Construction work of drain and CC in damaged street no. 04 in ward 82 Jawahar Park.
2026_DOLBU_1191134_46
132/Nirman/2026-27 Dated 18-09-2026 (601-700)
Open Tender
Civil Works
Percentage
Ghaziabad
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,416
₹81,262
30 Sept 2026
30 Sept 2026
15 Oct 2026
30 Sept 2026
15 Oct 2026
30 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling reinforced cement concrete or reinforced brick
work including stacking of materials as directed by the
Engineer-in- charge within a distance of 60 metre (200
|feet). PWD SOR 2022 17.3 | 9.5 | M3 | 1,340 | ₹12,730 |
| 2 | Dimantling brick work or stone work in lime or cement
mortar and including stacking of materials as directed be
the Engineer-in- charge within a distance of 60 meter (200 2022/17.
feet).PWD SOR 2022 17.2.2 | 17 | M3 | 600 | ₹10,200 |
| 3 | Desposal of refused material/malwa distance up to 8 km
etc all complete as the direction of engineer in charge. (AS
PER PWD SOR 2020 /231( a). | 9.4 | M3 | 195.1 | ₹1,833.94 |
| 4 | Taking out existing CC interlocking paver blocks from
footpath/ central verge, including removal of rubbish etc.,
disposal of unserviceable material to the dumping ground,
for which payment shall be made separately and stacking of
serviceable material within 50 metre lead as per direction
|of Engineer-in-Charge.DSR 2023 16.83 | 442 | M2 | 100.45 | ₹44,398.9 |
| 5 | Deduct Old interlocking tiles | 9,286.2 | Nos | -6 | - |
| 6 | concrete with 4cm gauge brick ballast fine sand of 1.25 FM and cement in proportion of 1:6:12 in foundation and under floor including supply of all material labour tools & plant etc | 26.13 | M3 | 4,000 | ₹1,04,520 |
| 7 | First class Brick Work in (1:4) cement & four coarse sand
|2.20 F.M. morter in foundation and plinth and T&P etc all
completed as per the direction of engineer - in -charge. (AS
PER PWD SOR 2022 PAGE NO 20 SI NO 6.0S ITEM NO 305
(a) | 55.2 | M3 | 5,170 | ₹2,85,384 |
| 8 | 12 mm thick plaster with cement and coarse sand of1.25
|fineness modules in (1:4) over brick work minimunm
thickness not to be less than 1 cm including supply of all
material, labour, tools & plant etc required for proper
completion of the work. (AS PER PWD SOR 2022 PAGE NO
36 SI NO 13.11 NEW ITEM) | 321.1 | M2 | 200 | ₹64,220 |
| 9 | S/L C:C (1:2:4) with 20 mm stone grit, coarse sand & cement etc all complete as the direction of engineer in charge | 9.3 | M3 | 7,050 | ₹65,565 |
| 10 | S/L of stone ballast 22.4 to 53 mm size with stacking for measurment etc all complete as per the direction of engineer in-charge . AS PER PWD SOR 2020 RMR | 106.5 | M3 | 2,151.2 | ₹2,29,102.8 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 20.10 MB
BOQ_2246498.xls
BOQ • 0.36 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .