| 1 | L1₹8.8 CrAdmitted-Finance | ₹8.8 Cr | L1 | Admitted-Finance |
| 2 | L2₹8.9 Cr+₹5.7 L (0.65%)Admitted-Finance | ₹8.9 Cr+₹5.7 L (0.65%) | L2 | Admitted-Finance |
| Sl No | Description | Qty | Unit | M/s LRT CONSTRUCTION L1 | Ms Pamong Construction L2 |
|---|---|---|---|---|---|
| 1.00SH: Jungle clearance | |||||
| 1.01 | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness.
(Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness
a) In area of thorny jungle | 8.5 | Hect. | 74,498.52 ₹6,33,237.42 Lowest | 74,498.52 ₹6,33,237.42 Lowest |
| 1.02 | Cutting of trees, including cutting of trunks, branches and removal of stumps, roots, stacking of serviceable material with all lifts and up to a lead of 1000 metres and earth filling in the depression/pit.
i) Girth from 300 mm to 600 mm | 850 | Each | 334.68 ₹2,84,478 Lowest | 334.68 ₹2,84,478 Lowest |
| 1.03 | ii) Girth from 600 mm to 900 mm | 212.5 | Each | 607.3 ₹1,29,051.25 Lowest | 607.3 ₹1,29,051.25 Lowest |
| 1.04 | iii) Girth from 900 to 1800 mm | 170 | Each | 1,167.8 ₹1,98,526 Lowest | 1,167.8 ₹1,98,526 Lowest |
| 2.00SH : Formation cutting | |||||
| 2.01 | Excavation in Hill Area in Soil by Mechanical Means (Excavation in soil in hilly area by mechanical means including cutting and trimming of side slopes and disposing of excavated earth with all lifts and lead upto 1000 metres) | 1,30,663.24 | Cum | 199.38 ₹2,60,51,636.79 Lowest | 203.75 ₹2,66,22,635.15 |
| 2.02 | Excavation in Hilly Area in Ordinary Rock by Mechanical Means not Requiring Blasting. (Excavation in hilly area in ordinary rock not requiring ballasting by mechanical means including cutting and trimming of slopes and disposal of cut material with all lift and lead upto 1000 metres ) | 1,25,375.28 | Cum | 289.91 ₹3,63,47,547.42 Lowest | 289.91 ₹3,63,47,547.42 Lowest |
| 2.03 | Deduct quantum of earthwork of all types disposal directly throwing into the valley without involving any lead and lift.
Ordinary and Hard Soil/Hard shale, soil containing shingle or small size boulders. | 52,265.3 | Cum | 86.46 ₹45,18,857.84 Lowest | 86.46 ₹45,18,857.84 Lowest |
| 2.04 | Deduct quantum of earthwork of all types disposal directly throwing into the valley without involving any lead and lift.
Ordinary and Hard Rock | 50,150.11 | Cum | 138.35 ₹69,38,267.72 Lowest | 138.35 ₹69,38,267.72 Lowest |
Tender Value
₹8.9 Cr
EMD Value
₹8.9 L
Closing Date
15 Mar 2025, 11:30 amClosed
Executive Engineer, Mariyang Division PWD,AP,Mrg.
Office of the Executive Engineer, Mariyang Division PWD, AP, Mariyang, PO/PS-Mariyang, District-Upper Siang, PIN-791002
Construction of road from Ropi to Ghero in Upper Siang District.
2025_PWDAP_2216_1
07/MRGD/SASCI/2024-25
Open Tender
Civil Works – Roads
Item Rate
547 days
Ropi to Ghero in Upper Siang District
Please refer Tender documents.
6 documents required · 6 mandatory
₹10,000
EE PWD Mariyang
₹8.9 L
22 Mar 2025
7 Mar 2025
15 Mar 2025
7 Mar 2025
15 Mar 2025
7 Mar 2025
Amount
SH: Jungle clearance
Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness. (Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness a) In area of thorny jungle
Cutting of trees, including cutting of trunks, branches and removal of stumps, roots, stacking of serviceable material with all lifts and up to a lead of 1000 metres and earth filling in the depression/pit. i) Girth from 300 mm to 600 mm
ii) Girth from 600 mm to 900 mm
iii) Girth from 900 to 1800 mm
SH : Formation cutting
Excavation in Hill Area in Soil by Mechanical Means (Excavation in soil in hilly area by mechanical means including cutting and trimming of side slopes and disposing of excavated earth with all lifts and lead upto 1000 metres)
Excavation in Hilly Area in Ordinary Rock by Mechanical Means not Requiring Blasting. (Excavation in hilly area in ordinary rock not requiring ballasting by mechanical means including cutting and trimming of slopes and disposal of cut material with all lift and lead upto 1000 metres )
Deduct quantum of earthwork of all types disposal directly throwing into the valley without involving any lead and lift. Ordinary and Hard Soil/Hard shale, soil containing shingle or small size boulders.
Deduct quantum of earthwork of all types disposal directly throwing into the valley without involving any lead and lift. Ordinary and Hard Rock
SH :- CC Drain
Earth work in excavation in foundation and trenches etc. in all kinds of soil (excluding soil containing 50% or more of shingle or small size boulders upto 30 cm size, saturated soil and rock), lift upto 1.50 m and stacking the excavated soil not more than 3 m clear from the edge of the excavation and returning the stacked soil in 15 cm layers, when required, into plinth sides of foundation etc consolidating each deposited layer by ramming and watering and then disposing of all surplus soil as directed within a lead of 50m.
Providing and laying cement concrete 1 : 2 : 4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) excluding the cost of centring an shuttering in: a) Foundations and plinth
Centering and shuttering including strutting , propping etc, and removal of form work for :- b) Walls including attached buttresses, pilasters etc.
I. 12 mm Cement plaster in CM 1:4 (1 Cement : 4 Sand)
A. Neat Cement Punning
SH :- Kutcha Drain
Excavation for Structures (Earthwork in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material.) Ordinary soil Mechanical Means upto 3 m depth
I. Ordinary rock not requiring blasting
SH :- Retaining/Breast wall
Excavation for structures) Earth work in excavation of foundation of structures as per drawing and technical epecification i/c setting out, construction of shoring and bracing, removal of stamps and other deleterious matterial, dressing of sites and bottom, and back filling with approved materials. i) Ordinary soil A) Manual Means i) upto 3 mtr Depth
PCC 1:3:6 in foundation( Plain Cement concrete 1:3:6 nominal mixed in foundation with crushed stone aggregate 40mm nominal mixed in foundation with crushed stone aggregate 40 mm nominal sizew mechanically mixed, placed in foundation and compacted by vibration i/c curing for 14 days
Stone masonry work in cement mortar 1:3 in foundation complete as per drawing and technical specification
Dry Rubble Masonry
Back filling behind abutment, w/wall and R/wall complete as per drawing and technical specification. A) Granular Material
Providing weep holes in brickmasonry/plain/reinforced concrete abutment, W/wall, R/wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1:V : 20H towards drawing face complete as per darwing and technical specification.
SH :- RCC Slab culvert-(1.5x1.5m)-2 Nos.
Excavation for Structures (Earthwork in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material.) I-Ordinary soil B-Mechanical Means (i) Depth up to 3 m
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.)
Stone masonry work in cement mortar 1:3 for substructure complete as per drawing and Technical Specifications Coursed rubble masonry (first sort )
Furnishing and Placing Reinforced/Prestressed cement concrete in super-structure as per drawing and Technical Specification A. RCC Grade M20 (q) Height 5m to 10m
Supplying, fitting and placing HYSD bar reinforcement in substructure complete as per drawing and technical specifications
Back filling behind abutment, wing wall and return wall complete as per drawing and Technical specification. A Granular material
Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return wall with 100mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical specifications
Ms Pamong Construction (BID ID -6612)
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.18 MB
TenderDoc.pdf
Tender Documents • 1.88 MB
BOQ_2377.xls
BOQ • 0.41 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .