PROVN OF SEWAGE TREATMENT PLANT AT MADHOPUR MIL STN
2025_MES_744969_1
CA NO CEPZ-14/2025-26
Open Tender
Civil Works
Lump-sum
3060 days
GE Basoli
AS PER TENDER DOCUMENTS
8 documents required · 8 mandatory
₹3,000
GE Basoli
₹7.7 L
Yes
2 Apr 2026
17 Dec 2025
22 Jan 2026
17 Dec 2025
15 Jan 2026
8 Jan 2026
Select, Excess (+), Less (-) Less (-)
Tender Inviting Authority: CHIEF ENGINEER PATHANKOT ZONE
Name of Work PROVISION OF SEWAGE TREATMENT PLANTS AT MADHOPUR MIL STN
Contract No: CEPZ - 14/2025 - 2026
Note: The Schedule of credit has been attached in tender in Pdf formate and amount of credit schedule i.e Rs.79700.00 shall be deducted from the total amount of BOQ to arrive at the contract sum. Srl No Item Code / Make Quantity Units Estimated Rate Addition / Deduction Addition / Deduction Values Currency Convertion against each Item Quoted Currency in INR / Other Currency Supplying, Installation, Testing and commissioning of extendable, compartmentalised, front operated , back openable, LT cubicle STP panel having ingress protection of IP 54, suitable for operation on 415 Volt 3 phase 50 c/s power supply fabricated out of 2mm thick CRCA sheet steel and base channel of MS section not less than 100mm X 50mm X 5mm, gland plate of 3 mm thick cleaned and treated in 7 tank process and powder coated with approved shade with TPN Electrolytic Aluminium busbar of 100A duly insulated in colour coding & suitable to withstand 25 MVA fault lavel complete with supplying & installation of following equipment including interconnection, control wiring etc as required. All MCCBs shall have microprocessor based release & shall have manually operated handle.It includes all wiring , cabling of required sizes from STP panel board to each electrical parts with on site control panel for individual motors . The panel will consists of Items as per drawings attached.(Panel shall be of outdoor type installation with suitable IP Protection) Complete LT cubicle STP panel having ingress protection of IP 54 to be provided as per the details given in Schedule 'A" Part-I from page No 44 to 45 of CA. Excise Duty VAT Freight Charges ( Unloading & Stacking) Any Other Taxes/Duties/Levies Other Taxes 2 IIIrd Party i.e DGS&D / RITES etc Inspection Charges @0.34%+Service Tax Less for Cenvat Credit,if any respect of Supplies Under full Excise Duty Category Description of Item of Works TOTAL AMOUNT With Taxes TOTAL AMOUNT In Words
1 Manning & Operation of the STP & SCADA (of capacity 100 KLD as per srl item No 1 & 2 of this BOQ) for 05 months after completion of Phase-IX { Phase- X refer Sch "A" note no.2.1(k) } complete.Operating and keeping the capacity in running / operational condition by deploying FGM / technical staff to produce the treated effluent of specified quality including Sundays and holidays including all connected LT cubicle STP panel , electrical & sewage pumps items such as main switch, starter, change over switch, MCCB, voltmeter, ammeter, panel board etc, Sewage water pump, valve system, controlling syatem, daily checking, leakage, checking noise, cleaning of plant and its surrounding area etc for a period of 11 (Eleven Months) including all holidays all as specified and directed by Engr-in-Charge. Note : - Contractor shall deploy one skilled operator (FGM) and one helper per shift for three shifts per day in each month for operation of each STP. 3 Each Job Excess(+) Full Conversion INR 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
2 Notes for Serial Item No. 40 to 42 above :- (a) Comprehensive maintenance includes replacement of all defective/ worn out / damaged parts including MBR membrane with new parts and nothing extra shall be paid on this account except the payment specified in this item. (b) The contractor shall be responsible for periodic maintenance as per maintenance schedule and specified including renewal/ replacement of parts, lubricants, fittings / fixtures filling of bacteria etc required for smooth functioning of the plant as per manufacturers instructions. (c) The rate quoted shall be deemed to be inclusive of safety gear & required tools for maintenance. (d) The quoted rate is deemed to be inclusive of tool & testing instruments required for operation & maintenance of STP plant. (e) The sludge cakes procured after treatment shall become contractors property and shall be removed from premises of STP as early as possible. The rate shall be quoted accordingly. 3 Each Job Excess(+) Full Conversion INR 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
3 Comprehensive maintenance of the above STP & SCADA (of capacity 100 KLD as per srl item No 1 to 3 of this BOQ) { Phase - VIII refer Sch "A" note no.2.1(h) } ,for the period of 3rd years after expiry of second year of Defect Liability Period. The scope of comprehensive maintenance includes maintenance of complete infrastructure under this work and replacing all defective components and restoring any defect / deformity / wear and tear and comprehensive maintenance of all STP components under this job, (Sl item No. 1.00 to 3.00) including all connected LT cubicle STP panel , all pumps and DG Sets in the scope of entire tender for further period of 12 Months after completion defect liability period. The scope shall also include comprehensive maintenance of all electrical & Sewage Pumps items such as main switch, starter, change over switch, MCCB, voltmeter, anmeter, panel board etc, Sewage water pump, valve system, controlling syatem, daily checking, leakage, checking noise, cleaning of plant and its surrounding area etc, as per manufacturers instructions and as specified and directede by Engr-in-Charge. 3 Each Job Excess(+) Full Conversion INR 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
4 Material and Labour for Construction of Block of Panel Room, Duty Room, Rest Room with Toilet & cum bath complete all as shown in drawings and as specified , and directed by the Engineer in Charge. 1 Each Block Excess(+) Full Conversion INR 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
5 Lumpsum price worked out by the contractor for EARTH WORK , SITE CLEARANCE AND DEVELOPMENT as listed in Schedule 'A' Part-III. 1 Each 10579008.26 Excess(+) Full Conversion INR 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
6 Lumpsum price worked out by the contractor for NEW ROADS, REPAIR TO ROAD, HUME PIPE CULVERT & HARDSTANDING/PATH as listed in Schedule 'A' Part-IV. 1 Each 2038480.09 Excess(+) Full Conversion INR 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
7 Lumpsum price worked out by the contractor for SEWAGE DISPOSAL as listed in Schedule 'A' Part-V. 1 Each 9600236.14 Excess(+) Full Conversion INR 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
8 Lumpsum price worked out by the contractor for AREA DRAINAGE as listed in Schedule 'A' Part-VI. 1 Each 667492.74 Excess(+) Full Conversion INR 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
9 Lumpsum price worked out by the contractor for Fencing & Gate as listed in Schedule 'A' Part-VII. 1 Each 331705.66 Excess(+) Full Conversion INR 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
10 Lumpsum price worked out by the contractor for EXTERNAL ELECTRIC SUPPLY as listed in Schedule 'A' Part-VIII. 1 Each 640240.95 Excess(+) Full Conversion INR 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
11 Lumpsum price worked out by the contractor for WATER SUPPLY as listed in Schedule 'A' Part-IX. 1 Each 443455.6 Excess(+) Full Conversion INR 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
12 Material and Labour for Painting Line, Dashes, Arrow, Letters etc on road pavement of new/old black top surface road surface and applying one coat of retro reflective thermoplastic road marking paint 2mm thick & width not exc 10 cm for longer durability with 8% glass beads using special applicator machine fitted with profile shoe heater driven by experianced operator on road surfaces on and including preparation of new or old black top surfaces of road , cleaning surfaces of all dirt, scales, oils, grease & foreign materials etc complete all as specified and directed by Engineer in charge with heating arrangement upto 160 degree celcius. Paint material shall be conforming to ministry of surface transport (MOST) specification 803.4 Vol -I as laid down in specification of Road / Bridge work " third revision" ; complete all as specified and directed by the Engineer In Charge. 40 Square Metre Excess(+) Full Conversion INR
13 Supply, laying and testing of 150 mm inner diameter of double wall corrugated (DWC) high density polyethylene pipes (HDPE) and stiffness classes-8 (SN-8) with ISI marked (with CML no) with and including all fitting & jointing material for sewage line and laid in trenches as specified in IS-16098 (Part-2) : 2013 and as per manufacturer's instructions complete all as specified and as directed. 1600 Running Metre Excess(+) Full Conversion INR
14 Supply, laying and testing of 200 mm inner diameter of double wall corrugated (DWC) high density polyethylene pipes (HDPE) and stiffness classes-8 (SN-8) with ISI marked (with CML no) with and including all fitting & jointing material for sewage line and laid in trenches as specified in IS-16098 (Part-2) : 2013 and as per manufacturer's instructions complete all as specified and as directed. 3330 Running Metre Excess(+) Full Conversion INR
15 BASIC RATE In Figures To be entered by the Bidder Rs. P 400 Running Metre Excess(+) Full Conversion INR
16 Materail & Labour for 100mm thick 560mm dia precast RCC factory made circular Manhole Cover set in cement mortar 1:6 complete all as specified and directed by the Engineer-in-charge. 125 Each Excess(+) Full Conversion INR
17 Materail & Labour for 100mm thick 900mm dia precast RCC factory made circular Manhole Cover set in cement mortar 1:6 complete all as specified and directed by the Engineer-in-charge. 83 Each Excess(+) Full Conversion INR
18 Material and labour for Preparing of new concrete surfaces of any description over 10cm width or girth and applying two coats of Epoxy coated Paint over a coat of primer ; complete all as specified and directed by the Engineer-in-charge. 1000 Square Metre Excess(+) Full Conversion INR
19 Material and Labour for Construction of Wet Well cum equalization Tank as per drawing no. ICC/MBR/01 Dt 25/11/2024, ARCH/WW/01 dt 07/10/2023 sh 1/2 to 2/2 , as specified and as directed by the Engineer in Charge. 1 Each Excess(+) Full Conversion INR
20 Material and Labour for Construction of Sump RCC Tank as per drg no. ICC/MBR/01 Dt 25/11/2024, as specified and as directed by the Engineer in Charge. 2 Each Excess(+) Full Conversion INR
21 Material and Labour for Construction of Oil & Grease Trap as per drg no. ICC/ARCH/OGT/01 Dt 25/11/2024 , as specified and as directed by the Engineer in Charge. 11 Each Excess(+) Full Conversion INR
22 Material & labour for disconnecting all type of cable & electric connections , earthing of exting transformer , and taking down the same transformer of capacity upto 100 KVA as per requirement from 2Pole or 4Pole structure carefully & safely and shifting the transformer by transporting with crane & mannul labour safely , place the transformer on existing platform and making all type of cable & electric connections at new shifted place , and installing complete connecting with electrical system, earthing, testing and startup the electric supply complete all as directed by the Engineer-in-charge. Note :- The rates quoted by the contractor for this item includes all type of Tool,Plants,crane, lorry, labour etc required for taking down and shifting of the transformer within the cantonment campus and making connections & installation complete and nothing extra shall be paid. 1 Each Job Excess(+) Full Conversion INR
23 Supply, laying and testing of 100 mm inner diameter of double wall corrugated (DWC) high density polyethylene pipes (HDPE) and stiffness classes-8 (SN-8) with ISI marked (with CML no) with and including all fitting & jointing material for sewage line and laid in trenches as specified in IS-16098 (Part-2) : 2013 and as per manufacturer's instructions complete all as specified and as directed. Note Serial Item No. 13 to 15 :- Bedding of pipe shall not be provided in normal condition and CONSTRUCTION METHODS shall be strictly compiled as per clause no A-4 of ANNEX 'A' of IS 16098 (Part-2) : 2013. 10 Each Set Excess(+) Full Conversion INR
24 Material & labour for earthing complete with galvanized steel earth plate electrode 600mm x 600mm x 6mm thickness , buried directly in ground (earth pit not less than 2.25 metres deep below the normal ground level ) with top edge of plate not less than 1.5 metres below the normal ground level connected to galvanized iron wire 4mm dia by means of nuts bolts, washers, check nuts of GI steel all as shown in electric plate no 3 of SSR -2009 Part I, all as specified and indicated complete and including charcoal dust, salt etc and GI protection pipe medium grade 40mm and GI watering pipe 20mm light grade with funnel and wire mesh,40mm thick pre-cast RCC M-15 (nominal mix) cover reinforced with XPM weight not less than 4 kg /sqm with suitable handle of 6mm dia MS bar and angle iron 40mmx40mmx3mm frame for cover,PCC M-15 (nominal Mix) pit , earth work in any type of soil and connected all as specified and as directed. Notes :- (i) Up to 7.5metres length of pipe of 40 mm dia and GI earth wire shall be deemed to be included in unit rate quoted by the tenderer (ii) Resistance of earthing should be less than 1 Ohms failing which the contractor will do the earthing again to achieve the desired result i.e. less than 1 ohms (iii) In case soil is not suitable same is to be replaced with good quality clay soil to achieve the desired result of less than 1 ohms (iv) Quoted rate shall be deemed to be inclusive for the above aspect 2 Each Set Excess(+) Full Conversion INR
25 Supply and fixing in replacement for FRP weather proof cable juction box of size 300mm x 200mm x 105mm including aluminium bus bar of capacity 63Amps 04 Nos with 02 Nos MS clamps of flat 40mm x 6mm of suitable size complete with nuts and bolts and making connections with cable and including thimbles of suitable size complete all as specified and as directed by Engineer-in-charge. 6 Each Excess(+) Full Conversion INR
26 Supply and fixing in replacement for street light bracket of 1.5 metres length made out of 40mm dia GI pipe medium grade bend to shape at 120 degree and welded at required end fixed with MS flat iron clamp bolts, nuts and washers including painting MS clamp with one primer coat and two coat of aluminium paint and bracket fixed to poles or walls complete all as specified and as directed by Engineer-in-charge. 6 Each Excess(+) Full Conversion INR
27 Supply and laying in replacement for PVC insulated and sheathed with copper conductor cable of size 1.5 Sqmm 3 core, 1100 volt fixed in position from junction box to street light fitting connector with fixing arrangements on wall/ RCC/Steel tubular poles complete all as specified and as directed by Engineer -in-charge. 45 Running Metre Excess(+) Full Conversion INR
28 Material & Labour for construction of platform of size 3000mm x 2500mm x 1200mm for transformer, complete all as specified and shown on drawing No CEPZ/C-TD/002/13 Sheet 2/5 , using under mentioned specifications :- (i) PCC (1:4:8) type D2 in foundation using 40mm graded stone aggregate. (ii) Brick work with cement mortar (1:4) using Sub class "B" Bricks. (iii) 15 mm thick rendering to exposed surface of bricks in CM (1:4). (iv) 100mm thick PCC 1:2:4 type B1 using 40mm graded stone aggregate at top portion of platform. (v) Two Coats of white wash on plastered surfaces. (vi) Mild Steel work ( i.e. MS jali/fencing/MS angle ) on the top of platform around transformer up to height of 90omm. (vii) Earth work (Excavation,Return filling & Removal) in any type of Soil. 1 Each Job Excess(+) Full Conversion INR
29 Material & labour for Earthing complete with galvanized steel earth plate electrode 600mm x 600mm x 6mm thickness , buried directly in ground (earth pit not less than 2.25 metres deep below the normal ground level ) with top edge of plate not less than 1.5 metres below the normal ground level connected to galvanized iron strip 32mm x 6mm by means of nuts bolts, washers, check nuts of GI steel all as shown in electric plate no 3 of SSR -2009 Part I, all as specified and indicated complete and including charcoal dust, salt etc and GI protection pipe medium grade 40mm and GI watering pipe 20mm light grade with funnel and wire mesh,40mm thick pre-cast RCC M-15 (nominal mix) cover reinforced with XPM weight not less than 4 kg /sqm with suitable handle of 6mm dia MS bar and angle iron 40x40x3mm frame for cover,PCC M-15 (nominal Mix) pit , earth work in any type of soil and connected all as specified and as directed. Notes :- (i) Up to 7.5metres length of pipe of 40 mm dia and GI strip shall be deemed to be included in unit rate quoted by the tenderer (ii) Resistance of earthing should be less than 1 Ohms failing which the contractor will do the earthing again to achieve the desired result i.e. less than 1 ohms (iii) In case soil is not suitable same is to be replaced with good quality clay soil to achieve the desired result of less than 1 ohms (iv) Quoted rate shall be deemed to be inclusive for the above aspect 1 Each Job Excess(+) Full Conversion INR
30 Supply ,Installation ,Testing & commisioning of totally enclosed feeder piller indoor type (IP-65) fabricated out of 3.15mm thick CRCA sheet dust and vermin proof powder coated double door type (independent cabin including locking arrangement for each MCCBs , bus bar chamber (enclosed) including locking arrangement complete suitable for operating on 415 Volt 50 Hz AC, with internally wired with copper conductor , TPN bus bar of aluminium strip (4 Nos) insulated by heat shrinkable sleaves & clips on shrouds for joints busbar shall be designed to withstand a fault lavel at 415 Volts having legs 45cms made out of 65mm x 65mm x 6mm angle iron grouted on brick masonary plateform upto 30Cms . Brick masonary plateform shall be 60 Cms above 1 Each Job Excess(+) Full Conversion INR
31 Material and labour for construction of masonary valve pit chamber of size 900mm x 900mm x 900mm (Internal dimension) complete all as specified using under mentioned specifications and shown on drawing No CEPZ/C-TD/006/13 Sheet 1/1 dated 11-09-2013 :- (i) Earth work (Excavation,Return filling & Removal) in any type of Soil. (ii) PCC (1:4:8) type D2 in foundation using 40mm graded stone aggregate. (iii) Brick work with cement mortar (1:4) using Sub class "B" Bricks. (iv) 15mm thick rendering to internal surfaces of chamber in CM(1:4). (v) 15 mm thick rendering to external surface of chamber upto 150mm below GL in CM(1:4) (vi) 50mm thick PCC (1:4:8) type D2 ain sub base of floor 40mm graded stone aggregate. (vii) 50mm thick floor in PCC 1:2:4 type B1 using 20mm graded stone aggregate surfaces finished even & smooth without using extra cement. (viii) Two Coats of white wash on all exposed internal & external surfaces. (ix) Mild Steel sheet cover not less than 6mm thick with angle iron frame size 50mmx50mmx6mm with locking arrangement. (x) Painting to steel surfaces internally externally with two coats of synthetic enamel painting over a coat of the red oxide primer. 1 Each Job Excess(+) Full Conversion INR
32 Material and labour for construction of masonary valve pit chamber of size 600mm x 600mm x 750mm (Internal dimension) complete all as specified using under mentioned specifications and shown on drawing No CEPZ/C-TD/006/13 Sheet 1/1 dated 11-09-2013 :- (i) Earth work (Excavation,Return filling & Removal) in any type of Soil. (ii) PCC (1:4:8) type D2 in foundation using 40mm graded stone aggregate. (iii) Brick work with cement mortar (1:4) using Sub class "B" Bricks. (iv) 15mm thick rendering to internal surfaces of chamber in CM(1:4). (v) 15 mm thick rendering to external surface of chamber upto 150mm below GL in CM(1:4) (vi) 50mm thick PCC (1:4:8) type D2 ain sub base of floor 40mm graded stone aggregate. (vii) 50mm thick floor in PCC 1:2:4 type B1 using 20mm graded stone aggregate surfaces finished even & smooth without using extra cement. (viii) Two Coats of white wash on all exposed internal & external surfaces. (ix) Mild Steel sheet cover not less than 6mm thick with angle iron frame size 50mmx50mmx6mm with locking arrangement. (x) Painting to steel surfaces internally externally with two coats of synthetic enamel painting over a coat of the red oxide primer. 10 Each Job Excess(+) Full Conversion INR
33 Supply, installation, commissioning and testing of ECO friendly diesel engine driven, water cooled generating set of capacity 82.5 KVA/66 KW , 415 volts, AC supply, 50 HZ, 3 phase 4 wire, 0.8 PF at NTP, speed 1500 RPM mounted on common base plate with flexible coupling and meeting the requiements of IS-4722/BIS -5514 specificaiton with CPCBIV+ approved accoustic enclousres fabricated out CRCA sheet 1.6mm thick and structual sheet metal base frame. Sound proofing of enclouser is done with high quality foam conforiming to IS 8183 of 25 mm thickness and density 30 Kg /M3 complete including PCC foundation in all respect complete as per manufactures recommendations:- (a) Diesel Engine : Water cooled diesel engine of adequate capacity at 1500 RPM generally in accordance with latest BIS/IS specifacition , self starting including 01 x 12 volts maintenance free battery of suitable capacity ,charging dynamo/alternator ,air cleaner , diesel/oil filters complete in all respect . The engine shall be capable to take 10% extra overload for one hour for every 12 hours of running confirming to the enviroment (protection act 1986) (29 of 1986) and as amended vide Gazette of India Notificaitons Part -II Section -III sub Section (I) dated 12 Jul 2004. (b) Engine Instructions Panel : All relevant information shall be displayed on a complete panel for easy monitoring of lubricant ,oil pressure, battery charging, ammeter, hours meter ,starting switch etc. (c) Fuel tank : In built fuel tank of adequate capacity with stop cock ,drain plug and necessary fuel pipe complete as per manufactures recommendaitons . 1 Each Excess(+) Full Conversion INR
33.01 Item No.33(Contd...) (d) Alternator - : 82.5 KVA / 66 KW at NTP , 3 phase ,50 HZ ,415 volts ,AC supply ,0.8 PF at 1500 RPM , this shall be self excited screen protected and drip proof type bruchless ,confirming to relevant IS/BIS code as per latest manufacturing schedule . CONTROL PANEL :- The standard control panel shall be built in acoustic enclosures with the following accessories complete wired with suitable size of copper cables. (i) MCCB /MCB TPN of suitable rating with overload and short circuit protection. (ii) Digital ammeter (iii) Digital voltmeter (iv) One set of indicating LED lamps RYB and fuse (v) Frequency meter, RPM meter, Hour meter, fuel level indicator (vi) KWH meter electronic tamper proof digital for 3 phase 415 volts AC unbalanced load of suitable capacity (vii) Water temprature & oil pressure gauge. AMF :- The panel on microprocessor based type shall be with AMF(ATS) controller suitable to start the engine on main failure after 10-15 second delay and to switch off engine only after 60-90 seconds after the main supply restored. The AMF controller shall have under/ over voltage, overload protection, coolant temp cut off, fuel control upto 10% tank capacity. The panel shall also have one automatic change over switch of suitable capacity to bypass main supply when the AMF control becomes defective. Note :- The gen set must be affixed with label meeting the following requirements (The label shall be durable and legible) :- (i) Name and address of the engine manufacturer (ii) Statement that this engine conforms to the environment protection (iii)Type and approval certificate number (iv) Date of manufacture of Gen set
33.02 Item No.33(Contd...) (f) ACCOUSTIC ENCLOSURE: Accoustic enclosure is made out of CRCA sheet of 1.6mm and ISMC base frame painted. The walls of enclosures will be insulated with rockwool so to canopy with 75 db(A) at 1mtrs sound leveled by ministry of environment and forest. The wall of enclosure will be insulated as per manufacturer's recommendatios with the following:- (i) Fitting arrangment (ii) Point for neutral and body earthing (iii) Lub oil drainage (iv) Air breather (v) Hood or rain protection (vi) Easy stop push button (vii) Panel meter viewing window (viii) Tube light fitting of suitable wattage Note :- (a) DG set should be sound proof as per latest policy. (b) First filling of Engine Oil and fuel etc should be arranged by the contractor. (c) There shall be proper air circulation and glass window in the acoustic enclosures suitable located to read the meters of various control form outside. (d) Necessary overload test shall be carried out in the presence of testing officer nominated by Accepting Off
34 Supply ,Installation ,Testing & commisioning of totally enclosed feeder piller indoor type (IP-65) fabricated out of 3.15mm thick CRCA sheet dust and vermin proof powder coated double door type (independent cabin including locking arrangement for each MCCBs , bus bar chamber (enclosed) including locking arrangement complete suitable for operating on 415 Volt 50 Hz AC, with internally wired with copper conductor , TPN bus bar of aluminium strip (4 Nos) insulated by heat shrinkable sleaves & clips on shrouds for joints busbar shall be designed to withstand a fault lavel at 415 Volts having legs 45cms made out of 65mm x 65mm x 6mm angle iron grouted on brick masonary plateform upto 30Cms . Brick masonary plateform shall be 60 Cms above the Ground Level . The panel shall be front operated with cable entry from the bottem with cable glands. The fault with standing capacity shall be 25 KA including Earth bus shall be part of the main feeder pillar . The Feeder Piller Box panel shall be CPRI approved , width of the panel not less than 600mm and Comprising & including of the under mentioned accessories :- (a) MCCB 4 pole, 200 A, 415 volt 50HZ with thermal setting 70% to 100% and rupturing capacity not less than 25 KA - 01 No (for Incoming). (b) MCCB 3 pole, 63 A, 415 volt 50HZ with thermal setting 70% to 100% and rupturing capacity not less than 16 KA - 03 No(Out going for STP No 1,2 & 3). (c) MCB SPN 32 amps- 01 No(For building ). (d) Digital Ammeter 0 to 500 Amp with selector switch & suitable range of CTs - 01 No . (e) Digital Voltmeter 0 to 500 V with selector switch - 01 No. (f) LED Phase indicating lamp (Set of three)- 03 Nos (RYB) Note :- Platform Shall be constructed using following specifications :- (i) PCC (1:4:8) type D2 in foundation using 40mm graded stone aggregate. (ii) Brick work with cement mortar (1:6) using Sub class "B" Bricks. (iii) 15 mm thick rendering to exposed surface cement mortar (1:4).(iv) 100mm thick PCC 1:2:4 type B1 using 40mm graded stone aggregate at top portion of platform. (v) Two Coats of white wash on plastered surfaces. (vi) Earth work (Excavation,Return filling & Removal) in any type of Soil. 11 Per Calander month Excess(+) Full Conversion INR
35 the Ground Level . The panel shall be front operated with cable entry from the bottem with cable glands. The fault with standing capacity shall be 25 KA including Earth bus shall be part of the main feeder pillar . The Feeder Piller Box panel shall be CPRI approved , width of the panel not less than 600mm and Comprising & including of the under mentioned accessories :- (a) MCCB 4 pole, 200 A, 415 volt 50HZ with thermal setting 70% to 100% and rupturing capacity not less than 25 KA - 01 No (for Incoming). (b) MCCB 3 pole, 200 A, 415 volt 50HZ with thermal setting 70% to 100% and rupturing capacity not less than 16 KA - 01 No(Out going for distribution LT panel). (c) MCCB 3 pole, 200 A, 415 volt 50HZ with thermal setting 70% to 100% and rupturing capacity not less than 25 KA - 01 No(spare ). (d) Digital Ammeter 0 to 500 Amp with selector switch & suitable range of CTs - 01 No . (e) Digital Voltmeter 0 to 500 V with selector switch - 01 No. (f) LED Phase indicating lamp (Set of three)- 03 Nos (RYB) Note :- Platform Shall be constructed using following specifications :- (i) PCC (1:4:8) type D2 in foundation using 40mm graded stone aggregate. (ii) Brick work with cement mortar (1:6) using Sub class "B" Bricks. (iii) 15 mm thick rendering to exposed surface cement mortar (1:4).(iv) 100mm thick PCC 1:2:4 type B1 using 40mm graded stone aggregate at top portion of platform. (v) Two Coats of white wash on plastered surfaces. (vi) Earth work (Excavation,Return filling & Removal) in any type of Soil. 11 Per Calander month Excess(+) Full Conversion INR
36 Manning & Operation of the STP & SCADA (of capacity 100 KLD as per srl item No 1 & 2 of this BOQ) for 11 months after completion of Phase-II { Phase-III refer Sch "A" note no.2.1(c) } complete.Operating and keeping the capacity in running / operational condition by deploying FGM / technical staff to produce the treated effluent of specified quality including Sundays and holidays including all connected LT cubicle STP panel , electrical & sewage pumps items such as main switch, starter, change over switch, MCCB, voltmeter, ammeter, panel board etc, Sewage water pump, valve system, controlling syatem, daily checking, leakage, checking noise, cleaning of plant and its surrounding area etc for a period of 11 (Eleven Months) including all holidays all as specified and directed by Engr-in-Charge. Note : - Contractor shall deploy one skilled operator (FGM) and one helper per shift for three shifts per day in each month for operation of each STP. 11 Per Calander month Excess(+) Full Conversion INR
37 Manning & Operation of the STP & SCADA (of capacity 100 KLD as per srl item No 1 & 2 of this BOQ) for 11 months { PHASE - II refer Sch "A" note no.2.1(b) } , after completion of STP & SCADA. Operating and keeping the capacity in running / operational condition by deploying FGM / technical staff to produce the treated effluent of specified quality including Sundays and holidays including all connected LT cubicle STP panel , electrical & sewage pumps items such as main switch, starter, change over switch, MCCB, voltmeter, ammeter, panel board etc, Sewage water pump, valve system, controlling syatem, daily checking, leakage, checking noise, cleaning of plant and its surrounding area etc for a period of 11 (Eleven Months) including all holidays all as specified and directed by Engr-in-Charge. Note : - Contractor shall deploy one skilled operator (FGM) and one helper per shift for three shifts per day in each month for operation of each STP. 11 Per Calander month Excess(+) Full Conversion INR
38 Manning & Operation of the STP & SCADA (of capacity 100 KLD as per srl item No 1 & 2 of this BOQ) for 11 months after completion of Phase-IV { Phase- V refer Sch "A" note no.2.1(e) } complete.Operating and keeping the capacity in running / operational condition by deploying FGM / technical staff to produce the treated effluent of specified quality including Sundays and holidays including all connected LT cubicle STP panel , electrical & sewage pumps items such as main switch, starter, change over switch, MCCB, voltmeter, ammeter, panel board etc, Sewage water pump, valve system, controlling syatem, daily checking, leakage, checking noise, cleaning of plant and its surrounding area etc for a period of 11 (Eleven Months) including all holidays all as specified and directed by Engr-in-Charge. Note : - Contractor shall deploy one skilled operator (FGM) and one helper per shift for three shifts per day in each month for operation of each STP. 11 Per Calander month Excess(+) Full Conversion INR
39 Manning & Operation of the STP & SCADA (of capacity 100 KLD as per srl item No 1 & 2 of this BOQ) for 11 months after completion of Phase-VI { Phase-VII refer Sch "A" note no.2.1(g) } complete.Operating and keeping the capacity in running / operational condition by deploying FGM / technical staff to produce the treated effluent of specified quality including Sundays and holidays including all connected LT cubicle STP panel , electrical & sewage pumps items such as main switch, starter, change over switch, MCCB, voltmeter, ammeter, panel board etc, Sewage water pump, valve system, controlling syatem, daily checking, leakage, checking noise, cleaning of plant and its surrounding area etc for a period of 11 (Eleven Months) including all holidays all as specified and directed by Engr-in-Charge. Note : - Contractor shall deploy one skilled operator (FGM) and one helper per shift for three shifts per day in each month for operation of each STP. 5 Per Calander month Excess(+) Full Conversion INR
39.01 Manning & Operation of the STP & SCADA (of capacity 100 KLD as per srl item No 1 & 2 of this BOQ) for 11 months after completion of Phase-VIII { Phase-IX refer Sch "A" note no.2.1(j) } complete.Operating and keeping the capacity in running / operational condition by deploying FGM / technical staff to produce the treated effluent of specified quality including Sundays and holidays including all connected LT cubicle STP panel , electrical & sewage pumps items such as main switch, starter, change over switch, MCCB, voltmeter, ammeter, panel board etc, Sewage water pump, valve system, controlling syatem, daily checking, leakage, checking noise, cleaning of plant and its surrounding area etc for a period of 11 (Eleven Months) including all holidays all as specified and directed by Engr-in-Charge. Note : - Contractor shall deploy one skilled operator (FGM) and one helper per shift for three shifts per day in each month for operation of each STP.
40 TOTAL AMOUNT Rs. P 12 Per Calander month Excess(+) Full Conversion INR
41 Comprehensive maintenance of the above STP & SCADA (of capacity 100 KLD as per srl item No 1 to 3 of this BOQ) { Phase - IV refer Sch "A" note no.2.1(d) } ,for the period of 1st years after expiry of Defect Liability Period. The scope of comprehensive maintenance includes maintenance of complete infrastructure under this work and replacing all defective components and restoring any defect / deformity / wear and tear and comprehensive maintenance of all STP components under this job, (Sl item No. 1.00 to 3.00) including all connected LT cubicle STP panel , all pumps and DG Sets in the scope of entire tender for further period of 12 Months after completion defect liability period. The scope shall also include comprehensive maintenance of all electrical & Sewage Pumps items such as main switch, starter, change over switch, MCCB, voltmeter, anmeter, panel board etc, Sewage water pump, valve system, controlling syatem, daily checking, leakage, checking noise, cleaning of plant and its surrounding area etc, as per manufacturers instructions and as specified and directede by Engineer-in-Charge. 12 Per Calander month Excess(+) Full Conversion INR
42 Comprehensive maintenance of the above STP & SCADA (of capacity 100 KLD as per srl item No 1 to 3 of this BOQ) { Phase - VI refer Sch "A" note no.2.1(f) } ,for the period of 2nd years after expiry of first year of Defect Liability Period. The scope of comprehensive maintenance includes maintenance of complete infrastructure under this work and replacing all defective components and restoring any defect / deformity / wear and tear and comprehensive maintenance of all STP components under this job, (Sl item No. 1.00 to 3.00) including all connected LT cubicle STP panel , all pumps and DG Sets in the scope of entire tender for further period of 12 Months after completion defect liability period. The scope shall also include comprehensive maintenance of all electrical & Sewage Pumps items such as main switch, starter, change over switch, MCCB, voltmeter, anmeter, panel board etc, Sewage water pump, valve system, controlling syatem, daily checking, leakage, checking noise, cleaning of plant and its surrounding area etc, as per manufacturers instructions and as specified and directede by Engr-in-Charge. 12 Per Calander month Excess(+) Full Conversion INR 1.01 Supplying, Conveying and fixing spls. Including eart item1 123.223 Nos
43 icer. (e) Shifting of DG set from factory to work site by means of truck/ crane is deemed included in quoted rates. (f) Platform for DG set shall be as per OEM recommendations and rates for construction of PCC plateform deemed included in quoted rates. (g) Contractor shall submit the CPCBIV+ compliance report/ certificate of DG set, BIS certificate for diesel engine, wiring diagram to the department alongwith, manufacturer test report etc.
Total in Figures 4 Construction of chamber for 100mm sluice plates item5 10 Nos
Quoted Rate in Figures Select
Quoted Rate in Words
stage.html
html • 0.02 MB
cancelled_1.pdf
pdf • 1.29 MB
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.81 MB
TENDER.pdf
Tender Documents • 4.65 MB
BOQ_834153.xls
BOQ • 0.34 MB
CORRIGENDUM05.pdf
PDF • 1.60 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .