| # | Company | Status |
|---|---|---|
| 1 | Admitted-Fee/PreQual/Technical | Admitted-Fee/PreQual/Technical |
| 2 | Admitted-Fee/PreQual/Technical | Admitted-Fee/PreQual/Technical |
| 3 | Admitted-Fee/PreQual/Technical AAKHADA CHOWK BANASO VISHNUGARH HAZARIBAGH | HAZARIBAGH | JHARKHAND | 825301 | Admitted-Fee/PreQual/Technical |
| 4 | Admitted-Fee/PreQual/Technical | Admitted-Fee/PreQual/Technical |
Tender Value
₹61.0 L
EMD Value
₹1.2 L
Closing Date
19 Mar 2026, 4:00 pmClosed
EXECUTIVE ENGINEER, W. W. DIV. NO. 02, HAZARIBAG
EXECUTIVE ENGINEER, W. W. DIV. NO. 02, HAZARIBAG
Upgradation Work of New Primary School Palma under Chalkusha Block. District - Hazaribag
2026_WRD_111556_1
05/2025 - 26 UNTIED FUND (Group-01)
Open Tender
Civil Works
Percentage
240 days
CHALKUSHA, HAZARIBAG
Please refer Tender documents.
2 documents required · 2 mandatory
₹10,000
₹1.2 L
10 Aug 2026
13 Mar 2026
20 Mar 2026
13 Mar 2026
19 Mar 2026
13 Mar 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Labour for site clearance and scrapping old paint etc. | - | nos. | 326.85 | - |
| 2 | Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing : 1:2:4 (1 cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size) | - | M3 | 5,626.21 | - |
| 3 | Centering and shuttering including strutting, propping etc. and removal of form for Weather shade, Chajjas, corbels etc., including edges. | - | M2 | 445.55 | - |
| 4 | Providing and laying APP (Atactic Polypropylene Polymer) modified prefabricated five layer 3 mm thick water proofing membrane, black finished reinforced with non-woven polyester matt consisting of a coat of bitumen primer for bitumen membrane @ 0.40 litre/sqm by the same membrane manufacture of density at 25°C, 0.87-0.89 kg/litre and viscocity 70-160 cps. Over the primer coat the layer of membrane shall be laid using Butane Torch and sealing all joints etc, and preparing the surface complete. The vital physical and chemical parameters of the membrane shall be as under : Joint strength in longitudinal and transverse direction at 23°C as 650/ 450N/5cm. Tear strength in longitudinal and transverse direction as 300/250N. Softening point of membrane not less than 150°C. Cold flexibility shall be upto -2°C when tested in accordance with ASTM, D - 5147. The laying of membrane shall be got done through the authorised applicator of the manufacturer of membrane : 3 mm thick. | - | M2 | 457.97 | - |
| 5 | Dismantling old plaster and pointing in cement or lime and raking out joints to 15mm depth, watering and disposal of unserviceable materials with all leads all complete as per direction of E/I. | - | M2 | 21.46 | - |
| 6 | Providing 6mm cement plaster (1:4) in celling with clean coarse sand of F.M. 1.5 including screening, curing with all leads and lifts of water, scaffolding taxes and royalty all complete as per building specification and direction of E/I. | - | M2 | 184.06 | - |
| 7 | Providing 12mm cement plaster (1:6) with clean coarse sand of F.M. 1.5 including screening, curing with all leads and lifts of water, scaffolding taxes and royalty all complete as per building specification and direction of E/I. | - | M2 | 165.8 | - |
| 8 | E/W in excavation in foundation trenches in ordinary(vide classification of soil item- A )and disposal of excavated earth as obtained to a distance upto 50m including all lifts wuth levelling, ramming the foundation trenches removing roots trees shrubs all complete job as per approved design, buiding specification and direction of E/I. | - | M3 | 151.82 | - |
| 9 | Earth work in excavation in foundation trenches in hard soil (vide classification of soil item - A+B) and disposal of excavated earth as obtained to a distance up to 50M including all lifts with leveling, ramming the foundation trenches, removing roots of trees, shrubs all complete as perbuilding specification and direction of E/I. | - | M3 | 167.33 | - |
| 10 | Earth filling in foundation trenches and plinth in layers not exceeding 150mm thick well watered, rammed, fully compacted and finally dressed with earth obtained from excavation of foundation trenches with a lead of 50m and lift of 1.5m all complete as per building specification and direction of E/l. | - | M3 | 55.28 | - |
stage.html
html • 0.03 MB
tech_bid_open.pdf
cancelled_1.pdf
pdf • 0.23 MB
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.56 MB
TENDER_DOCUMENTS_05_01.pdf
Tender Documents • 15.09 MB
BOQ_150621.xls
BOQ • 0.42 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .