| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.2 CrAccepted-Finance 1954 BELA CHOWK ROPAR | ₹1.2 Cr | L1 | Accepted-Finance As per site |
Tender Value
₹1.3 Cr
EMD Value
₹2.5 L
Closing Date
10 Apr 2026, 1:00 pmClosed
Executive Engineer
EXECUTIVE ENGINEER Construction Division PWD B and R Malerkotla
Raising Widening and Strengthening of LR Balance work Manvi to Saroud Including Maintenance of Road for 5 Year.
2026_CEPW_164925_1
Bid Notice No.37 Date 30.03.2026
Open Tender
Civil Works - Roads
180 days
Malerkotla
Please refer Tender documents.
19 documents required · 19 mandatory
₹0
₹2.5 L
Yes
23 Apr 2026
31 Mar 2026
10 Apr 2026
31 Mar 2026
10 Apr 2026
31 Mar 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Dismantling of existing brick on end edging complete in all respect as per PWD specifications. | |||||
| 2Dismantling of flexible pavements thickness above 50mm by mechanical means and disposal of dismantled materials up to a lead of 1000 meters, stacking serviceable and unserviceable materials separately as per technical clause 202 of MORT&H specifications | |||||
| 3Scarifying existing bituminous surface to a depth of 50 mm by mechanical means (Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material with in all lifts and lead upto 1000 metres.) complete as per technical clause 404 of MORT&H specifications | |||||
| 4Excavation in Soil (any type) using Hydraulic Excavator CK 90 Excavation with hydraulic excavator of 0.9 cum bucket capacity including cutting trimming bottom with side slopes, in accordance with requirements of lines, grades and cross sections including all lifts and combined lead up to 60 mtr. | |||||
| 5Compacting of earth work Compaction of earth work & Preparation of sub grade including loosening, leveling of earth 225mm thick top layer, rough dressing of soil, final dressing of earth to give level, camber, watering, rolling with road roller, compacting the bed to achieve minimum dry density as given in the Table 300-2 as per Technical clause 305 of MORT&H specifications. ( | |||||
| 6Construction of embankment /Shoulders with good quality earth obtained from borrow pits including compensation of earth, loading, unloading, carriage to site of work, spreading, grading to required slope and compacting to meet requirement of table 300-2 as per technical clause 305 of MORT&H specifications. | |||||
| 7Construction of granular sub-base by providing graded material grading-III Table-400-1, (retrieved after dismantling of existing crust) spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per technical clause 401 of MORT&H specifications (Only Labour Rate) | |||||
| 8Construction of granular sub-base by providing material as per grading-III ( Table 400-I of MORT&H 5th revision), mixing in a mechanical mix plant at OMC, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per technical clause 401 of MORT&H specifications | |||||
| 9Providing and laying of Brick on end edging 6.83cm wide, 11.11cm long and 22.86cm high half brick deep including excavation, refilling and disposal of surplus earth up to 50mtr complete as per Punjab PWD specifications | |||||
| 10Providing, laying, spreading and compacting stone aggregates of Grading I to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheeled roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density complete as per technical clause 404 of MORT&H specifications | |||||
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.30 MB
Technicalconditions.pdf
Tender Documents • 4.61 MB
SBD1.pdf
Tender Documents • 21.49 MB
boqMANVI.pdf
Tender Documents • 2.76 MB
COPACONDITIONS.pdf
Additional Documents • 3.66 MB
BOQ_334428.xls
BOQ • 0.35 MB
Download all tender documents and submit your bid