| 1 | L1₹9.2 LAccepted-AOC DHOTI VINDHYANAGAR WAIDHAN DIST SINGRAULI M P 486886 | WAIDHAN | SINGRAULI | MADHYA PRADESH | 486886 | L1 | Accepted-AOC As per TC recommendation and approval. | |
| 2 | L2₹9.2 L+₹1.4 L (18.5%)Rejected-Finance SHUKIA MORE MORWA DISTT SINGRAULI MP | MORWA | SINGRAULI | MP | L2 | Rejected-Finance As per NIT |
Tender Value
₹10.8 L
EMD Value
₹13,500
Closing Date
30 Aug 2024, 10:00 amClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
M K Pandey
O/o AGM, Bina Area, NCL, District Sonebhadra (UP), Pincode 231220
Repairing work that includes repairing and plates changing horizontal and vertical (20 mm to 50 mm) of Drag, Hoist, Walk and Swing system and cracks repairing and plates changing of machine body outer below house area of inner machine house of ballas
2024_NCL_315153_1
Bina/SO(Excv)/Tender/24-25/35 dt 14.08.2024
Open Tender
Excavation Department Work
Item Rate
31 days
Bina Project, NCL
As per NIT
5 documents required · 5 mandatory
₹13,500
14 Nov 2024
14 Aug 2024
31 Aug 2024
15 Aug 2024
30 Aug 2024
15 Aug 2024
15 Aug 2024 - 22 Aug 2024
Amount
Repair of cracks of vertical and horizontal plates of outer rotating bodies at many places and changing of plates which are prone to frequent cracks generation (16 mm to 20mm plates) and repairing of all cracks nearby rail path areas. Repair of plates and changing of plates of counterweight areas (20mm to 50mm) and ballast box area with replacement of old cracked plates with new plates. Repairing of cracks of newly developed cracks at King post assembly and Centre Hall Assembly.
Labour charges for the work (Labour consists of 03 nos. Skilled fitter / Grinderman for a period of 24 shiftdays i.e. 2 shift X 12 days, 03 nos. Welder for a period of 24 shiftdays i.e. 2 shift X 12 days, 04 nos. Semi-Skilled for a period of 24 shiftdays i.e. 2 shift X 12 days, 03 nos. Unskilled for a period of 24 shiftdays i.e. 2 shift X 12 days and 01 no. Supervisor for a period of 24 shiftdays i.e. 2 shift X 12 days)
Applicable contractors profit
Replacement and crack repairing of 50mm plates of Hoist & Drag system foundation assemblies including plates below Hoist and Drag gearbox, Hoist & Drag pedestal systems and motor foundation assembly with proper alignment of plates after repairing. Cracks repairing and plates changing below and nearby areas of walk assembly with proper alignment after work completion. Replacement of aged vertical plates (04 Nos: 2-meter X1.5-meter X 20 mm each approx.) of L-16 girders of house deck of machines, fabrication of doors with 20mm plates in place of old and cracked doors of lower house deck.
Labour charges for the work (Labour consists of 04 nos. Skilled fitter / Grinderman for a period of 26 shiftdays i.e. 2 shift X 13 days, 03 nos. Welder for a period of 26 shiftdays i.e. 2 shift X 13 days, 04 nos. Semi-Skilled for a period of 26 shiftdays i.e. 2 shift X 13 days, 04 nos. Unskilled for a period of 26 shiftdays i.e. 2 shift X 13 days and 01 no. Supervisor for a period of 26 shiftdays i.e. 2 shift X 13 days)
Applicable contractors profit
Repairing work of cracks below and nearby areas of swing system assembly including swing shaft housing cracks repairing, Cracks repairing of vertical and horizontal 20mm plates at different positions and vertical plates changing of swing area which are having multiple cracks and are beyond repairing and crack repairing of entry doors.
Labour charges for the work (Labour consists of 03 nos. Skilled fitter / Grinderman for a period of 12 shiftdays i.e. 2 shift X 6 days, 03 nos. Welder for a period of 12 shiftdays i.e. 2 shift X 6 days, 03 nos. Semi-Skilled for a period of 12 shiftdays i.e. 2 shift X 6 days, 03 nos. Unskilled for a period of 12 shiftdays i.e. 2 shift X 6 days and 01 no. Supervisor for a period of 12 shiftdays i.e. 2 shift X 6 days)
Applicable contractors profit
Material Charges
Welding Electrode: 660NH 4.0 mm
Types of test required
D P Test
Stress relieving by controlled cooling
Hiring Charges
03 nos. of welding machine with accessories
03 nos. Gas cutting set with accessories
02 nos. Grinder machine with stone
03 nos. Hand lamp with holder
Misc. tools and tackles like chipping hammers, tie rods, wedges, hammers. Crowbars, alignment tools, heating oven for electrodes etc.
03 nos. of exhaust fan
Transportation charges
Total impact of GST for the purpose of CTC
Kohli Engineering Company
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_326598.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .