Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.6 LAccepted-AOC 4 49 KTC NAGAR 1ST STREET TUTICORIN 628 002 | NA | NA | 628002 | L1 | Accepted-AOC Tender Accepted | |
| 2 | L2₹2.1 L+₹48,200 (29.0%)Rejected-AOC 4 A 39 2 MACHADO NAGAR OPP APC COLLEGE TUTICORIN 2 | TUTICORIN | TAMIL NADU | 626202 | L2 | Rejected-AOC L2 Bidder |
Tender Value
Refer Docs
EMD Value
₹1,600
Closing Date
6 Jul 2021, 2:00 pmClosed
SE/ES
Superintending Engineer-Electrical Systems- Tuticorin Thermal Power Station-Tuticorin
EM III Rectification of 4 Nos defective 6.6 kV 630 amps SF6 gas ABB make breakers available in 6.6 kV HT Switchgear Of Unit IV
2021_EB_202077_1
SE/ES/TTPS/65/2021-22
Open Tender
Electrical Works
Item Rate
15 days
TTPS
As per BQR conditions in NIT
6 documents required · 6 mandatory
₹0
₹1,600
Yes
18 Feb 2022
21 Jun 2021
7 Jul 2021
21 Jun 2021
6 Jul 2021
21 Jun 2021
Transportation of defective breaker and venting out of SF6 gas: Charges for transporting the breaker from switchgear room to breaker testing room, opening of breaker door, cleaning, venting out of SF6 gas with vacuum pump including cost of consumables and hire charges for T&P.
Dismantling of Fixed contact in Extinction Unit : Charges for remove the fixed contact from the arc chamber tube, replace the worn out “O” rings, unscrew the pot from the fixed contact in R, Y, B phases, cleaning inside the arc chamber, inspecting the condition of the arcing tip. Replacing the arcing tip if needed.including cost of " O" rings , consumables and hire charges for T&P.
Cleaning of casing Charges for cleaning of casing with vacuum cleaner inspection and replacement of worn out “ O “ rings.including cost of " O" rings , consumables and hire charges for T&P.
REPLACEMENT OF WORN OUT POWER FINGER CPL & FINGER CPL IN THE FIXED CONTACT: Charges for releasing of worn out Power Finger CPL and Finger CPL in the arc chamber unit and replacing the worn out Power Finger CPL and Finger CPL in each fixed contact and cleaning of remaining Power Finger CPL and Finger CPL. including cost of consumables and hire charges for T&P.
ASSEMBLING THE BREAKER AND FILLING UP OF GAS : Charges for fixing of entire assembly, filling of Nitrogen gas, checking of gas leak in the arc chamber and housing unit with soap water, arresting of gas leak if any by replacement of worn out “ O “ rings. Evacuation of Nitrogen gas after 2 days and filling of SF6 gas ( 6 bar level ) and checking gas leak. [ Nitrogen gas & SF6 gas will be supplied by board ].including cost of consumables and hire charges for T&P.
TESTING OF BREAKER: Charges for assisting to measuring of contact resistance, closing time, tripping time of the rectified breakers and checking of the breaker auxiliary switch, checking of closing and tripping coil and breaker operation .including cost of consumables and hire charges for T&P.
ABR ENGINEERS
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .