| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹15.2 LAccepted-AOC | ₹15.2 L | L1 | Accepted-AOC L1 BIDDER |
| 2 | L2₹15.5 L+₹26,886.84 (1.77%)Rejected-Finance | ₹15.5 L+₹26,886.84 (1.77%) | L2 | Rejected-Finance 2 ND LOWEST BID |
| 3 | L3₹15.5 L+₹30,684.41 (2.02%)Rejected-Finance | ₹15.5 L+₹30,684.41 (2.02%) | L3 | Rejected-Finance 3 RD LOWEST BID |
Tender Value
₹15.2 L
EMD Value
₹30,381
Closing Date
2 Mar 2026, 11:00 amClosed
EE_COOCHBEHAR_IRRIGATION_DIVISION
EE_COOCHBEHAR_IRRIGATION_DIVISON_DEBIBARI_COOCH_BEHAR
M R to Santoshpur Embankment near Ch 600 m along the left bank of river Gadadhar within P.S- Tufanganj, Block - Tufanganj-I,Dist- Cooch Behar.
2026_IWD_998921_3
WBIW/EE/COB/e-NIT-18/2025-26
Open Tender
CIVIL WORKS
Percentage
90 days
Tufanganj-I
Please refer Tender documents.
8 documents required · 8 mandatory
₹30,381
Yes
30 Mar 2026
7 Feb 2026
2 Mar 2026
7 Feb 2026
2 Mar 2026
7 Feb 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Cutting and clearing jungles including shrubs, water weeds, bushes, trees, plants, upto 30 cm. girth including removing as directed by Engineer-in-charge.. | - | Sqm | 2.38 | - |
| 2 | Earthwork in excavation in the canals / drainage channels / borrow pits / River bed / slope of bank as noted below as per designed section &
throwing the spoils in layers of 25 cm. for making banks as per profile or to deposit the same in any other place within an initial lead of 30 metre and initial lift of 1.5 metre including breaking clods, rough dressing etc. complete as per direction of the Engineer-in-charge.
(a) Ordinary soil / local soil / soil mixed with moorum or kankar / silt, dry or moist / slushy silt / sticky soil. | 359 | Cum | 129.91 | ₹46,637.69 |
| 3 | Labour charges for collecting loose scattered laterite and stone boulders from slope, bed or apron and stacking the same above ground level within a lead of 100 metre and all lifts as per direction of the Engineer - in-charge. | 7 | Cum | 244.32 | ₹1,710.24 |
| 4 | Quarrying ,Carrying ,Supplying stone boulders/shingles from the Engineer in Charge selected quarrying site to the site of work including cost of materials,loading,unloading and carriage including all incidental charges like Royalty but excluding the cost of labour charges for laying boulder in apron or with in wire netting of sausage for slope pitching and all lifts & dressing the exposed faces etc. complete as per direction of the Engineer In Charge.(Quarry bed belongs to Forest Dept. Govt. Of WB) N.B.-The construction wing is to add royalty and other related fees at the presently prescribed rates for forest and non-forest area as stated below to arrive at the total rate at quarry side till such rates are modified by the forest department and department of industry, commerce and enterprises, Government of West Bengal.(a) for forest area royalty including entry fee and TP fee: Rs.178.33 per cum .b) For non-forest area Royalty: Rs. 106.00 per cum Royalty (including other charges where ever applicable) certificates in original from competent authority are to be submitted along with the bill, otherwise amount due towards Royalty (including othere charges where ever applicable, but excluding GST) will be deducted from the bills of works. a) Comprising Boulder above 30Kg each @ 60% , Boulder above 20Kg each @ 30% & Boulder above 10Kg each @ 10% | - | Cum | 1,549.86 | - |
| 5 | Making rectangular / circular sausage cage with 8 SWG galvanized iron wire of 150 mm. x 150 mm. mesh wire netting with proper lapping of minimum 150 mm including sewing the joints with 10 SWG G I wire and supply of all materials and equipments including placing the sausage cage in position, filling the same with boulder or lumpaggregatescomplete as per direction of the Engineer-in-charge but excluding thecost of boulder / lump aggregates and its carriage upto site.(Cost isexcluding the cost of end pieces) a)1.80metre x 0.60 metre nominal section | - | Metre | 997.54 | - |
| 5.01 | d)1.80metre x 0.45 metre nominal section. | - | Metre | 885.51 | - |
| 5.02 | h) 1.50 metre diameter. | - | Metre | 1,159.62 | - |
| 6 | Supplying, fitting, fixing end pieces for rectangular / square / circular sausages at the ends, with 10 SWG / 8 SWG G I wire net of different mesh sizes tying & sewing the same maintaning a lap langth of 150 mm all around with 12 SWG G I wire complete, including the cost of supply of wire netting,fitting etc, complete as per direction of the Engineer - in - charge.
d) Mesh size 150 mm x 150 mm with 8 SWG wire | - | Sqm | 143.02 | - |
| 7 | Quarrying, carrying, supplying stone boulders / shingles from the Engineer-in-charge selected quarrying site to the site of work including cost of materials, loading, unloading and carriage including all incidental charges like Royalty and including labour charges for laying boulders in apron or within wire netting of sausage for slope pitching and all lifts and dressing the exposed faces etc. complete as per direction of the Engineer-in-charge. (Quarry bed belongs to Forest Department, Govt. of WB) N.B. The construction wing is to add royalty and other related fees at the presently prescribed rates for forest and non-forest area as stated below to arrive at the total rate at quarry site till such rates are modified by the Forest Department and Department of Industry, Commerce & Enterprises, Government of West Bengal. (a) For Forest area Royalty including entry fee and TP fee : Rs. 178.33 per Cum (b) For Non-Forest area Royalty : Rs. 106.00 per Cum Royalty( including other charges wherever applicable) certificates in original from competent authority are to be submitted along with the bill, otherwise amount due towards Royalty( including other charges wherever applicable, but excluding GST) will be deducted from the bills of works .
a)Boulder above 30 Kg each 70% ,Boulder above 20 kg each 20 % , and Boulder above 10 kg each10% | - | Cum | 1,868.54 | - |
| 8 | Labour charge for dumping / laying of Laterite / Stone Boulders / Shingles / Brick Bats, from stack of worksite with all leads and lifts in water or spreading the same on the slope of the bank of River/Sea or the slope of the embankment or in the River/ Sea bed to an uniform thickness as per direction of the Engineer-in-charge including cost of all accessories and other incidental charges.
(a) Boulder 20kg & above where boats are not necessary. | - | Cum | 241.94 | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.26 MB
2911_agreement.pdf
Tender Documents • 2.94 MB
BOQ_2446319.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .