Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹17.4 LAccepted-AOC | L1 | Accepted-AOC L1 accepted | |
| 2 | L2₹18.1 L+₹63,954 (3.67%)Rejected-Finance | L2 | Rejected-Finance Other than L1 | |
| 3 | L3₹18.4 L+₹99,000 (5.68%)Rejected-Finance | L3 | Rejected-Finance Other than L1 | |
| 4 | L4₹18.8 L+₹1.4 L (8.00%)Rejected-Finance | L4 | Rejected-Finance Other than L1 | |
| 5 | L5₹21.3 L+₹3.9 L (22.4%)Rejected-Finance | L5 | Rejected-Finance Other than L1 |
Tender Value
Refer Docs
EMD Value
₹62,600
Closing Date
19 May 2021, 6:00 pmClosed
GE North Akhnoor
GE North Akhnoor C/O 56 APO
MANNING AND OPERATIONS OF WATER SUPPLY INSTALLATION AT AKHNOOR UNDER GE NORTH AKHNOOR
2021_MES_433510_2
GE(N)/AKH-62/2020-21
Open Tender
Civil Works
Item Rate
330 days
Akhnoor
Class D cat d v
8 documents required · 8 mandatory
₹500
Yes
GE North Akhnoor
₹62,600
Yes
2 Jun 2021
4 May 2021
21 May 2021
4 May 2021
19 May 2021
4 May 2021
Amount
Maintenance and operation including controlling of valves of RCC over head tanks of capacity 50000 gallons at Ridge Area and PVC over head tank of capacity 4500 gallons at ASC Buttchery (The jobs includes daily cleaning of valve pits replacing of gland packing wherever required) for One shift (08 Hours Per shift) including Sunday and holidays by engaging one un- skilled labour per shift for smooth and efficient functioning of the installation including maintenance of documents as applicable.
Maintenance and operation for Tubewell No. 05 with one Semi-skilled labour per shift for Two shifts (08 Hours Per shift) including Sunday and holidays and maintance and operation of following equipment:- (a) Transformer 200 KVA- 01 No. (b) GOD 11000 Volts - 01 No. (c) Bore well with submersible pump 50 HP-02 No (One stand by). (d) Voltage stabilizer 63 KVA -01 No. (e) LT Panel complete with MCCBs and submersible pump starter -01 No.
Maintenance and operation for Stage III pump house with one semi skilled labour per shift for Two shifts ( 08 Hours Per shift) including Sunday and holidays and maintance and operation of following equipment:- (a) Transformer 100 KVA- 01 No (b) Transformer 250 KVA- 01 No. (c) GOD 11000 Volts - 01 No. (d) Voltage stabilizer 100 KVA -01 No (e) Voltage stabilizer 200 KVA -01 No. (f) DG set 125 KVA -01 No. (g) Centrifugal Pump set 75 HP-03 Nos. (h)Centrifugal Pump Set 50 HP-02 Nos (i) Bleaching Dozer -01 Nos. (j) Semi UG Tank 50000 glns -02 Nos. (k) LT Panel complete with MCCBs and starters -05 Nos.
Maintenance and operation for Pump house 6 with one semi skilled labour per shift for one shifts (08 Hours Per shift) including Sunday and holidays and maintance and operation of following equipment:- (a) Transformer 200 KVA- 01 No. (b) GOD 11000 Volts - 01 No. (c) Voltage stabilizer 150 KVA -01 No (d) Voltage stabilizer 100 KVA -01 No. (e) DG set 125 KVA -01 No. (f) Centrifugal Pump set 100 HP-03 Nos. (g) Borewell with submersible pump 41 HP-01 Nos (h) Semi UG Tank 50000 glns -02 Nos. (i) LT Panel complete with MCCBs and starters -04 Nos.
Maintenance and operation for comprehensive maintenance and repair to external water supply pipe line of area of Ridge line, Feild Park, Butchery,Army Dog unit, and water supply installation as stage I Tube Well No 3/5/6/7 area consisting of pumping, supply and distribution system, by engaging one team of one skilled labour as pipe fitter and one helper requisite manpower for One shift (08 Hours Per shift) excluding sundays and holidays complete all as directed by Engineer in charge.
Maintenance and operation for comprehensive maintenance and repair to external water supply pipe line of area of offrs mess, Med regt,EME bn,DOU area,CDS area, MH, FD Hosp, and water supply installation at stage II,consisting of pumping, supply and distribution system, by engaging one team of one skilled labour as pipe fitter and one helper requisite manpower for One shift (08 Hours Per shift) excluding sundays and holidays complete all as directed by Engineer in charge.
Maintenance and operation for comprehensive maintenance and repair to external water supply pipe lines of area of total Tanda area (except the area mentioned at Srl No 06 here-in-above) from GM Vihar up to SATA Battery including Stage III Pump House consisting pumping, supply and distribution system, in complete by engaging one team of one skilled labour as pipe fitter and one helper requisite manpower for One shift (08 Hours Per shift) excluding sundays and holidays complete all as directed by Engineer in charge.
Note for srl item No 1 to 7 (a) Rectification of minor faults in water supply installation will be the responsibility of the contractor's man power. (b) The T & P required to carry out the above work will be provided by the contractor. (c ) The safety precautions for the operator will be the responsibility of the contractor and the unit rate is deemed to be included for the safety eqpt/T & P. (d) The general cleanliness of the plants and equipments in the installation is the responsibility of the contractor. (e) Tradesman deployed must possess mobiles phone without camera. (f) FGM/Helper shall be deputed in other area GE (N) Akh for working as directed by JE E/M, AGE E/M, GE if necessary. (g) Contractor has to provided reliever and the cost of same deemed to be included. (h) All store/accessories be issued by dept for day to day maint. (j) A recovery @ Rs 300/- per day per complaint shall be recovered from the contractor if complain given to the contractor remains unattended/ not rectified at the end of the day. (k) Contractor has to provide Blue uniform for manpower to be employed and rates are included in quoted rate. (l) The contractor shall produce details of the persons like Name, Aadhar No, Aadhar linked Bank A/C No, EPF No and ESIC No within a week of Acceptance of tender. The work will be commenced only after submission of requisite documents.
Jiwan Singh
harish kumar and co
darshan kumar gandhi
ASIA ENTERPRISES
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .