| Sl No | Description | Qty | Unit | palani L2 | K.Moorthy L1 |
|---|---|---|---|---|---|
| 1.00Provision for 2000 Litr Sintex, Shower and Existing Compound Painting at Kilkandigai in Chitheri Panhayat | |||||
| 2.00 | Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth, earth mixed with small sized boulders and hard gravelly soil as per SS 20B | 12.5 | cum | 260 ₹3,250 Lowest | 260 ₹3,250 Lowest |
| 3.00 | Cement Concrete 1:4:8 mix using 40mm metal including cost and conveyanceof all materials to work site and all labour charges etc. | 3.07 | cum | 5,818 ₹17,861 Lowest | 5,818 ₹17,861 Lowest |
| 4.00 | Brick work in C.M 1:5 mix using country bricks incuding cost and conveyance and all labour charges etc. | 4.32 | cum | 6,212 ₹26,836 | 6,210 ₹26,827 Lowest |
| 5.00 | RCC 1:1.5:3 mix using 20mm metal including cost and conveyance and all labour charges etc. | 6.45 | cum | 9,567.05 ₹61,707 Lowest | 9,567 ₹61,707 Lowest |
| 6.00 | Supplying and errecting for sides & soffits including supports and strutting upto 3.29m height for plane surface in all floors including cost and conveyance and all labour charges etc. | 13.83 | Sqm | 547.5 ₹7,572 | 547 ₹7,565 Lowest |
| 7.00 | Above | 22.74 | Sqm | 1,095 ₹24,900 Lowest | 1,095 ₹24,900 Lowest |
| 8.00 | Supply and fabrication of steel including cost and conveyance and alla labour charges etc. complete. | 0.2 | MT | 91,957.3 ₹18,391 Lowest | 91,957 ₹18,391 Lowest |
| 9.00 | Plastering with cement mortar 1:3, 10mm thick including cost and conveyance and all labour charges etc. | 22.79 | Sqm | 328.74 ₹7,492 | 328 ₹7,475 Lowest |
| 10.00 | Providing granolithic floor finish of the following thickness with plain cement concrete 1:2:4 (One Cement, Two crushed stone M.Sand and Four aggregate) using 10 to 12mm gauge hard broken stone jelly including laying, finishing and the top rubbed smooth with power trawl, thread lining, curing etc. complete complying with standard specification and as directed by the departmental officers. (The rate is inclusive of necessary planking for panelling wherever necessary and as directed by the departmental officers) | 15 | Sqm | 169.82 ₹2,547 | 169 ₹2,535 Lowest |
Tender Value
Refer Docs
EMD Value
₹2,940
Closing Date
24 Jul 2026, 3:00 pmClosed
The President
The President Panchayat Office Chitheri
Provision for 2000 Litr Sintex, Shower and Existing Compound Painting at Kilkandigai in Chitheri Panhayat
2026_RDTN_686008_1
A1/1388/2025
Open Tender
Civil Works
Item Rate
Panchayat Office Chitheri
Please refer Tender documents.
1 document required · 1 mandatory
₹0
₹2,940
Yes
24 Jul 2026
15 Jul 2026
24 Jul 2026
15 Jul 2026
24 Jul 2026
15 Jul 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Provision for 2000 Litr Sintex, Shower and Existing Compound Painting at Kilkandigai in Chitheri Panhayat | - | - | - | - |
| 2 | Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth, earth mixed with small sized boulders and hard gravelly soil as per SS 20B | 12.5 | cum | 263.78 | ₹3,297.25 |
| 3 | Cement Concrete 1:4:8 mix using 40mm metal including cost and conveyanceof all materials to work site and all labour charges etc. | 3.07 | cum | 5,818.79 | ₹17,863.69 |
| 4 | Brick work in C.M 1:5 mix using country bricks incuding cost and conveyance and all labour charges etc. | 4.32 | cum | 6,212.57 | ₹26,838.3 |
| 5 | RCC 1:1.5:3 mix using 20mm metal including cost and conveyance and all labour charges etc. | 6.45 | cum | 9,567.05 | ₹61,707.47 |
| 6 | Supplying and errecting for sides & soffits including supports and strutting upto 3.29m height for plane surface in all floors including cost and conveyance and all labour charges etc. | 13.83 | Sqm | 547.5 | ₹7,571.93 |
| 7 | Above | 22.74 | Sqm | 1,095 | ₹24,900.3 |
| 8 | Supply and fabrication of steel including cost and conveyance and alla labour charges etc. complete. | 0.2 | MT | 91,957.3 | ₹18,391.46 |
| 9 | Plastering with cement mortar 1:3, 10mm thick including cost and conveyance and all labour charges etc. | 22.79 | Sqm | 328.74 | ₹7,491.98 |
| 10 | Providing granolithic floor finish of the following thickness with plain cement concrete 1:2:4 (One Cement, Two crushed stone M.Sand and Four aggregate) using 10 to 12mm gauge hard broken stone jelly including laying, finishing and the top rubbed smooth with power trawl, thread lining, curing etc. complete complying with standard specification and as directed by the departmental officers. (The rate is inclusive of necessary planking for panelling wherever necessary and as directed by the departmental officers) | 15 | Sqm | 169.82 | ₹2,547.3 |
stage.html
html • 0.03 MB
tech_eval.pdf
fin_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.37 MB
BOQ_824611.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .