WAMS system)
User Authentication
Web & Data Replica
Web & Mobile Application
SMS Gateway
Geographic Map & associated Software
Other Utility Software such as Document, Patch Management. Identity Management, Server Back-Up, Report Development and Generation etc. as required for the complete system
Functional Software
SCADA
Development & Testing
Operator Training Simulator (OTS)
Voltage/ VAR Control
Load Forecasting
Decsion Support System
Asset Heallth Management
RAS &AFAS
WAMS (PDC & Visualization & Analytics Software)
Back-Up Center (including Regional Control Center for Jodhpur Zone)
Hardware
Server
Blade Server Chassis
Blade Servers (each with minimum two CPUs)
Storage
SAN & NAS
External Storage Disk (DAT/MO)
Workstation
Console
Remote Video Display Unit
Printers
A4 Size B&W Laser Printer
A3 Size Color Printer
GPS/TSE
Ethernet Switch
Test Equipment for RTU Configuration and Testing
Power & Control Cables (to be quoted in Item A1,5)
Cable Accessories for Installation
Miscellaneous Communication Cables
Earthing Items/ Material
Software
System & Application Software
Operating System for Blade Servers
Relational Data Base System
Data Historian (SCADA System)
User Authentication
Web & Data Replica
Web & Mobile Application
SMS Gateway
Geographic Map & associated Software
Other Utility Software such as Document, Patch Management. Identity Management, Server Back-Up, Report Development and Generation etc. as required for the complete system
Functional Software
SCADA
Development & Testing
Operator Training Simulator (OTS)
Voltage/ VAR Control
Load Forecasting
Decsion Support System
Asset Heallth Management
RAS &AFAS
Regional Control Center for Ajmer Zone)
Hardware
Server
Blade Server Chassis
Blade Servers (each with minimum two CPUs)
Storage
SAN & NAS
External Storage Disk (DAT/MO)
Workstation
Console
Remote Video Display Unit
Printers
A4 Size B&W Laser Printer
A3 Size Color Printer
GPS/TSE
Ethernet Switch
Test Equipment for RTU Configuration and Testing
Power & Control Cables (to be quoted in Item A1,5)
Cable Accessories for Installation
Miscellaneous Communication Cables
Earthing Items/ Material
Software
System & Application Software
Operating System for Blade Servers
Relational Data Base System
Data Historian (SCADA System)
User Authentication
Web & Data Replica
Web & Mobile Application
SMS Gateway
Geographic Map & associated Software
Other Utility Software such as Document, Patch Management. Identity Management, Server Back-Up, Report Development and Generation etc. as required for the complete system
Functional Software
SCADA
Development & Testing
Operator Training Simulator (OTS)
Voltage/ VAR Control
Load Forecasting
Decsion Support System
Asset Heallth Management
RAS &AFAS
Access Control System
MANDATORY SPARES
CPU Card
Power Supply Card
Analog Input Card
Digital Input Card
Digital Output Card
RAS & AFAS System
WAMS System
PMU (offered type)
Transducer/ Sensors
DC Voltage Transducer ( 6 Nos. each type)
DC Current Transducer (6 Nos. each type)
Temprature Transducer ( 6 Nos. Each type)
Mechanical Key Interlock Box (1 NO, 1 NC Contact)
Contact Multiplier Relays
Interposing Relays
Workstation
Hard Disk
Monitor
Power Supply
Description of Work / Item(s)
INSTALLATION, TESTING & COMMISSIONING OF MATERIAL/ EQUIPMENT
Field Infrastructure
Type-I Substations
765 kV GSS
Transducers/ Sensors, CMR, Interposing Relays (to be quoted in item B1, 5)
Power & Control Cabling (to be quoted in item B1, 5)
Communication Cables (to be quoted in item B1, 5)
RAS & AFAS System Component (Substation end)
Data Concentrator Unit (DCU) at Substation for RAS with sutiable enclosure/ panels fully wired
24 Port Ethernet Switch
Media Converters
400 kV GSS
Transducers/ Sensors, CMR, Interposing Relays (to be quoted in item B1, 5)
Power & Control Cabling (to be quoted in item B1, 5)
Communication Cables (to be quoted in item B1, 5)
RAS & AFAS System Component (Substation end)
Data Concentrator Unit (DCU) at Substation for RAS with sutiable enclosure/ panels fully wired
24 Port Ethernet Switch
Media Converters
220 kV GSS
Transducers/ Sensors, CMR, Interposing Relays (to be quoted in item B1, 5)
Power & Control Cabling (to be quoted in item B1, 5)
Communication Cables (to be quoted in item B1, 5)
RAS & AFAS System Component (Substation end)
Data Concentrator Unit (DCU) at Substation for RAS with sutiable enclosure/ panels fully wired
24 Port Ethernet Switch
Media Converters
132 kV GSS
Transducers/ Sensors, CMR, Interposing Relays (to be quoted in item B1, 5)
Power & Control Cabling (to be quoted in item B1, 5)
Communication Cables (to be quoted in item B1, 5)
RAS & AFAS System Component (Substation end)
Data Concentrator Unit (DCU) at Substation for RAS with sutiable enclosure/ panels fully wired
24 Port Ethernet Switch
Media Converters
Type-II Substations
400 kV GSS
Transducers/ Sensors, CMR, Interposing Relays (to be quoted in item B1, 5)
Power & Control Cabling (to be quoted in item B1, 5)
Communication Cables (to be quoted in item B1, 5)
RAS & AFAS System Component (Substation end)
Data Concentrator Unit (DCU) at Substation for RAS with sutiable enclosure/ panels fully wired
24 Port Ethernet Switch
Media Converters
220 kV GSS
Transducers/ Sensors, CMR, Interposing Relays (to be quoted in item B1, 5)
Power & Control Cabling (to be quoted in item B1, 5)
Communication Cables (to be quoted in item B1, 5)
RAS & AFAS System Component (Substation end)
Data Concentrator Unit (DCU) at Substation for RAS with sutiable enclosure/ panels fully wired
24 Port Ethernet Switch
Media Converters
132 kV GSS
Transducers/ Sensors, CMR, Interposing Relays (to be quoted in item B1, 5)
Power & Control Cabling (to be quoted in item B1, 5)
Communication Cables (to be quoted in item B1, 5)
RAS & AFAS System Component (Substation end)
Data Concentrator Unit (DCU) at Substation for RAS with sutiable enclosure/ panels fully wired
24 Port Ethernet Switch
Media Converters
Type-III Substations
RTU complete with accessories/ items
220 kV Substation (New Location)
220 kV Substation (Replacement Location)
132 kV Substation
Analog Input (AI) [ Inbuilt Points and Additional cards shall be considered in RTUs in i (a,b & c) above as per Survey & approval of Nigam]
Digital Input (DI) [ Inbuilt Points and Additional cards shall be considered in RTUs in i (a,b & c) above as per Survey & approval of Nigam]
Digital Output (DO) [ Inbuilt Points and Additional cards shall be considered in RTUs in i (a,b & c) above as per Survey & approval of Nigam]
GPS/Time Synchronizing Unit
RAS & AFAS System Component (Substation end)
Data Concentrator Unit (DCU) at Substation for RAS with sutiable enclosure/ panels fully wired
24 Port Ethernet Switch
Media Converters
WAMS System Component (Substation End)
Phasor Measurement Unit (PMU) alongwith all associated accessories mounted on Panel fully wired including required software
Other associated Items
SIC Panel
Multifunction Panel Meter
Transducers/ Sensors
Substation Auxiliary Supply Monitoring Related
DC Voltage Transducer
220 V DC System
110 V DC System
48 V DC System
DC Current Transducer
220 V DC System
110 V DC System
48 V DC System
Transformer Related
Tap Indicator Transducer
Winding Temprature Transducer
Oil Temprature Transducer
Weather Related
Weather Sensor
Isolator Related
Mechanical Key Interlock Box (1 NO, 1 NC Contact)
Contact Multiplier Realy
2 NO+NC Non Latching Type CMR
Interposing Relays
Heavy Duty Control Output Interposing Relays
Cables
Power & Control Cables (Armoured)
3 C x 2.5 Sq. mm
5 C x 2.5 Sq. mm
7 C x 2.5 Sq. mm
Power & Control Cable (Unarmoured)
4 C x 4 Sq. mm
3C x 2.5 Sq. mm
4 C x 2.5 Sq. mm
7C x 2.5 Sq. mm
10 C x 2.5 Sq. mm
3 C x 1.5 Sq. mm
Copper Coil for Panel Wiring
Cable accessories for Installation
Cable Conduits, tags, trays, joint boxes etc. as required for laying of cables as per standard installation requirements at substations
Miscellaneous Communication Cables
Ethernet CAT6A, Armoured fiber, Co-axial Cable etc. as required for connecting all data acquistion Devices and equipments/ items for completing the work on substations
Earthing
Earthing Strips / Electordes and other items for Earthing of supplied Equipments/ Panels at Substations
Smart Grid Command & Control Center (s) (Main, Back-up & Regional)
Main Control Center (including Regional Control Center for Jaipur Zone)
Hardware
Server
Blade Server Chassis
Blade Servers (each with minimum two CPUs)
Archive Storage
SAN & NAS
External Storage Disk (DAT/MO)
Workstation
Remote Video Display Unit
Printers
A3 Size B&W Laser Printer
A3 Size Color Printer
A4 Size B&W Laser Printer
A4 Size Color Printer
GPS/TSE
24 Port Ethernet Switch
Test Equipment for RTU Configuration and Testing
Power & Control Cables (to be quoted in item B1, 5)
Cable Accessories for Installation
Miscellaneous Communication Cables
Earthing Items/ Material
Software
System & Application Software
Operating System for Blade Servers
Relational Data Base System
Data Historian (for SCADA System)
Data Historian (for WAMS system)
User Authentication
Web & Data Replica
Web & Mobile Application
SMS Gateway
Geographic Map & associated Software
Other Utility Software such as Document, Patch Management. Identity Management, Server Back-Up, Report Development and Generation etc. as required for the complete system
Functional Software
SCADA
Development & Testing
Operator Training Simulator (OTS)
Voltage/ VAR Control
Load Forecasting
Decsion Support System
Asset Heallth Management
RAS &AFAS
WAMS (PDC & Visualization & Analytics Software)
Back-Up Center (including Regional Control Center for Jodhpur Zone)
Hardware
Server
Blade Server Chassis
Blade Servers (each with minimum two CPUs)
Storage
SAN & NAS
External Storage Disk (DAT/MO)
Workstation
Console
Remote Video Display Unit
Printers
A4 Size B&W Laser Printer
A3 Size Color Printer
GPS/TSE
Ethernet Switch
Test Equipment for RTU Configuration and Testing
Power & Control Cables (to be quoted in item B1, 5)
Cable Accessories for Installation
Miscellaneous Communication Cables
Earthing Items/ Material
Software
System & Application Software
Operating System for Blade Servers
Relational Data Base System
Data Historian (SCADA System)
User Authentication
Web & Data Replica
Web & Mobile Application
SMS Gateway
Geographic Map & associated Software
Other Utility Software such as Document, Patch Management. Identity Management, Server Back-Up, Report Development and Generation etc. as required for the complete system
Functional Software
SCADA
Development & Testing
Operator Training Simulator (OTS)
Voltage/ VAR Control
Load Forecasting
Decsion Support System
Asset Heallth Management
RAS &AFAS
Regional Control Center for Ajmer Zone)
Hardware
Server
Blade Server Chassis
Blade Servers (each with minimum two CPUs)
Storage
SAN & NAS
External Storage Disk (DAT/MO)
Workstation
Console
Remote Video Display Unit
Printers
A4 Size B&W Laser Printer
A3 Size Color Printer
GPS/TSE
Ethernet Switch
Test Equipment for RTU Configuration and Testing
Power & Control Cables (to be quoted in item B1, 5)
Cable Accessories for Installation
Miscellaneous Communication Cables
Earthing Items/ Material
Software
System & Application Software
Operating System for Blade Servers
Relational Data Base System
Data Historian (SCADA System)
User Authentication
Web & Data Replica
Web & Mobile Application
SMS Gateway
Geographic Map & associated Software
Other Utility Software such as Document, Patch Management. Identity Management, Server Back-Up, Report Development and Generation etc. as required for the complete system
Functional Software
SCADA
Development & Testing
Operator Training Simulator (OTS)
Voltage/ VAR Control
Load Forecasting
Decsion Support System
Asset Heallth Management
RAS &AFAS
Access Control System
Pre-Implementation [Refer Specification Clause No. 2.1 Vol-II, Part-I]
Pre-implementation Site Survey
Training [Refer Specification Clause No. 2.5 Vol-II, Part-I]
Advance Training for System Administration and Maintenance
Advance Training on Configuration and maintenance of deployed control center hardware and application software
Advance Training for Data Acquistion Devices
Training on general Operation and Usage of System Deployed
Comprehensive Maintenance Contract [Refer Specification Clause No. 2.6 Vol-II, Part-I]
Complerhensive Maintenance
Project Change Request/ Management [Refer Specification Clause No. 4.0 Vol-II, Part-I]
Addition of New EHV Substation Location (without IEC-61850 based Automation) [Refer Specification Clause No. 4.1 a, Vol-II, Part-I]
Addition of New EHV Substation Location (with IEC-61850 based Automation) [Refer Specification Clause No. 4.1 b, Vol-II, Part-I]
400kV & above
Addition of New Bay at Existing Substation [Refer Specification Clause No. 4.1 c, Vol-II, Part-I]
400kV & above
Addition of any New Reactive Power Element/ On-Line condition Monitoring Equipments/ Any other Substation Data acquisition Equipment for grid/ substation parameter measurements [Refer Specification Clause No. 4.1 d, Vol-II, Part-I]
Description of Work / Item(s)
Total Schedule No. BOQB1
SUPPLY PART
Total Schedule No. BOQB2
SERVICE PART
GE TD India Ltd
Larsen and Toubro Limited
GE TD India Ltd
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid