| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹63.7 LAdmitted-Finance | ₹63.7 L | L1 | Admitted-Finance |
| 2 | L2₹66.5 L+₹2.8 L (4.39%)Admitted-Finance | ₹66.5 L+₹2.8 L (4.39%) | L2 | Admitted-Finance |
| 3 | Rejected-Technical | - | - | Rejected-Technical Technically Not Qualified |
| 4 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical EMD/Fee not received |
| 5 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical EMD/Fee not received |
| Sl No | Description | Qty | Unit | Abhishek Thakur L2 | sham lal L1 |
|---|---|---|---|---|---|
| 1.00 | Earth work in excavation by mechanical means Hydraulic excavator)/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto1.5 m, as directed by Engineer-in-charge. Ordinary rock. | 241.98 | Cum | 1,08,891 ₹1,28,491.38 | 47,186.1 ₹55,679.6 Lowest |
| 2.00 | Centering and shuttering including strutting, propping etc. and removal of form work for Retaining walls, return walls, walls (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc. | 375.06 | Sqm | 82,513.2 ₹97,365.58 Lowest | 1,35,021.6 ₹1,59,325.49 |
| 3.00 | Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing:1:2:4 (1 Cement : 2 coarse sand) : 4 graded stone aggregate 20 mm nominal size). | 760.66 | Cum | 49,44,290 ₹58,34,262.2 | 47,76,944.8 ₹56,36,794.86 Lowest |
| 4.00 | Providing and fixing U-PVC pipes (working pressure 4 kg / cm²) Single socketed pipe 110 mm dia. for weep holes. | 239.5 | Metre | 59,875 ₹70,652.5 | 35,925 ₹42,391.5 Lowest |
| 5.00 | Providing and filling of Stone boulder behind R/wall. | 34.65 | Cum | 41,580 ₹49,064.4 Lowest | 43,312.5 ₹51,108.75 |
| 6.00 | Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer-in-charge.Nominal concrete 1:4:8 or leaner mix (i/c equivalent design mix). | 51.88 | Cum | 62,256 ₹73,462.08 | 44,098 ₹52,035.64 Lowest |
| 7.00 | Centering and shuttering including strutting, propping etc. and removal of form for Edges of slabs and breaks in floors and walls Under 20 cm wide. | 54 | M | 13,500 ₹15,930 | 5,940 ₹7,009.2 Lowest |
| 8.00 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level upto floor five level, excluding cost of centering, shuttering, finishing and reinforcement: 1:1.5:3 (1 cement: 1.5 coarse sand): 3 graded stone aggregate 20 mm nominal size). | 26.4 | Cum | 1,71,600 ₹2,02,488 Lowest | 1,76,880 ₹2,08,718.4 |
| 9.00 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing inpositionand binding all complete above plinth levelThermo-MechanicallyTreatedbarsofgrade Fe-500D or more. | 1,473.4 | KG | 1,47,340 ₹1,73,861.2 | 1,29,659.2 ₹1,52,997.86 Lowest |
Tender Value
₹64.1 L
EMD Value
₹1.3 L
Closing Date
12 May 2026, 5:00 pmClosed
Dy General Manager (PnC)
Procurement and Contract Wing, CPS-I Khairi Distt. Chamba (HP) 176325.
Protection work near Left and Right Bank of TRT Outlet, CPS-1, Khairi.
2026_NHPC_906591_1
NH/CPS-1/PnC/W-1627/2026-27/66 Dated 27/04/2026
Open Tender
Civil Works
Works
120 days
Chamera Power Station-1, Khairi, Distt-Chamba (HP)
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,180
NHPC LIMITED
₹1.3 L
Yes
11 Jul 2026
27 Apr 2026
15 May 2026
27 Apr 2026
12 May 2026
27 Apr 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means Hydraulic excavator)/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto1.5 m, as directed by Engineer-in-charge. Ordinary rock. | 241.98 | Cum | 1 | ₹241.98 |
| 2 | Centering and shuttering including strutting, propping etc. and removal of form work for Retaining walls, return walls, walls (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc. | 375.06 | Sqm | 1 | ₹375.06 |
| 3 | Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing:1:2:4 (1 Cement : 2 coarse sand) : 4 graded stone aggregate 20 mm nominal size). | 760.66 | Cum | 1 | ₹760.66 |
| 4 | Providing and fixing U-PVC pipes (working pressure 4 kg / cm²) Single socketed pipe 110 mm dia. for weep holes. | 239.5 | Metre | 1 | ₹239.5 |
| 5 | Providing and filling of Stone boulder behind R/wall. | 34.65 | Cum | 1 | ₹34.65 |
| 6 | Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer-in-charge.Nominal concrete 1:4:8 or leaner mix (i/c equivalent design mix). | 51.88 | Cum | 1 | ₹51.88 |
| 7 | Centering and shuttering including strutting, propping etc. and removal of form for Edges of slabs and breaks in floors and walls Under 20 cm wide. | 54 | M | 1 | ₹54 |
| 8 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level upto floor five level, excluding cost of centering, shuttering, finishing and reinforcement: 1:1.5:3 (1 cement: 1.5 coarse sand): 3 graded stone aggregate 20 mm nominal size). | 26.4 | Cum | 1 | ₹26.4 |
| 9 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing inpositionand binding all complete above plinth levelThermo-MechanicallyTreatedbarsofgrade Fe-500D or more. | 1,473.4 | KG | 1 | ₹1,473.4 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 4.74 MB
Tender.pdf
Tender Documents • 5.54 MB
BOQ_952918.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .