| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.3 CrAccepted-AOC 001 CASABLANCA SANGAM PRESS ROAD KOTHRUD PUNE 411038 | PUNE | PUNE | MAHARASHTRA | 411038 | ₹2.3 Cr | L1 | Accepted-AOC Lowest |
| 2 | L2₹2.4 Cr+₹6.9 L (3.00%)Rejected-Finance | ₹2.4 Cr+₹6.9 L (3.00%) | L2 | Rejected-Finance Not Lowest |
| 3 | L3₹3.1 Cr+₹83.0 L (35.9%)Rejected-Finance 309 SKYLARK BUILDING 309 SKYLARK BUILDING 60 NEHRU PLACE NEW DELHI NEW DELHI DELHI 110019 | SOUTH EAST DELHI | DELHI | 110019 | ₹3.1 Cr+₹83.0 L (35.9%) | L3 | Rejected-Finance Not Lowest |
| 4 | Rejected-Technical | - | - | Rejected-Technical Not meeting the tender criteria |
Tender Value
Refer Docs
Closing Date
17 May 2022, 3:00 pmClosed
Manager-Admin (Purchase)
CDAC Innovation Park Pune 411 008
Design, Site Preparation, SITC and AMC services of Basic Infrastructure for the establishment of a Data Center
2022_DIT_682426_1
CDACP/ Airawat-DC/22-23/342
Open Tender
Electrical Goods/Equipment
Turn-key
150 days
Pune
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,000
CDAC
Exempted
Pune
7 Jun 2023
5 Apr 2022
18 May 2022
5 Apr 2022
17 May 2022
30 Apr 2022
6 Apr 2022 - 11 Apr 2022
18 Apr 2022
Design, Site Preparation, Supply, Installation, Testing, Commissioning and AMC services of Basic Infrastructure for the establishment of a Data Centre at CDAC Pune.
Civil and allied works
All LT Cabling –Power and Control, Earthing, Lighting Arrestors, Cable Trays, Supports, Cable terminations, Glands and other accessories etc.
Internal Illumination System along with DBs
Precision Air Conditioning Unit (PAC), Cu piping and other accessories etc.
Pipes of all sizes, Bends, valves, actuators, joints, end flanges and other hardware including accessories etc.
Rear Door Heat Exchanger along with Hose Pipe
In Row System along with Close-Rack Containment
All 42 U Racks- Server Rack -42 U along with Dual PDU, cable manager and blanking plates
Fire Alarm system including Detectors, panels, cabling and associated accessories etc.
Fire Suppression system for Data Center area including Gas release panel, cylinder, Manifold, piping and associated accessories etc.
NOVEC Gas for Data center area
CCTV system including camera, switch, NVR, Cables, monitors etc.
Integration of third party devices, I/O modules, all control and communication cabling etc. on existing BMS.
Other IBMS including Water leak detectors, Rodent Repellent, VESDA etc. system
Any other item, material required to complete the solution
CAMC Charges
Comprehensive Annual Maintenance Contract -Year-4
Comprehensive Annual Maintenance Contract -Year-5
RAHI SYSTEMS PVT LTD
Nikom Infrasolutions Pvt. Ltd.
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .