| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.9 LAccepted-AOC | L1 | Accepted-AOC Accepted | |
| 2 | L2₹4.0 L+₹7,863.20 (2.02%)Rejected-Finance | L2 | Rejected-Finance High price |
| Sl No | Description | Qty | Unit | MR.VIJAAY, CONTRACTOR L1 | MS SURIYA CONSTRUCTION L2 |
|---|---|---|---|---|---|
| 1.00 | Earth work excavation in all soils such as red earth ,hard stiff clay soil, stiff black cotton soil, hard redearth,shales, murrams, gravel,hard rock not requiring blasting ete complete., | 9.76 | Cum | 263 ₹2,566.88 Lowest | 300 ₹2,928 |
| 2.00 | Cement concrete 1 : 4 : 8 mix using 40mm HBG metal including cost and conveyance of all materials to site including labour for mixing laying curing etc complete | 3.18 | One cubic metre | 5,586 ₹17,763.48 Lowest | 5,600 ₹17,808 |
| 3.00 | Random Rubble Masonry in cement Mortar 1 : 5 for foundation and basement using new stones including necessary provision for bond stones with simultaneous flush pointing with the same mortar above ground level complying with standard specifications. | 9.43 | One cubic metre | 5,975 ₹56,344.25 Lowest | 6,000 ₹56,580 |
| 4.00 | Supplying and filling foundation and basement with excavated earth well rammed, watered and compacted complete complying with stanard specification. | 2.94 | One cubic metre | 45 ₹132.3 Lowest | 50 ₹147 |
| 5.00 | Brick work in CM 1:5mix using country bricks ground moulded of size 23 x 11 x 7cm for the following including curing etc., complete complying with standard specifications. | 11.9 | One cubic metre | 6,118 ₹72,804.2 Lowest | 6,200 ₹73,780 |
| 6.00 | Reinforcement Cement concrete 1:1 1/2:3 using 20mm ISS HBG metal for all RCC item of works excluding cost of Rein forcement and fabricating charges, centering and shuttering but including curing and providing fixtures like fan clamps in the RCC floor or r | 2.75 | Cum | 9,197 ₹25,291.75 Lowest | 9,200 ₹25,300 |
| 7.00 | Supplying and Fabricating and placing in position MS steel or ribbed for steel for all reinforced cement concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification. | 350 | Kg | 91.5 ₹32,025 Lowest | 92 ₹32,200 |
| 8.00 | Supplying & Erecting centering for sides & soffits including necessary supports & strutting upto 3.29m height for plane surfaces in all floors with all cross bracings using mild steel sheets of size 90 x 60cm & 10 gauge stiffened, welded with steel angle | 15.59 | Sqm | 1,095 ₹17,071.05 Lowest | 1,100 ₹17,149 |
| 9.00 | Supplying and applying of two coats of putty of 3mm thick over the exposed RCC surface of ceiling including finishing the joints smoothy with grinding machine and the surface shall be thoroughly cleaned out of dust and scrubbing. The Surface shall then be allowed to dry for atleast 48 hours. It shall then be sand papered (waterproof abrasive sheet) to give a smooth and even surface. Any unevenness shall be made good by applying 1st coat of putty mixed with water on the entire surface including filling up the undulations and applying 2nd coat of putty after 6 hours of 1st coat of putty and then sand papering (waterproof abrasive sheet) the same after it is dry and finishing the surface smoothly, etc., complete. | 13.17 | Sqm | 309 ₹4,069.53 Lowest | 320 ₹4,214.4 |
| 10.00 | Plastering with Cement Mortar 1:5, 12mm thick Superstructure complying with standard specifications as directed etc., complete. | 107.89 | Sqm | 284.5 ₹30,694.71 Lowest | 300 ₹32,367 |
Tender Value
Refer Docs
EMD Value
₹5,000
Closing Date
11 Dec 2025, 3:00 pmClosed
Block Development officer (B.Pt), Kalakad
Main road, North Salaipudur, Kalakad
Construction of toilet at Rajaputhur near Community hall in Thalavaipuram Panchayat
2025_RDTN_626621_1
A2/352/2025 15th CFC (Dt.Pt)
Open Tender
Civil Works
Works
Rajapudur
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹5,000
17 Dec 2025
26 Nov 2025
11 Dec 2025
26 Nov 2025
11 Dec 2025
26 Nov 2025
Amount
Earth work excavation in all soils such as red earth ,hard stiff clay soil, stiff black cotton soil, hard redearth,shales, murrams, gravel,hard rock not requiring blasting ete complete.,
Cement concrete 1 : 4 : 8 mix using 40mm HBG metal including cost and conveyance of all materials to site including labour for mixing laying curing etc complete
Random Rubble Masonry in cement Mortar 1 : 5 for foundation and basement using new stones including necessary provision for bond stones with simultaneous flush pointing with the same mortar above ground level complying with standard specifications.
Supplying and filling foundation and basement with excavated earth well rammed, watered and compacted complete complying with stanard specification.
Brick work in CM 1:5mix using country bricks ground moulded of size 23 x 11 x 7cm for the following including curing etc., complete complying with standard specifications.
Reinforcement Cement concrete 1:1 1/2:3 using 20mm ISS HBG metal for all RCC item of works excluding cost of Rein forcement and fabricating charges, centering and shuttering but including curing and providing fixtures like fan clamps in the RCC floor or r
Supplying and Fabricating and placing in position MS steel or ribbed for steel for all reinforced cement concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.
Supplying & Erecting centering for sides & soffits including necessary supports & strutting upto 3.29m height for plane surfaces in all floors with all cross bracings using mild steel sheets of size 90 x 60cm & 10 gauge stiffened, welded with steel angle
Supplying and applying of two coats of putty of 3mm thick over the exposed RCC surface of ceiling including finishing the joints smoothy with grinding machine and the surface shall be thoroughly cleaned out of dust and scrubbing. The Surface shall then be allowed to dry for atleast 48 hours. It shall then be sand papered (waterproof abrasive sheet) to give a smooth and even surface. Any unevenness shall be made good by applying 1st coat of putty mixed with water on the entire surface including filling up the undulations and applying 2nd coat of putty after 6 hours of 1st coat of putty and then sand papering (waterproof abrasive sheet) the same after it is dry and finishing the surface smoothly, etc., complete.
Plastering with Cement Mortar 1:5, 12mm thick Superstructure complying with standard specifications as directed etc., complete.
Providing granolithic floor finish in cement concrete 1:2:4 mix using 10-12 mm ISS metal to 25mm thick including cost and conveyance of all materials to site and all labour charges for mixing laying curing etc complete for 10 cum
Paving the Floor with scratch proof ceromic tiles of size 305x305x6mm including cost and conveyance of all materials to site and all labour charges etc complete
Dadooing of walls with Colour glazed tiles of size 15 cm x15cmx6mm laid in CM 1:2, 10mm thick & pointing with white cement using 0.4kg/cm2 including cost and conveyance of all materials to site and all labour charges etc complete
Painting two coats with oil bound distemper in all floors including brushes etc ., complete etc ( Inner wall )
Painting two coats with exterior emulsion in all floors including brushes etc ., complete etc
Supplying and fixing in positon Indian Water Closet (Oriya type) of size 580 x 440mm colour glazed earthern ware of approved quality and brand with "P" or "S" trap conforming to BIS with sand cushion and forming flooring alround the closet using 40mm brok
Provision for EWC
Solid PVC Door Shutters using 19 Gauge 19mm MS square tubes for styles and outer frames. 15mm MS square tubes for top, lock and bottom rails. The steel tubes shall be covered with 5mm thick solid PVC Sheets.Shutter using 5mm thick solid PVC Sheets for panelling shall rigidly fixed in position including necessary furniture and fittings.
Finishing the top of roof with one course of PRESSED TILES of size 23 cm X 23 cm X 2 cm laid in cement mortar 1:3 (One cement and three Sand) 12mm thick mixed with water proofing compound conforming to I.S. at 2% by weight.
MS SURIYA CONSTRUCTION (BID ID -1530337)
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_749257.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.67 MB
BOQ_749257.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .