Loading…
Loading…
| # | Company | Amount | Status |
|---|---|---|---|
| 1 | ₹26.4 LAWARDED | AWARDED |
Tender Value
₹26.5 L
EMD Value
₹78,125
Closing Date
31 Jul 2025, 9:30 pmClosed
Directorate of Municipal Administration
Proposed Vermi composting Shed at SWM Site TP Examba
DMA/2025-26/BD/WORK_INDENT44054/CALL-2
DMA/2025-26/BD/WORK_INDENT44054/CALL-2
Open
Buildings
Two Tender Document System(Two Cover)
DMA Town Panchayat Examba
₹670
₹78,125
24 Jul 2025
24 Jul 2025
2 Aug 2025
24 Jul 2025
Proposed Vermi composting Shed at SWM Site TP Examba
Compacting original ground supporting embankment Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of ...
Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution li...
Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes...
Providing Coursed rubble masonry (first sort) with hard stone in foundation and plinth with Cement mortar 1:6 (1 cement : 6 coarse sand)PWD Common SR 2023-24 VOl.2(Page No.9, I.No.5.2)
Providing Flush/ Ruled pointing: Pointing on stone work with cement mortar 1:3 (1 cement : 3 fine sand) after raking joints to depth nicely lin
ing, including cost of materials, labour, curing as p...
Providing and laying in position Cement Concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes...
Form Work: As per recommendations of Technical working group, rates for formwork shall be added on percentage basis to the finished concrete item rate For Foundation upto Plinth All other types Form...
Form Work: As per recommendations of Technical working group, rates for formwork shall be added on percentage basis to the finished concrete item rate For RCC Beams, Lintels & Troughs of Aqueducts Fo...
Form Work: As per recommendations of Technical working group, rates for formwork shall be added on percentage basis to the finished concrete item rate For RCC Columns / Shaft (Slip Centering) Form Wo...
Supplying, fitting and placing TMT FE 550 / 550D Steel Reinforcement including cost of all materials, machinery, labour, cleaning, straightening, cutting, bending, hooking, laping/welding joints, tyin...
Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by r...
Construction of Granular Sub-Base of required grading as per design spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with front end loader at OMC and com...
Construction of dry lean cement concrete Sub- base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm,aggregate cement rat...
Providing and constructing un-reinforced plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M20 (Grade), c...
Providing and fixing Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and applying a priming coat of approv...
Providing & fixing corrugated G.S. sheet roofing including vertical / curved surface fixed with polymer coated J or L hooks, bolts and nuts 8 mm diameter with bitumen and G.I. limpet washers or with G...
Providing Brick work with common burnt clay Non Modular bricks of class designation 3.5 in superstructure above plinth level in all shapes and
sizes in Cement mortar 1:4 (1 cement : 4 coarse sand) in...
Providing 15 mm cement plaster on the rough side of single or half brick wall of mix 1:4 (1 cement: 4 fine sand) including rounding off corners wherever required smooth rendering, providing and removi...
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .