| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹23.3 CrAccepted-AOC | ₹23.3 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹24.5 CrRejected-Finance | ₹24.5 Cr | L2 | Rejected-Finance SECOND BIDDER LOWEST |
| 3 | L3₹25.7 CrRejected-Finance | ₹25.7 Cr | L3 | Rejected-Finance THIRD BIDDER LOWEST |
| 4 | L4₹26.1 CrRejected-Finance | ₹26.1 Cr | L4 | Rejected-Finance FOURTH BIDDER LOWEST |
| 5 | L5₹26.5 CrRejected-Finance | ₹26.5 Cr | L5 | Rejected-Finance FIFTH BIDDER LOWEST |
Tender Value
Refer Docs
EMD Value
₹43.5 L
Closing Date
15 Mar 2021, 12:00 pmClosed
SE ETAWAH CIRCLE PWD ETAWAH
SE ETAWAH CIRCLE PWD ETAWAH
Widening and Strengthening of Bheekheypur to Juhikha (ODR) from Chainage 0.000 to Chainge 17.600(Part of Newly Declared SH 152) in District Auraiya (Length 17.600 KM)
2021_CEKNP_549623_1
292/55C-EV/2020-21 DATE 14-01-2021
Open Tender
Civil Works - Roads
300 days
AURAIYA
Please refer Tender documents.
5 documents required · 5 mandatory
₹2,714
₹43.5 L
ETAWAH
2 Jul 2021
28 Jan 2021
16 Mar 2021
28 Jan 2021
15 Mar 2021
28 Jan 2021
28 Jan 2021 - 15 Mar 2021
12 Feb 2021
Amount
Clearing grass and removal of rubbish up to a distance of 50 metres outside the periphery of the area . As per Morth Sepecification No. 201
Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material with in all lifts and lead upto 1000 metres. as per MORTH specification No. 305. 4.3
Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m as per MORTH specification No. 301. 3.6
Construction of embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2.
Construction of granular sub-base Gr.-I by providing close graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401. for widening portion. as per MoRTH specification clause No. 401
Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.(two coat) as per MoRTH specification clause No. 406
Providing, laying, spreading of graded stone aggregate(WMM) after mixing with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying with 1% OPC cement and 3.5% Emulsion in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.
Providing and applying tack coat with bitumen using bitumen pressure distributor at the rate of 0.35 kg per sqm on the prepared bituminous/granular surface cleaned with mechanical broom. (Clause No. 503)
Providing and laying bituminous concrete with 100-120 TPH batch type hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 to 5.6 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 509 complete in all respects
Construction of un-reinforced, dowel jointed, plain cement concrete pavement over a prepared sub base with 43 grade cement @ 400 kg per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing compound, finishing to lines and grades as per drawing
Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work.
Sand Filling in Foundation Trenches as per Drawing & Technical Specification
Plain cement concrete 1:4:8 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.
Brick Masonry Work in Cement Mortar 1:3 in Foundation complete excluding Pointing and Plastering, as per Drawing and Technical Specifications.
Providing and laying of weephole in brick massonary in abutment and wing wall with 100mm dia PVC pipe extending through the full width of the structuer with slope of 1v:20 H towarddrawing force complete as per drawing and technical specification
Plain/Reinforced Cement Concrete in Open Foundation With Batching Plant, Transit Mixer and Concrete Pump (M - 25 Grade) 1:1.5:3
Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications.(1:2:4)
Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per drawing and technical specifications
Stuck pointing with cement and fine sand of 1.25 fineness modulus morter on stone work in proportion of 1:2 including supply of all materials, labour and tools and plants etc. required for proper completion of the work.
Filling brickbats as filler material between roadcrust and abutment
SIDDHARTH CONSTRUCTION
Jeevan Construction Company
M/S SHUBH CONSTRUCTION
RCC Developers ltd.
M/S YATINDRA KUMAR TRIPATHI
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf