| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹8.3 LAdmitted-Finance | L1 | Admitted-Finance | ||
| 2 | L2₹9.3 L+₹1.0 L (12.6%)Admitted-Finance | L2 | Admitted-Finance | ||
| 3 | L3₹9.4 L+₹1.1 L (13.8%)Admitted-Finance | L3 | Admitted-Finance | ||
| 4 | L4₹9.4 L+₹1.1 L (13.8%)Admitted-Finance | L4 | Admitted-Finance | ||
| 5 | L5₹9.5 L+₹1.2 L (14.0%)Admitted-Finance | L5 | Admitted-Finance |
Tender Value
₹14.5 L
EMD Value
₹29,080
Closing Date
17 Aug 2026, 6:00 pmClosed
Er Karanjeet Singh
Executive Engineer PWD RandB Division Gandhi Nagar Jammu
Fencing of FPF HQ Complex excluding front side by way of providing and fixing of Y-Shape angle iron concertina wire on existing boundary walls, repair of boundary wall, painting, whitewashing along with allied works at FPF HQ J-01 F/S Jammu
2026_PWDJK_319728_2
Short e-NIT No. DGN/56 of 2026-27 Dated 05-08-2026
Open Tender
Civil Works
Percentage
90 days
FPF HQ Complex Jammu
Please refer to e-NIT/SBD
3 documents required · 3 mandatory
₹600
Executive Engineer PWD RandB Division Gandhi Nagar
₹29,080
Jammu
27 Aug 2026
6 Aug 2026
18 Aug 2026
6 Aug 2026
17 Aug 2026
6 Aug 2026
11 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Demolishing brick work manually/by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 meters lead as per direction of Engineer-in-charge in cement mortar. | 16.41 | Cum | 1,458.45 | ₹23,933.16 |
| 2 | Dismantling old plaster or skirting, raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 50 meters lead. | 1,026.02 | Sqm | 38.9 | ₹39,912.18 |
| 3 | Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts,struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchors blocks, plain window sills, fillets etcupto floor V level, including curing but excluding the cost of centring, shuttering and finishing with 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size). | 16.41 | Cum | 8,422.45 | ₹1,38,212.4 |
| 4 | Centering and shuttering including strutting, propping etc. and removal of form for Retaining walls, return walls, walls (any thickness) including attached pilasters buttresses, plinth and string course fillets, kerbs and steps etc. | 107.69 | Sqm | 628.95 | ₹67,731.63 |
| 5 | 12mm Cement plaster of mix 1 : 6 (1 cement : 6 coarse sand). | 1,133.71 | Sqm | 266.2 | ₹3,01,793.6 |
| 6 | White washing with lime to give an even shade on New Work (three or more coats). | 4,553.78 | Sqm | 29.95 | ₹1,36,385.71 |
| 7 | Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works. | 2,436 | Kg | 181.6 | ₹4,42,377.6 |
| 8 | Painting with synthetic enamel paint of approved brand and manufacture to give an even shade. Two or more coats on new work. | 111.24 | Sqm | 131.85 | ₹14,666.99 |
| 9 | Providing and fixing concertina coil fencing with punched tape concertina coil 600 mm dia 10 meter openable length ( total length 90m), having 50 nos rounds per 6 meter length, upto 3 m height of wall with existing angle iron ‘Y’ shaped placed 2.4 m or 3.00 m apart and with 9 horizontal R.B.T. reinforced barbed wire, stud tied with G.I. staples and G.I. clips to retain horizontal, including necessary bolts or G.I. barbed wire tied to angle iron, all complete as per direction of Engineer-in-charge, with reinforced barbed tape (R.B.T.) / Spring core (2.5mm thick) wire of high tensile strength of 165 kg/ sq.mm with tape (0.52 mm thick) and weight 43.478 gm/ meter (cost of M.S. angle, C.C. blocks shall be paid separately). | 701.22 | Mtrs | 305.8 | ₹2,14,433.08 |
| 10 | Fencing with R.C.C. post placed at required distance, embedded in cement concrete blocks, every 15th post, last but one end post and corner post shall be strutted on both sides and end post one side only, provided with horizontal lines and two diagonals of barbed wire weighing 9.38 kg per
100 meters (minimum), between the two posts fitted and fixed with G.I. staples on wooden plugs or G.I. binding wire tied to 6 mm bar nibs fixed while casting the post (cost of R.C.C. posts, struts, earth work and concrete to be paid for separately) :- Payment to be made per meter cost of total length of barbed wire used.With G.I. barbed wire. | 3,300 | Mtrs | 12.45 | ₹41,085 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.75 MB
BOQ_1060006.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .