Tender ID
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹7.9 L
EMD Value
₹15,876
Closing Date
2 Dec 2026, 3:00 pm6d left
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Manisha Naik Dessai
Fatorpa Quital
Construction of retaining wall behind Devappa Scholl at Cotto in w.No. 1 of V.P. Fatorpa-Quitol
2026_VP_33492_1
VP/FQ/E-Tender/N/2026-2027/788 Line3
Open Tender
Civil Works
Works
90 days
Fatorpa Quital
Please refer Tender documents.
2 documents required · 2 mandatory
₹5,000
₹15,876
23 Nov 2026
23 Nov 2026
4 Dec 2026
23 Nov 2026
2 Dec 2026
23 Nov 2026
90 days
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earthwork in excavation by mechanical means (hydraulic excavator)/manual means in foundation pipeline trenches drain (not exceeding 1.5m in width or 10 sq. m. on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m including getting out the excavated soil and disposal of surplus excavated soil as directed within a lead of 50m. | 44.85 | Cu.m. | 291 | ₹13,051.35 |
| 2 | Rubble packing with hard laterite stone under floors including watering ramming and consolidating etc. in pipeline trenches and other foundations complete. | 8.97 | Cu.m. | 2,211 | ₹19,832.67 |
| 3Providing and laying in position cement concrete 1:2:4 (1 cement : 2 coarse sand: 4 graded granitic or basaltic stone aggregate 40 m nominal size) excluding cost of centering, shuttering and finishing : | |||||
| 3.01 | All works upto plinth level | 101.32 | Cu.m. | 6,635 | ₹6,72,258.2 |
| 4Centering & shuttering including Strutting, Propping & removal of forms for | |||||
| 4.01 | Foundations, footings, bases for columns and mass concrete. | 185.01 | Sq.m. | 407 | ₹75,299.07 |
| 5 | Refilling the pipeline/foundation trenches plinth sides, foundation etc. with available excavated earth in layers not exceeding 20 cm depth consolidating each layer ramming and watering lead upto 50 M and all lifts and disposal of surplus earth as directed by Engineer in Charge. | 32.89 | CU.M. | 245 | ₹8,058.05 |
| 6 | Providing and fixing weepholes with rigid PVC make laid in position with a required slope and level while layingpipes of approved the concrete of retaining wall,wing wall and earth retainig structure complete as directed by the Engineer in charge | 28.8 | RM | 185 | ₹5,328 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.39 MB
BOQ_33875.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .