| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹5.2 LAccepted-AOC | 1 | Accepted-AOC Accepted | |
| 2 | 2₹5.7 L+₹47,084.81 (9.04%)Accepted-AOC | 2 | Accepted-AOC Accepted | |
| 3 | Not Admitted-Fee/PreQual/Technical PLEASE PROVIDE THE DOCUMENT CONTAINING THE ADDRESS | NEW DELHI | DELHI | 110001 | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹6.5 L
EMD Value
₹13,000
Closing Date
17 Feb 2020, 9:00 amClosed
EE MGCCD-7 Bijnor
EE MGCCD-7 Bijnor
Const. of canal from km 0.230 to km 0.280 VRB 0.255 of Sherpur Mr.
2020_UPIDC_433284_2
03/EE/2019-20
Open Tender
Civil Works - Canal
Item Wise
90 days
Sambhal
Please refer Tender documents.
2 documents required · 2 mandatory
₹354
EE MGCCD7 Bijnor
₹13,000
Yes
9 Jul 2020
12 Feb 2020
17 Feb 2020
12 Feb 2020
17 Feb 2020
12 Feb 2020
Amount
Earth work in embankment in ordinary soil in 20 cm layer including ramming and dressing the surface to be required level and slope also including carriage 600 M up to work site with all lead and lift, royalty and all taxes complete as per directed by Engineer-in-Charge.
Earth work in excavation in foundation in ordinary soil with wet earth & disposal within 30 M.
Cement concrete in 1:6:12 including all cost of material, labour , T&P etc. for completion of work per cum.
Cement concrete in 1:3:6 including all cost of material, labour , T&P etc. for completion of work per cum.
Cement concrete in 1:2:4 (M-15) including all cost of material, labour , T&P etc. for completion of work per cum.
First class brick work in 1:4 C.M. including all cost of material, labour and T&P etc. for proper completion of work. Per cum
Centering & Shuttering including all cost of material, labour and T&P etc. for proper completion of work. per Sqm.
For CC Work
For RCC Work
Cement concrete with stone ballast in R.C.C. 1:1.5:3 (M-20) including all cost of material, labour , T&P etc. for completion of work per cum.
Supply and laying steel reinforcemet with cutting, binding, & placing includign cost of binding wire, steel, labour and T&P etc. complete.
Cement concrete in 1:1.5:3 (M-20) including all cost of material, labour , T&P etc. for completion of work per cum.
Cement pointing in 1:2 (struck deep) on brick masonry i/c cost of all material, labour, T&P etc for completion of work.
S/F of 75 mm dia G.I.pipe as drainage spout icluding cost of all material, labour and T&P etc. for proper completion of work. R/M
Supply and laying Tarfelt sheet in two layers on Bed Block including all cost of material, labour and T&P etc. complete. Per sqm.
Supply and laying thermocoal sheet in expanson joint including all cost of material, labour and T&P etc. complete. Per sqm.
Supply and fixing wheel gaurd including all cost of material, labour and T&P etc. complete. Per No..
Earth work in filling in Ramp and diversion including ramming and dressing the surface to be required level and slope also including carriage 600 M up to work site with all lead and lift, complete as per directed by Engineer-in-Charge.
Suplying and laying of R.B.M. over diversion including cost of all material, labour and T&P etc. complete.
Dry brick on edge soling laid dry filling joints including all cost of material, labour and T&P etc. all complete. Per sqm.
Filling of expansion Joint with bitumen and saw dust including all cost of material, labour and T&P etc. complete. Per No..
Supply and fixing diversion Board including all cost of material, labour and T&P etc. complete. Per No..
Removal of diversion including 1.50 m lift and up to 100 m lead.
M/S VIPIN KUMAR CONTRACTOR
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .