| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.5 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹2.8 L+₹28,005.42 (11.3%)Rejected-AOC | L2 | Rejected-AOC L2 |
Tender Value
₹2.5 L
EMD Value
₹2,543
Closing Date
23 Jun 2026, 5:00 pmClosed
Executive Officer, Paralakhemundi Municipality
Executive Officer, Paralakhemundi Municipality
Drain work
2026_ORULB_131882_15
01/PKDM-2026-27
Open Tender
Civil Works - Others
Percentage
60 days
Paralakhemundi Municipality
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,000
₹2,543
Yes
23 Sept 2026
12 Jun 2026
24 Jun 2026
12 Jun 2026
23 Jun 2026
12 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismentalling and removing cement concrete including stacking the useful materials for reuse and removing the debris within 50 m . Lead | 4.5 | Cum | 877.16 | ₹3,947.22 |
| 2 | Earth work in all kinds of soil within 50m. Initial lead and 1.5m. Initial lift including rough dressing and breaking clods to maximum 5cm.to 7cm. and laying in layers not exceeding 0.3 m. in depth asper direction of the Engineer-in-charge. | 31.22 | Cum | 306.01 | ₹9,553.63 |
| 3 | Disposal of excavated earth by truck within 5 km. lead including to the lower area of the town for filling of depression etc. complete. | - | Cum | 185.85 | - |
| 4 | Filling foundation and plinth with sand and wel watered &rammedetc . Complete including cost of sand . | 2.08 | Cum | 915.12 | ₹1,903.45 |
| 5 | Cement Concrete (1:3:6) by using 4cm. Size C. B.H.G. metal including cost, conveyance etc. complete. | 4.16 | Cum | 6,333.97 | ₹26,349.32 |
| 6 | R:C:C: (1:2:4) using 12 mm. size H.G.(C.B) Chips including the cost of all materials, labour carriage, royalty etc complete. | 14.15 | Cum | 7,948 | ₹1,12,464.2 |
| 7 | Straightening, cutting, bending, binding tor steel rods, cranking, hooking,tying the grills & placing in proper positionfor RCC work including cost of binding wire ,cost conveyance, taxes of steel and other materials etc. complete | 6.85 | Qntl. | 10,798.31 | ₹73,968.42 |
| 8 | Rigid & smooth centering shuttering for Rcc work including false work & dismantling R.C.C Foundation & Plinth & Footing bases of Coloums mass Concrete etc. | 66.6 | Sqmt | 249.83 | ₹16,638.68 |
| 9 | Cost of sign board & photographs etc…. | 1 | Ls | 2,900 | ₹2,900 |
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.58 MB
BOQ_596148.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .