| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹2.1 LAccepted-Finance M 36 HOUSING UNIT MATHAIYANKUTTAI PO METTUR DAM 636452 | METTUR DAM | SALEM | TAMIL NADU | 636452 | 1 | Accepted-Finance Satisfied | |
| 2 | 2₹2.2 L+₹11,340 (5.50%)Accepted-Finance H 6 HOUSING BOARD UNIT MATHAVANKUTTAI P O METTUR DAM 636 452 | METTUR DAM | SALEM | TAMIL NADU | 636452 | 2 | Accepted-Finance Satisfied |
Tender Value
Refer Docs
EMD Value
₹2,700
Closing Date
17 Feb 2021, 2:00 pmClosed
Superintending Engineer /Mechanical-I/MTPS-I
Office of the Superintending Engineer / Mechanical -I Mettur Thermal Power Station- I Mettur Dam-636406
MTPS I Mill Plant Unit I Dismantling patch welding and assembling of Mill outlet elbows orifices Transition pieces fabrication of spool piece Multiple port outlets and rectification of hanger support etc
2021_EB_195310_1
SE / M-I / MTPS-I / MP / OT. 335 / 2020-21
Open Tender
Power/Energy Projects/Products
Works
20 days
Mettur Thermal Power Station-I / Mettur Dam
As per the Tender Specification
4 documents required · 4 mandatory
₹0
₹2,700
Yes
24 Feb 2021
11 Feb 2021
18 Feb 2021
11 Feb 2021
17 Feb 2021
11 Feb 2021
Amount
Charges for arresting the coal pipe firmly, dismantling victaulic coupling and lowering down the mill outlet elbows to 4.5 m. floor including charges for scaffolding
Charges for inspection of mill outlet elbows and changing the deflector block if any lifting the elbows and assembling with proper alignment with the existing pipe line and removing coal pipe supports and devolution of scraps to stores.
Labour charges for including drawl of materials from stores and removal of old eroded coal pipe after arresting the coal pipes firmly and providing necessary supports or platform and welding coal pipe pieces in MOE/coal pipes below MOE / MPO & Transition piece devolution of scraps to stores
Charges for dismantling the Spool pieces, multiple port outlet bodies and transition pipes 4 Nos. each after assembling the coal pipe inspection with center feed pipe structures including transportation of supporting material from stores to site and re-fixing the Spool piece, MPO bodies and transition pieces and assembling to its original position and carrying out necessary related works. and devolution of scraps to stores etc. for a mill.(1D to 1F)
Charges for removal of orifice 1 No. after dismantling the victaulic coupling, inspecting and inverting the same orifice or new orifice and assembling in position.
Cutting the worn out pipes of varied length , grinding edges and welding with coal pipe collars in the respective area inclusive of cutting the new coal pipe of same length and transporting of pipe from stores and devolution of scraps to stores.(Vertical portion)
Charges for removing the existing damaged hanger supports assembly arrangements in the coal pipes for assembly
Rectification of hanger support rod fixture eye, strengthening the pin and its nuts for assembly.
Charges for re fixing the hanger supports arrangements in its original position of the coal pipes without changing its elevation for assembly.
Consumables and T&P’s Sl.No. 1 to 9
R K ENGINEERING CONTRACTOR
stage.html
html • 0.04 MB
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .