| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹6.7 LAccepted-Finance | L1 | Accepted-Finance L1 LOWEST
PRICE
BIDDER | |
| 2 | L2₹7.1 L+₹40,540 (6.09%)Rejected-Finance | L2 | Rejected-Finance RATES ARE
ON HIGHER
SIDE
BIDDER | |
| 3 | L3₹7.2 L+₹53,940 (8.11%)Rejected-Finance | L3 | Rejected-Finance RATES ARE
ON HIGHER
SIDE
BIDDER |
Tender Value
Refer Docs
EMD Value
₹7,000
Closing Date
10 Feb 2025, 1:00 pmClosed
SUPERINTENDING ENGINEER
Electricity Transmission Circle, 220KV Sub-Station, Gidahi, Basti.
Replacement of old and defective Gasket by new standard Gasket to prevent oil leakage of 40MVA Transformer-I BBL make and 40MVA Transformer-II AREVA make at 132 KV Sub-station, Bansi under ETD-II, Basti H.Q. at Siddharthnagar
2025_UPTCL_999697_1
SHORT TERM E-TENDER NO.34/ETC(B)/2024-25
Open Tender
Electrical Works
Lump-sum
15 days
220 KV SUB STATION GIDAHI BASTI
As per Tender Document
2 documents required · 2 mandatory
₹826
UPSEB ELECTRICITY TRANSMISSION DIVISION BASTI
₹7,000
13 Feb 2025
29 Jan 2025
11 Feb 2025
29 Jan 2025
10 Feb 2025
29 Jan 2025
Amount
Dismantling of 40 MVA T/F Accessories including radiator, Bushing, Buchholz relay. Oil pipe line from conservatore tank oil line to OLTC Surge Relay, Conservator tank etc
Complete drain out of T/F oil from the Existing 40 MVA T/F in to Empty oil drum/ oil tank.
Replacement of all Gasket including the top Cover of T/F by Providing and Fixing of new gasket as per Existing Size made of rubberized Cork Sheet Kotika / turboze/ Cork brand grade.
Creating vacuum inside the main tank for the period of 12 Hrs and Filling of Centrifusing oil step up to Core & Winding conservator Tank Radiator etc.
Erection of HV/LV and neutral bushing with its turrets, inlet-outlet and OLTC pipelines with all valves surge relay, buchholz relay, inspection covers, tap changer gearbox etc for the gasket replacement of 40 MVA T/F-I & II M/S BBL and Areva make Transformer.
Centrifusing of complete T/F oil in oil tank by connecting centrifusing pipes circulating oil through centrifusing machine and observing BDV values till the desired value is achieved as per direction of supervising engineer and after complete filling the oil in T/F along with conservators and OLTC as above, completing the circulation of T/F oil through centrifusing machine till the desired oil properties and IR values are achieved as per direction of supervising engineer.
Carriage of oil tank 20 Kl including loading & unloading from 220KV store location to near 40MVA T/F-I & II at 132KV Substation, Bansi
Gupta Elect and Engg Works (BID ID -4935124)
Perfect Power Transformer Associates (BID ID -4935495)
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .