| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹8.9 CrAccepted-AOC | ₹8.9 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹9.1 Cr+₹14.6 L (1.63%)Rejected-Finance | ₹9.1 Cr+₹14.6 L (1.63%) | L2 | Rejected-Finance L2 |
| 3 | L3₹11.0 Cr+₹2.1 Cr (23.2%)Rejected-Finance | ₹11.0 Cr+₹2.1 Cr (23.2%) | L3 | Rejected-Finance L3 |
| Sl No | Description | Qty | Unit | Traders and Engineers Private Limited L2 | GBC INFRASTRUCTURE PRIVATE LIMITED L3 | Pathak Utility Private Limited L1 |
|---|---|---|---|---|---|---|
| 1.00 | Supply, delivery , storage, installation, testing & commissioning of 4 panel HT VCB switch board , having voltage level 6 KV , at 50 Hz, with fault level 40 KA to complete as per technical specification and direction of EIC. | 1 | set | 36,00,000 ₹36,00,000 Lowest | 40,00,000 ₹40,00,000 | 48,01,290 ₹48,01,290 |
| 2.00 | Supply, delivery, installation of LT PDB for Substation
in view of supplying power to the PMCC at annex
building , keeping provision for feeding the plant by
partially loading both the transformer or from a single
transformer if required to complete . The new panel will be able to cater all the existing outgoing loads of the old panel.
The new panel has to be designed keeping in mind
that it should fit in the space of the Old Panel. | 1 | set | 31,26,600 ₹31,26,600 Lowest | 40,00,000 ₹40,00,000 | 1,12,09,004 ₹1,12,09,004 |
| 3.00 | Supply , delivery ,storage, installation of 110 Volt , DC, 100 AH sealed maintenance free battery comprising of 55 no 2 volt cells with float cum boost battery charger cum DCDB panel as per specification, technical offer and as directed by EIC. | 1 | job | 4,50,000 ₹4,50,000 Lowest | 5,00,000 ₹5,00,000 | 13,94,590 ₹13,94,590 |
| 4.00 | Supply, delivery, installation of LT PMCC for Annex
Building as per existing LT Panel. The new panel will be
able to cater all the existing outgoing loads of the old
panel including blower motor feeders, backwash
pump feeders, surface wash pump feeders, flash
mixtures, agitators etc. to complete as per direction of EIC and technical specification. The new panel has to be designed keeping in mind the available space in the
existing building. | 1 | set | 40,26,600 ₹40,26,600 | 75,00,000 ₹75,00,000 | 26,30,683 ₹26,30,683 Lowest |
| 5.00 | Supply, delivery, installation of LT PMCC for Chemical
House as per existing LT Panel. The new panel will be
able to cater all the existing outgoing loads of the old
panel including alum tank filling pumps and agitators
etc.as per direction of EIC. The new panel has to be designed keeping in mind the available space in the existing building. | 1 | set | 18,00,000 ₹18,00,000 | 15,00,000 ₹15,00,000 | 9,17,345 ₹9,17,345 Lowest |
| 6.00 | Supply, delivery, installation of LT PMCC for Sludge
Pumping as per existing LT Panel. The new panel will
be able to cater all the existing outgoing loads of the
old panel including sludge pump motors, air blowers
etc. and as per direction of EIC. The new panel has to be designed keeping in mind the available space in the existing building. | 1 | set | 18,00,000 ₹18,00,000 | 15,00,000 ₹15,00,000 | 9,17,345 ₹9,17,345 Lowest |
| 7.00 | Supply, delivery, installation of LT PMCC outdoor type
for Clariflocullator as per existing LT Panel. The new
panel will be able to cater all the existing outgoing
loads of the old panel including scrapper drives,
flocullator etc. as per direction of EIC . The new panel has to be designed keeping in mind the available space in the existing building. | 2 | set | 4,50,000 ₹9,00,000 | 6,00,000 ₹12,00,000 | 3,39,872 ₹6,79,744 Lowest |
| 8.00 | Supply, delivery, installation of Control Desk for the Water
Treatment Plant annex building as per existing drives/Loads set up and as per direction of EIC and tech. specification. | 1 | set | 27,00,000 ₹27,00,000 | 30,00,000 ₹30,00,000 | 20,01,474 ₹20,01,474 Lowest |
| 9.00 | Supply , delivery and installation of LOH with all fittings and fixtures suitable for mounting on filter control console complete with necessary pipe fittings and valves as per existing set up to complete as per direction of EIC. | 12 | set | 2,70,000 ₹32,40,000 | 2,00,000 ₹24,00,000 | 1,34,926 ₹16,19,112 Lowest |
| 10.00 | Supply , delivery and installation of ROF with all fittings and fixtures suitable for mounting on filter control console complete with necessary pipe fittings and valves as per existingas per existing set up to complete as per direction of EIC. | 12 | set | 1,80,000 ₹21,60,000 | 2,00,000 ₹24,00,000 | 1,00,397 ₹12,04,764 Lowest |
Tender Value
Refer Docs
EMD Value
₹10 L
Closing Date
26 Mar 2025, 3:00 pmClosed
SE(E/M)-I, KMDA
OFFICE OF THE SUPERINTENDING ENGINEER (E/M)-I, E-M SECTOR, K.M.D.A. UNNAYAN BHAVAN, 6th FLOOR, SALT LAKE CITY, KOLKATA 700 091.
Rejuvenation and Stabilization with supply, delivery, installation, repairing, overhauling and renovation of the Electromechanical equipment of 30 MGD Water Treatment Plant (WTP) at Padmapukur under Howrah by Replacement and Renovation etc....
2025_KMDA_808751_1
29/SE (E/M)-I /KMDA/WTP (30 MGD)/Howrah/2W-15/2023-24 Date- 24/01/2025
Open Tender
Miscellaneous Works
Item Rate
365 days
Padmapukur
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹10 L
OFFICE OF THE SUPERINTENDING ENGINEER (E/M)-I
20 Jan 2026
31 Jan 2025
28 Mar 2025
31 Jan 2025
26 Mar 2025
31 Jan 2025
10 Feb 2025
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Supply, delivery , storage, installation, testing & commissioning of 4 panel HT VCB switch board , having voltage level 6 KV , at 50 Hz, with fault level 40 KA to complete as per technical specification and direction of EIC. | |||||
| 2Supply, delivery, installation of LT PDB for Substation in view of supplying power to the PMCC at annex building , keeping provision for feeding the plant by partially loading both the transformer or from a single transformer if required to complete . The new panel will be able to cater all the existing outgoing loads of the old panel. The new panel has to be designed keeping in mind that it should fit in the space of the Old Panel. | |||||
| 3Supply , delivery ,storage, installation of 110 Volt , DC, 100 AH sealed maintenance free battery comprising of 55 no 2 volt cells with float cum boost battery charger cum DCDB panel as per specification, technical offer and as directed by EIC. | |||||
| 4Supply, delivery, installation of LT PMCC for Annex Building as per existing LT Panel. The new panel will be able to cater all the existing outgoing loads of the old panel including blower motor feeders, backwash pump feeders, surface wash pump feeders, flash mixtures, agitators etc. to complete as per direction of EIC and technical specification. The new panel has to be designed keeping in mind the available space in the existing building. | |||||
| 5Supply, delivery, installation of LT PMCC for Chemical House as per existing LT Panel. The new panel will be able to cater all the existing outgoing loads of the old panel including alum tank filling pumps and agitators etc.as per direction of EIC. The new panel has to be designed keeping in mind the available space in the existing building. | |||||
| 6Supply, delivery, installation of LT PMCC for Sludge Pumping as per existing LT Panel. The new panel will be able to cater all the existing outgoing loads of the old panel including sludge pump motors, air blowers etc. and as per direction of EIC. The new panel has to be designed keeping in mind the available space in the existing building. | |||||
| 7Supply, delivery, installation of LT PMCC outdoor type for Clariflocullator as per existing LT Panel. The new panel will be able to cater all the existing outgoing loads of the old panel including scrapper drives, flocullator etc. as per direction of EIC . The new panel has to be designed keeping in mind the available space in the existing building. | |||||
| 8Supply, delivery, installation of Control Desk for the Water Treatment Plant annex building as per existing drives/Loads set up and as per direction of EIC and tech. specification. | |||||
| 9Supply , delivery and installation of LOH with all fittings and fixtures suitable for mounting on filter control console complete with necessary pipe fittings and valves as per existing set up to complete as per direction of EIC. | |||||
| 10Supply , delivery and installation of ROF with all fittings and fixtures suitable for mounting on filter control console complete with necessary pipe fittings and valves as per existingas per existing set up to complete as per direction of EIC. | |||||
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tenderdocument.pdf
Tender Documents • 3.09 MB
BOQ.xls
BOQ • 0.37 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .