| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹75.9 LAccepted-AOC PATHANTIR MENDHAR | MENDHAR | POONCH | JAMMU AND KASHMIR | ₹75.9 L | L1 | Accepted-AOC The lowest responsive bidder was found technically and financially suitable. |
| 2 | L2₹78.7 L+₹2.9 L (3.79%)Rejected-AOC | ₹78.7 L+₹2.9 L (3.79%) | L2 | Rejected-AOC Higher rates quoted compared to the L1 bidder. |
| 3 | L3₹80.5 L+₹4.6 L (6.05%)Rejected-AOC | ₹80.5 L+₹4.6 L (6.05%) | L3 | Rejected-AOC Higher rates quoted compared to the L1 bidder. |
Tender Value
₹96.2 L
EMD Value
₹1.9 L
Closing Date
5 Feb 2026, 6:00 pmClosed
Executive Engineer I and FC poonch
Office of the Executive Engineer I and FC poonch
Construction of check dams and water channel in Tehsil Mendhar District Poonch JK 2nd Call
2026_IFC_301916_1
e-NIT No.29 of 2025-26 Dated 31-01-2026
Open Tender
Civil Works
Percentage
Mendhar
As per NIT
2 documents required · 2 mandatory
₹1,600
Yes
Executive Engineer, Irrigation and Flood Control D
₹1.9 L
Yes
9 May 2026
31 Jan 2026
6 Feb 2026
31 Jan 2026
5 Feb 2026
31 Jan 2026
Construction of Checkdam at Pallian Nallah
Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth upto 30 cm measured at a height of 1 m above ground level and removal of rubbish upto a distance of 50 m outside the periphery of the area cleared.
Clearing grass and removal of the rubbish upto a distance of 50 m outside the periphery of the area cleared.
Earth work in bulk excavation by manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 m2 on plan) including disposal of excavated earth lead upto 50 meters and lift upto 1.5 m, as directed by Engineer-in-Charge.Hard Rock (Blasting Prohibited)
Banking excavated earth in layers not exceeding 20cm in depth, breaking clods, watering, rolling each layer with 1/2 tonne roller, or wooden or steel rammers, and rolling every 3rd and top-most layer with power roller of minimum 8 tonnes and dressing up, in embankments for roads, flood banks, marginal banks, and guide banks etc., lead upto 50 m and lift upto 1.5 m in All kinds of soil:
Providing and laying in position ready mixed plain cement concrete, with cement content as per approved design mix and manufactured in fully automatic batching plant and transported to site of work in transit mixer for all leads, having continuous agitated mixer, manufactured as per mix design of specified grade for plaincement concrete work, including pumping of R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering and finishing, including cost of curing, admixtures in recommended proportions as per IS : 9103 to accelerate/ retard setting of concrete, improve workability without impairing strength and durability as per direction of the Engineer - in - charge. Note: 1) Excess/less cement used than specified in this item is payable/recoverable separately. M-15 grade plain cement concrete (cement content considered @ 240 Kg/cum.)
workability without impairing strength and durability as per direction of Engineer-incharge. Note: - Cement in this item is @ 330 kg/ cum. Excess or less cement used as per design mix is content considered payable or recoverable separately. 5.34.1 All works upto plinth level
workability without impairing strength and durability as per direction of Engineer-incharge. Note: - Cement in this item is @ 330 kg/ cum. Excess or less cement used as per design mix is content considered payable or recoverable separately. All works above plinth level upto floor V level
Extra for providing richer mixes at all floor levels. Note:- Excess/ less cement over the specified cement content used is payable/ recoverable separately Providing M-40 grade concrete instead of M-25 grade BMC/RMC.
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level Thermo-Mechanically Treated bars of grade Fe-500D or more.
Centering and shuttering including strutting, propping etc. and removal of form work for: Foundations, footings, bases for columns
Centering and shuttering including strutting, propping etc. and removal of form for: Retaining walls, return walls, walls (any thickness) including attached pilasters buttresses, plinth and string course fillets, kerbs andsteps etc.
Dry stone pitching 22.5 cm thick including supply of stones and preparing surface complete.
carriage of sand & Aggregates 10 km by MT
carriage of cement avg Distance of 200M by H/L
carriage of steel avg distance of 12km by MT&100m by H/L
Construction of checkdam Near chakbanola At Kalaban Nallan
Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth upto 30 cm measured at a height of 1 m above ground level and removal of rubbish upto a distance of 50 m outside the periphery of the area cleared.
Clearing grass and removal of the rubbish upto a distance of 50 m outside the periphery of the area cleared.
Earth work in bulk excavation by manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 m2 on plan) including disposal of excavated earth lead upto 50 meters and lift upto 1.5 m, as directed by Engineer-in-Charge.Hard Rock (Blasting Prohibited)
Banking excavated earth in layers not exceeding 20cm in depth, breaking clods, watering, rolling each layer with 1/2 tonne roller, or wooden or steel rammers, and rolling every 3rd and top-most layer with power roller of minimum 8 tonnes and dressing up, in embankments for roads, flood banks, marginal banks, and guide banks etc., lead upto 50 m and lift upto 1.5 m in All kinds of soil:
Providing and laying in position ready mixed plain cement concrete, with cement content as per approved design mix and manufactured in fully automatic batching plant and transported to site of work in transit mixer for all leads, having continuous agitated mixer, manufactured as per mix design of specified grade for plaincement concrete work, including pumping of R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering and finishing, including cost of curing, admixtures in recommended proportions as per IS : 9103 to accelerate/ retard setting of concrete, improve workability without impairing strength and durability as per direction of the Engineer - in - charge. Note: 1) Excess/less cement used than specified in this item is payable/recoverable separately. M-15 grade plain cement concrete (cement content considered @ 240 Kg/cum.)
workability without impairing strength and durability as per direction of Engineer-incharge. Note: - Cement in this item is @ 330 kg/ cum. Excess or less cement used as per design mix is content considered payable or recoverable separately. All works upto plinth level
workability without impairing strength and durability as per direction of Engineer-incharge. Note: - Cement in this item is @ 330 kg/ cum. Excess or less cement used as per design mix is content considered payable or recoverable separately. All works above plinth level upto floor V level
Extra for providing richer mixes at all floor levels. Note:- Excess/ less cement over the specified cement content used is payable/ recoverable separately Providing M-40 grade concrete instead of M-25 grade BMC/RMC.
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level Thermo-Mechanically Treated bars of grade Fe-500D or more.
Centering and shuttering including strutting, propping etc. and removal of form work for: Foundations, footings, bases for columns
Centering and shuttering including strutting, propping etc. and removal of form for: Retaining walls, return walls, walls (any thickness) including attached pilasters buttresses, plinth and string course fillets, kerbs andsteps etc.
Dry stone pitching 22.5 cm thick including supply of stones and preparing surface complete.
carriage of sand & aggregates10 km by MT &800M by H/L
carriage of cement avg Distance of 800M by H/L
carriage of steel avg distance of 12km by MT&800m by H/L
Construction of checkdams at Takiya on Kalaban Nallan
Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth upto 30 cm measured at a height of 1 m above ground level and removal of rubbish upto a distance of 50 m outside the periphery of the area cleared.
Clearing grass and removal of the rubbish upto a distance of 50 m outside the periphery of the area cleared.
Earth work in bulk excavation by manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 m2 on plan) including disposal of excavated earth lead upto 50 meters and lift upto 1.5 m, as directed by Engineer-in-Charge.Hard Rock (Blasting Prohibited).
Banking excavated earth in layers not exceeding 20cm in depth, breaking clods, watering, rolling each layer with 1/2 tonne roller, or wooden or steel rammers, and rolling every 3rd and top-most layer with power roller of minimum 8 tonnes and dressing up, in embankments for roads, flood banks, marginal banks, and guide banks etc., lead upto 50 m and lift upto 1.5 m in All kinds of soil:
Providing and laying in position ready mixed plain cement concrete, with cement content as per approved design mix and manufactured in fully automatic batching plant and transported to site of work in transit mixer for all leads, having continuous agitated mixer, manufactured as per mix design of specified grade for plaincement concrete work, including pumping of R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering and finishing, including cost of curing, admixtures in recommended proportions as per IS : 9103 to accelerate/ retard setting of concrete, improve workability without impairing strength and durability as per direction of the Engineer - in - charge. Note: 1) Excess/less cement used than specified in this item is payable/recoverable separately. M-15 grade plain cement concrete (cement content considered @ 240 Kg/cum.)
workability without impairing strength and durability as per direction of Engineer-incharge. Note: - Cement in this item is @ 330 kg/ cum. Excess or less cement used as per design mix is content considered payable or recoverable separately. All works upto plinth level
workability without impairing strength and durability as per direction of Engineer-incharge. Note: - Cement in this item is @ 330 kg/ cum. Excess or less cement used as per design mix is content considered payable or recoverable separately. All works above plinth level upto floor V level
Extra for providing richer mixes at all floor levels. Note:- Excess/ less cement over the specified cement content used is payable/ recoverable separately Providing M-40 grade concrete instead of M-25 grade BMC/RMC.
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level Thermo-Mechanically Treated bars of grade Fe-500D or more.
Centering and shuttering including strutting, propping etc. and removal of form work for: Foundations, footings, bases for columns
Centering and shuttering including strutting, propping etc. and removal of form for: Retaining walls, return walls, walls (any thickness) including attached pilasters buttresses, plinth and string course fillets, kerbs andsteps etc.
Dry stone pitching 22.5 cm thick including supply of stones and preparing surface complete.
carriage of sand & Aggregates15 km by MT & 500M by H/L
carriage of cement avg Distance of 500 M by H/L
carriage of steel avg distance of 15km by MT 500m by H/L
Construction of Water channel and Protection work
Earth work in bulk excavation by mechanical means (hydraulic excavator) over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 m2 on plan) including disposal of excavated earth lead upto 50 meters and lift upto 1.5 m, as directed by Engineer-in-Charge. All kinds of soil
24.5 Hand-packing stones in wire-crates; excluding cost of crates and stones
supply of stone
carriage of stone 500 M by H/L
supply of crates including carriage (6x1.5x1.5)
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.40 MB
BOQ_979562.xls
BOQ • 0.42 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .