| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹38.5 LAdmitted-Finance ALKAPURI ETAWAH | ETAWAH | UTTAR PRADESH | 206001 | -1.10% | ₹38.5 L | L1 | Admitted-Finance |
| 2 | L2₹38.9 LAdmitted-Finance | -0.10% | ₹38.9 L | L2 | Admitted-Finance |
| 3 | L3₹38.9 LAdmitted-Finance | +0.00% | ₹38.9 L | L3 | Admitted-Finance |
Tender Value
₹40.2 L
EMD Value
₹4.0 L
Closing Date
23 Jan 2026, 5:00 pmClosed
DDC
Office of DDC Mandi Parishad Tindwari Road Banda
Construction of Link Road From Amara Baretha To Chhota Khod under Mandi Samiti Banda.
2026_RKUMP_1107060_2
Nirman Khand Banda/Tender/2026-2149 dt.16Jan.2026
Open Tender
Civil Works
90 days
Banda
Please refer Tender documents.
2 documents required · 2 mandatory
₹7,200
DDC Mandi Parishad Banda
₹4.0 L
26 Jan 2026
17 Jan 2026
24 Jan 2026
17 Jan 2026
23 Jan 2026
17 Jan 2026
Part A- Earth work in cutting or in embankment in black cotton soil, excavation to be it he from of regular pits not exceeding 1/2 meter(20") in depth earth work in embankment to be in 20 cm(8") layers including 1.5 meter (5ft) lifts and 30m (100ft) lead. The earth from cutting to be used in making embankment or to be deposited as spoil banks with in 30m (100ft) distance as directed by th Engineer-in-charge.
Laying and consolidation of blanket coat stone dust by road roller as required including hire and fuel charge of roller .
Construction of granular sub-base by providing well graded material, mixing in a uniform layers with motor grader on prepared surface mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401
Providing , laying, spreading and compacting stone aggregates of 45-63mm sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 KN in stages to proper grade and camber, applying and brooming stone screening to fill up the interstices of coarse aggregates, watering and compacting to the requirede density grading-II as per technical specification clause405
Providing , laying, spreading and compacting stone aggregates of 22.4-53mm sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 KN in stages to proper grade and camber, applying and brooming stone screening to fill up the interstices of coarse aggregates, watering and compacting to the requirede density grading-III as per technical specification clause 405
Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70 to 1.00kg/sqm using mannual means. Clause 502
Providing and applying tack coat with V.G.-10 bitumin using bitumin pressure distributor @ 0.30 kg. per sqm. On the prepared bitumins surface cleaned with Hydrulic broom as per Technical Specifictin Clause 503
Providing laying & rolling of open graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates using VG-10 grade bitumin to required line, grade and level to serve as wearing course on a previously prepared base including mixing in a suitable plant , laying and rolling with a three wheel 80-100 KN static roller capacity fifnished to required level and grades to be followed by seal coat Technical specification Claues508 By Mechanical Means.
Providing and laying seal coat by manual means with VG-10 grade Bitumin sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type_C as per Technical Specification Clause 510 By Mechanical Means.
Providing & Fixing of Typical informatory sign board as per MORD specification and drawing . Three MS Plates of 1.6 mm thick, top and middle plate duly welded with MS flat iron 25mmx5m size on back on edges. The lower plates will be welded with MS angle iron frame of 25mmx25mmx5mm. The angle iron frame of lower most plate and flat iron frame of middle plate will be welded to 2 nos. 75mm x 75mm of 12 SWG sheet tubes posts duly embedded in cement concrete M-15 grade blocks of 450mm x 450mm x 600mm, 600mm below ground level. All M.S. will be stove enameled on both sides. Lettering and printing with ready mixed synthetic enamel paint of superior quality in required shade and colour. All section of framed posts and steel tube will be painted with primer and two coats of eppoxy paint as per drawing Clause 1701 and Annexure 1700.1
Brick Edging on both side of the road with M-150 class brick on edge 3" wide and 4-1/2" deep laid with mud mortar, finished to the required temples in proper aligment & also dressing ramming the excavated earth and directed by Engineer-in-charge. S.I. 765
Excavation in foundation of structures upto 3m depth as per drawing and technical specification clause 305. 1 including setting out construction of shouring and bracing removal of stumps and other delterious materials and disposal upto a lead of 50m. dressing of sides and bottom and backfilling in trenchs with excavated suitable material as per MORD Specification No. 300 as Per Data Book item No. 9.1
Sand filling in plinth including supply of necessary quantity of sand including watering dressing etc. for proper completion of the work. S.I.No.-255+ cost of sand.
Cement concrete with 4cm (1/2") gauge approved stone ballast approved coarse sand. Cment in proportion 1:4:8 including supply of all materials, labour and tools and plants etc. required for proper completion of the work.
M-150 class brick work in 1:4 cement and coarse sand1(.25 FM) mortar in foundation and plinth in one brick thick wall, including necessary cutting and moulding of bricks as required and also including honey comb brick work including supply of all materials, labour and T&P etc. required for proper completion of the work. . (SI NO 305+309+310)
Providing and laying reinforced concrete 600 mm dia pipe NP3 in single row for culverts on TYPE A (Concrete cradie) bedding with M 15 grade cement concrete including fixing coller with cement mortar 1:2 but excluding excavation protrction work, backfilling, concrete and masonary works in head walls and parapets clause 11 t0 as per Data Book item No. 9.3 (B)
12mm thick cement plaster 1:4 cement and coarse sand( FM 1.25) mortar over brickwork including supply of all materials, labour and T&P et. required for proper completion of work. (SI NBO 17.59 ii )
Providing and laying reinforced concrete 350mm dia pipe NP3 in single row for culverts on TYPE A (Concrete cradie) bedding with M 15 grade cement concrete including fixing coller with cement mortar 1:2 but excluding excavation protrction work, backfilling, concrete and masonary works in head walls and parapets clause 11 t0 as per Data Book item No. 9.3 (B)
Earth work in cutting or in embankment in black cotton soil, excavation to be it he from of regular pits not exceeding 1/2 meter(20") in depth earth work in embankment to be in 20 cm(8") layers including 1.5 meter (5ft) lifts and 30m (100ft) lead. The earth from cutting to be used in making embankment or to be deposited as spoil banks with in 30m (100ft) distance as directed by th Engineer-in-charge.
Laying and consolidation of blanket coat stone dust by road roller as required including hire and fuel charge of roller .
Providing , laying, spreading and compacting stone aggregates of 45-63 mm sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 KN in stages to proper grade and camber, applying and brooming stone screening to fill up the interstices of coarse aggregates, watering and compacting to the requirede density grading-III as per technical specification clause 405
Providing , laying, spreading and compacting stone aggregates of 22.4-53mm sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 KN in stages to proper grade and camber, applying and brooming stone screening to fill up the interstices of coarse aggregates, watering and compacting to the requirede density grading-III as per technical specification clause 405
Excavation in foundation trenches in ordinary soil( loam, clay or sand ) I/C ligt up tol. 50m lead up to 30m & I/C filling, watering & ramming of excavation earth in to trenches or in to the space between trenches or in to the plinth and removal and disposal of Surplus earth as diverted by the engineer in charge up to a distance of 30m from the foundation trenches.(251)
Sand filling in plinth including supply of necessary quantity of sand including watering dressing etc. for proper completion of the work. S.I.No.-255+ cost of sand.
Cement concrete with 4 cm gauge stone ballast, coarse sand of cement in proportion of 1:6:12 in foundation & under floors, including supply of all materials, labour & T&P etc. required for proper completion of the work(S.I.No. 271)
M. 150 class brick work in 1:4 cement and fine sand mortar in plinth, including supply of all materials, labour & T&P etc. required for proper completion of the work. S.I. No. 305
P/L of Rubble moulded Zig Zag Interlocking Concrete Block Pavements having thickness 80 mm as per drawing and Technical Specification Clause 1504. (Chapter 6) 6.7
Cement concrete with 20mm (1/2") guage approved stone grit, approved coarse sand cement in the proportion 4:2:1 including supply of all materials, labour and tools and plants etc. required for proper completion of the work. S.I. No. 279a
12 mm thick cement plaster with cement & coarse sand in 1:4 including supply of all materials, labour & tools and nts etc. required for proper completion of the work . S.I. 584
Part-B As Per E/I for the period of five years the actual completion date of the work. GST shall be paid extra as per applicable at the time of payment. Maintenance of first year total work amount of P.C. Work.
Maintenance of seconed year total work amount of P.C. Work.
Maintenance of third year total work amount of P.C. Work.
Maintenance of fourth year total work amount of P.C. Work.
Maintenance of five year total work amount of P.C. Work.
Maintenance of fourth year total work amount of Interlocking
Maintenance of fourth year total work amount of Interlocking
Please Enable Macros to View BoQ information
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 5.57 MB
BOQ_2042781.xls
BOQ • 0.39 MB
Download all tender documents and submit your bid