Tender Value
₹10 L
EMD Value
₹10,000
Closing Date
12 Dec 2022, 12:00 pmClosed
SE, EUDC, Firozabad
SE, EUDC, Firozabad
electrification work to give proper electric supply to various connections under full deposit scheme in the jurisdiction of EUDD-I, Firozabad
2022_DVVNL_749435_1
EUDC/F/T-18/2022-23
Open Tender
Electrical Works
Lump-sum
365 days
Firozabad
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,180
Superintending Engineer, EUDC, Firozabad
₹10,000
14 Dec 2022
15 Nov 2022
12 Dec 2022
15 Nov 2022
12 Dec 2022
15 Nov 2022
Cartage including loading unloading & Proper Stacking of following stock materials from store center departmental store to dump site distance 0 to 20Kms
ST POLE 9/11 Mtr long
LT Cable 3.5x50/70sqmm
11KV HT Cable 3x70/120 sqmm/300 Sqmm
11KV Metering cubical
11KV CT&PT Unit
Transformer 25kva
Transformer 63kva
Fabrication, erection of sub -station Double pole on 11 mtr longST Pole/PCC Pole 8.5mtr long with fixing of necessories clamps, accessories required including supply and fixing of straight MS 100X50MM.(2240MM LONG) 2 nos . with arrangment of fixing 3 nos. pin insulator, grouting in 1:2:4 cement sand brick and ballast and making of plinth 300mm above ground level along with D.O fuse set as per RESSPO spenc. & direction of E/I ST pole shall be supplied by the depth.
Fabrication, erection of single 11 Mtr long ST Pole with fixing of X-arm with necessary clams, accessories required including supply and fixing & digging of pit and fixing of all accessories clamps as well as gouting and plinthilng of pole as per RESSPO Norms.Only pole shall be supply by deppt.
Grouting & binding of stay set in 1:4:8 ratio with cement,sand,and brick,ballast including cost of all grouting meterials as per RESSPO
Earthing of pole by M.S Earthing Rod.
Stringing,sagging,binding and jumpering of 3x95/120 Sq mm AB Conductor with the help of All type of clamps (cost of clamps shall be borne by the contractor)
Laying, Stringing, sagging, binding and jumpering etc of conductor on the erected supports Weasel Conductor/Dog Conductor
Mounting of 25 KVA T/F as per RESPO Norms
Mounting of 63 KVA T/F as per RESPO Norms
Mounting of 100 KVA T/F as per RESPO Norms
Laying of 11 kv 3x70/120mm XLPE Cable in single circuit By Drilling method under ground and approximate 1 mtr depth including digging of trech cutting of road with leying of as per agriment norms
Laying of 11 kv 3x70/120mm XLPE Cable in Single circuit by Manual Method under ground and approximate 1 mtr depth including digging of trech cutting of road with leying of as per norms
Laying of 11 kv 3x70/120mm XLPE Cable in double circuit by Manual Method under ground and approximate 1 mtr depth including digging of trech cutting of road with leying of as per norms
Hosting of 11kv cable along with providing of G.I. pipe 3 diax3mtr cost of accessories will be born by the contractor as per respo norms
Pipe Type earthing 20mtr deep boring and providing G.I. pipe 1.5 dia of ISI make and GI Strip 25x5mmx6 mtr long attached with clamps L Nut bolts and GI pipe All material shall be supplyed by the contractor
Instalation and commissioning of CT/PT Metering unit including its connection in between TVM Meter and CT/PT unit with required size of copper cable. Cable will be arranged by the contractor at his own cost
Fixing of metering cubical 11kv
Providing and fixing of 11 kv TPMO Set with all accessories and clamps (all material shall be borne by the contractor ) as per RESSPO Norms
Supply and Fixing 11 KV D.O. Fuse Set.
Tapping of line
SAMADHIYA ENTERPRISES
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .