Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹20.5 LAccepted-AOC 213 TAJOPUR PASCHIMPURA MAUNATH BHANJAN MAU MAU UTTAR PRADESH 275101 UDYAM UP 55 0009322 | MAU | UTTAR PRADESH | 275101 | ₹20.5 L | L1 | Accepted-AOC Accepted,BeingL-1 |
| 2 | L2₹21.2 LRejected-Finance | ₹21.2 L | L2 | Rejected-Finance Rejected,BeingL-2 |
| 3 | Rejected-Technical | - | - | Rejected-Technical Being Non Responsive |
| Sl No | Description | Qty | Unit | M/S TANISHAQ ENTERPRISES L2 | M/S SINGH CONSTRUCTION L1 |
|---|---|---|---|---|---|
| 1.00 | Cleaning thick bushes and thorny jungle without uprooting , labour,material and T & P etc as directed by Engineer-in-Charge for proper completion of work . | 14,175 | M2 | 5.12 ₹72,576 | 4.95 ₹70,166.25 |
| 2.00 | Silt clearance/trench digging in wetted drain including all lifts and all leads , including cost of driver/assistant driver, POL, maintenance of machine, contractor profit, taxes etc but excluding leveling, dressing & compaction as directed by Engineer-in-Charge for proper completion of work. | 236 | M3 | 57.23 ₹13,506.28 | 55.4 ₹13,074.40 |
| 3.00 | Silt clearance/trench digging in under water in drain including all lifts and all leads , including cost of driver/assistant driver, POL, maintenance of machine, contractor profit, taxes etc but excluding leveling, dressing & compaction as directed by Engineer-in-Charge for proper completion of work . | 1,739 | M3 | 70.81 ₹1.2 L | 68.6 ₹1.2 L |
| 4.00 | Silt clearance/trench digging in under water in drain with for slush and lehel including all lifts and all leads , including cost of driver/assistant driver, POL, maintenance of machine, contractor profit, taxes etc but excluding leveling, dressing & compaction as directed by Engineer-in-Charge for proper completion of work . | 2,076.5 | M3 | 98 ₹2.0 L | 94.9 ₹2.0 L |
| 5.00 | Removing sewar and jalkumbhi from main canal branches & distributaries, escapes & its disposal at toe of bank & destroying by burning as directed by Engineer-in-Charge for proper completion of work . | 1,157.5 | M2 | 4.9 ₹5,671.75 | 4.7 ₹5,440.25 |
| 6.00 | Plain cement concrete in M10 (1:3:6) in with stone ballast including cost of material, labour and t&p etc complete as directed by Engineer-in-Charge for proper completion of work . | 44.88 | M3 | 5,980.53 ₹2.7 L | 5,795 ₹2.6 L |
| 7.00 | Random rubble masonary work in 1:4 with cement , coarse sand with hard stone in toe wall & sleeper including cost of all material, labour and T&P etc. complete as directed by Engineer-in-Charge for proper completion of work . | 149.5 | M3 | 5,599 ₹8.4 L | 5,425 ₹8.1 L |
| 8.00 | Supply of Geotextile sheet made of 200 GSM woven multiflament polypropylene yarn sheet below pitching on slopes including all cost of labour material, and T&P etc. with all taxes but excluding cost of GST directed by Engineer-in-Charge for proper completion of work . | 840 | M2 | 109 ₹91,560 | 106.2 ₹89,208 |
| 9.00 | Laying Boulder pitching 20 to 40 kg. weight including all cost of material , labour , T & P etc as directed by Engineer-in-Charge for proper completion of work . | 193.2 | M3 | 2,150.78 ₹4.2 L | 2,084.25 ₹4.0 L |
| 10.00 | Finishing walls with Acrylic Smooth exterior paint of required shade Old work (Two or more coat applied @ 1.67 ltr/ 10 sqm) on existing cement paint surface as required including cost of all material, labour and T&P etc. required for proper completion of work or as directed by Engineer-in-Charge. | 880.6 | M2 | 99.23 ₹87,381.94 | 96.25 ₹84,757.75 |
Tender Value
₹21.8 L
EMD Value
₹44,000
Closing Date
12 Jan 2026, 11:00 amClosed
Executive Engineer ,Head works Division, Sarda can
Executive Engineer, Head works Division, Sarda canal Bareilly.
Purani Sharda Devha Poshak Nahar ke km. 7.577 per Sthit Lohiya Saiphon ko cross Karti hui Lohiya Drain ke U/S v D/S main Drain Safai v Boulder Pitching ke Karya.
2026_UPIDC_1103227_1
E-Tender Notice No 06/EE/2025-26
Open Tender
Civil Works - Canal
30 days
Banbasa
Please refer Tender documents.
2 documents required · 2 mandatory
₹854
₹44,000
Yes
3 Feb 2026
5 Jan 2026
12 Jan 2026
5 Jan 2026
12 Jan 2026
5 Jan 2026
Cleaning thick bushes and thorny jungle without uprooting , labour,material and T & P etc as directed by Engineer-in-Charge for proper completion of work .
Silt clearance/trench digging in wetted drain including all lifts and all leads , including cost of driver/assistant driver, POL, maintenance of machine, contractor profit, taxes etc but excluding leveling, dressing & compaction as directed by Engineer-in-Charge for proper completion of work.
Silt clearance/trench digging in under water in drain including all lifts and all leads , including cost of driver/assistant driver, POL, maintenance of machine, contractor profit, taxes etc but excluding leveling, dressing & compaction as directed by Engineer-in-Charge for proper completion of work .
Silt clearance/trench digging in under water in drain with for slush and lehel including all lifts and all leads , including cost of driver/assistant driver, POL, maintenance of machine, contractor profit, taxes etc but excluding leveling, dressing & compaction as directed by Engineer-in-Charge for proper completion of work .
Removing sewar and jalkumbhi from main canal branches & distributaries, escapes & its disposal at toe of bank & destroying by burning as directed by Engineer-in-Charge for proper completion of work .
Plain cement concrete in M10 (1:3:6) in with stone ballast including cost of material, labour and t&p etc complete as directed by Engineer-in-Charge for proper completion of work .
Random rubble masonary work in 1:4 with cement , coarse sand with hard stone in toe wall & sleeper including cost of all material, labour and T&P etc. complete as directed by Engineer-in-Charge for proper completion of work .
Supply of Geotextile sheet made of 200 GSM woven multiflament polypropylene yarn sheet below pitching on slopes including all cost of labour material, and T&P etc. with all taxes but excluding cost of GST directed by Engineer-in-Charge for proper completion of work .
Laying Boulder pitching 20 to 40 kg. weight including all cost of material , labour , T & P etc as directed by Engineer-in-Charge for proper completion of work .
Finishing walls with Acrylic Smooth exterior paint of required shade Old work (Two or more coat applied @ 1.67 ltr/ 10 sqm) on existing cement paint surface as required including cost of all material, labour and T&P etc. required for proper completion of work or as directed by Engineer-in-Charge.
Please Enable Macros to View BoQ information
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.55 MB
BOQ_2034505.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid