| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹82.5 LAccepted-AOC | ₹82.5 L Quoted ₹83.2 L | L1 | Accepted-AOC Accepted-Finance |
| 2 | L2₹91.2 LRejected-Finance | ₹91.2 L | L2 | Rejected-Finance Not Lowest |
| 3 | L3₹94.1 LRejected-Finance | ₹94.1 L | L3 | Rejected-Finance Not Lowest |
Tender Value
₹1.2 Cr
EMD Value
₹7.9 L
Closing Date
24 Mar 2026, 12:00 pmClosed
Superintending Engineer Deoria Circle PWD Deoria
Office of The Superintending Engineer Deoria Circle PWD Deoria
Construction work of Padri Piparpati to Judhawaniya Ahir Tola via Nauka Tola Link road in Dist Kushinagar
2026_CEGKP_1125671_6
972/76yat-Deo Circle/26 Dated 28.02.2026
Open Tender
Civil Works
365 days
Kushinagar
Please refer Tender documents.
3 documents required · 3 mandatory
₹2,714
₹7.9 L
Deoria
25 May 2026
16 Mar 2026
24 Mar 2026
16 Mar 2026
24 Mar 2026
16 Mar 2026
23 Mar 2026
Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1. (Excluding GST)
(A) By Mix in Place Method Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per MORD Technical Speicification Clause 401 (Excluding GST)
Providing, laying, spreading and compacting stone aggregates of 45-63mm to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, screening Type-B to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 2 as per Technical Specification Clause 405. (Excluding GST)
Providing, laying, spreading and compacting stone aggregates of 22.4-53mm size to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, screening Type-B to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification Clause 405. (Excluding GST)
Brick edging on both side of theS.O.B. brick 8 cm. (3") wide and 12 cm. (4 1/2) deep laid with mud mortar all labour finished to the required template and in proper alignment and also including dressing and ramming the excavated earth including all labour T & P sudries required for proper completion of the work as per S.O.R. 2014 S.I. No. 765 (Excluding GST)
Providing and applying Primer coat with bitumen emulsion on prepared (SS-2) on prepared surface of granular base including clearing of road surface and spraying primer at the rate of 0.70 kg / sqm using mechanical means. As per technical specification clause 502 (Excluding GST)
Providing and applying tack coat with bitumen (VG-10)using bitumen pressure distributor at the rate of 0.35 kg per sqm on the prepared bituminous surface cleaned with Hydraulic broom as per Technical Speicification Clause 503 including cost of bitumen (VG-10) (Excluding GST)
Providing, laying and rolling of open-graded premix carpet of 20mm thickness composed of 13.2 to 5.6 mm aggregates either using penetration grade bitumen or emulsion to required line grade and level to serve as wearing coarse on a previously Prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 80-100kN static roller capacity finished to required lavel and grades to be followed by seal coat as per Techincal Specification clause 508 including cost of bitumen (Excluding GST)
Providing and applying seal coat type "C" comprising of a layer of bituminous binder followed by a cover of stone chipping of specified grading and rolling with power roller 8-10 tonne kN Static roller and finishing to required level and grades as per Technical Specification Clause 510 including cost of bitumen (Excluding GST)
(Construction of subgrade and Earthen shoulders) Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1. (Excluding GST)
Box Culvert 1x3 m Span- Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202. (Excluding GST)
Sand Fillling in foundation trenches as per drawing and technical specification Clause 305.3.9 (Excluding GST)
Providing and laying Cement Concrete 1:3:6 (1 cement :3sand : 6graded Stone aggregate 40 mm nominal size) including supply of all materials, labour and T&P etc. required for proper completion of work and curing complete, also including cost of formwork in foundation and floors as per SI no.281
M-30 Providing and laying reinforced cement concrete in superstructure as per drawing and technical specifications Clauses 800, 1205.4 and 1205.5 (Excluding GST)
Supplying, fitting and placing TMT bar reinforcement in foundation complete as per drawings and technical specifications Clauses 1000 and 1202 (Excluding GST)
Backfilling behind abutment, wing wall and return wall complete as per drawings & technical specification Clause 1204.3.8 (Excluding GST)
Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical Specifications (Excluding GST)
Brick on edge pavement on patries with bricks laid dry, joints filled with local sand including preparation of base to proper slope and its ramming, spreading a layer of 1 cm. 3/8" depth of local sand over the subgrade & including supply of all materials. As per SI. 763 (Excluding GST)
600 mm Hume Pipe- Plain cement concrete M10(1:3:6 nominal mix) in levelling course below open foundation of head wall as per drawing and technical specification clause 1109.(Excluding GST)
Brik Masonry Work in cement mortar (1:4) in foundation of head walls complete excluding poining and plastering as per rawing and technical specification Clause 1109 (Excluding GST)
Pointing with cement mortar (1:3 ) on brick work as per drawing and Technical Specifications Clauses 613.3 7 1204. As per MoRD Sl. No.-12.2 and Specification no.- 600. (Excluding GST)
Providing and laying reinforced cement concrete pipe NP3 600 mm dia. for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets Clause 1106 (Excluding GST)
Maintenance of constructed road for next five year after completion of work shall be paid. as per GO No 17/2024/lk0-113/23-1-2024-23-1099-113/2023 yksd fuekZ.k foHkkx vuqHkkx–1 fnuakd 16-01-2024 yoa dk;kZy; izeq[k vfHk;Urk ;krk;kr oxZ yks0fu0fo0 y[kuÅ dk i=kad& 3689lh@ vks0ih0vkj0ye0lh0@ewy@23&24 fnuakd 17-02-2024- Payment shall be done as per satisfaction of engineer in chage regarding maintenance work carried out by contractor (Including Labour Cess but GST will paid extra as applicable). 1st year Maintenance cost total construction of cost Item No. 1 to 22 @ Zero percent & for 2nd year @ 0.75%
For 3rd year @ 1.50%
For 4th year @ 2.25%
For 5th year @ 3.00%
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 11.39 MB
Tendernotice_2.pdf
PDF • 8.83 MB
BOQ_2098712.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid