Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.8 LAdmitted-Fee/PreQual/Technical/Finance | ₹4.8 L | L1 | Admitted-Fee/PreQual/Technical/Finance |
| 2 | L2₹5.0 L+₹12,994.64 (2.69%)Admitted-Fee/PreQual/Technical/Finance | ₹5.0 L+₹12,994.64 (2.69%) | L2 | Admitted-Fee/PreQual/Technical/Finance |
| 3 | L3₹6.1 L+₹1.3 L (26.6%)Admitted-Fee/PreQual/Technical/Finance | ₹6.1 L+₹1.3 L (26.6%) | L3 | Admitted-Fee/PreQual/Technical/Finance |
| Sl No | Description | Qty | Unit | BALASUBRAMANIYAN L1 | SABAREESH L3 | DHEV & CO L2 |
|---|---|---|---|---|---|---|
| 1.00 | Earth work excavation in all parts of soils except hard rock requiring blastering etc. with initial lead and life and as directed by the departmental officers etc., complete as per standard specification SS 20. | 18.5 | M3 | 198 ₹3,663 Lowest | 950 ₹17,575 | 225 ₹4,162.5 |
| 2.00 | Supplying and filling in foundation and basement with Crushed Stone Sand (M- Sand) in layers of not more than 15cm thick well rammed watered and compacted etc., complete complying with standard specification. | 3 | M3 | 2,439 ₹7,317 Lowest | 4,850 ₹14,550 | 2,500 ₹7,500 |
| 3.00 | Plain Cement Concrete 1:4:8 (one part of cement, four part of Crushed Stone Sand (M- Sand) and Eight part of coarse aggregates) using 40mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges and all incidential charges such as water providing etc., complete as per standard specification | 3 | M3 | 6,046.83 ₹18,140.49 | 4,000 ₹12,000 Lowest | 6,100 ₹18,300 |
| 4.00Centering for sofits of RCC slabs of Plane surface like lintels, beams etc., including strutting 3m high using mild steel sheets of size 90cm x 60cm and B.G. 10 stiffened with M.S. angles of size 25mm x 25mm x 3mm laid over silver Oak (CW) joists of size 10cmx 6.5cm (spaced at about 90cm c/c) complying with standard specification. | ||||||
| 4.10 | Grade Beam | 12 | M2 | 293.13 ₹3,517.56 Lowest | 4,500 ₹54,000 | 293.13 ₹3,517.56 Lowest |
| 4.20 | Column | 21 | M2 | 1,171.55 ₹24,602.55 Lowest | 2,500 ₹52,500 | 1,171.55 ₹24,602.55 Lowest |
| 4.30 | Slab & Beam | 30.5 | M2 | 976.46 ₹29,782.03 Lowest | 6,000 ₹1,83,000 | 976.46 ₹29,782.03 Lowest |
| 5.00Providing and laying in position Standardised Concrete Mix M-20 Grade in accordance with IS 456 - 2000 using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement contenet of 325Kg/ cum and maximum water cement ratio of 0.55 including admixture (Plasticiser / super plasticiser) in recommended proportions as per IS 9103 to accelerate, related setting of concrete, improve workability without imparing strength and durability with about (5.0cum), 7730Kg of 20mm machine crushed stone jelly and with about (3.3 cum), 5156kg of 10 - 12mm machine crushed stone jelly and with about (4.79cum) 7670 kg of Crushed Stone Sand (M- Sand), but excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary without claiming extra cost etc., complete complying with standard specification and as directed by the departmental officers - | ||||||
| 5.10 | Basement | 4.75 | M3 | 8,717.84 ₹41,409.74 | 5,500 ₹26,125 Lowest | 8,850 ₹42,037.5 |
| 5.20 | Above Basement | 5.75 | M3 | 8,845 ₹50,858.75 | 7,500 ₹43,125 Lowest | 8,900 ₹51,175 |
Tender Value
₹6.5 L
EMD Value
₹6,550
Closing Date
21 Aug 2026, 3:00 pmClosed
The Commissioner, Nagapattinam Municipality.
The Commissioner, Nagapattinam Municipality.
Construction of Kitchen at Samanthanpettai Middle School in Nagapattinam Municipality.
2026_MAWS_692078_8
0070/2026/E1
Open Tender
Civil Works - Buildings
Item Rate
90 days
Nagapattinam Municipality
Qualification
2 documents required · 2 mandatory
₹0
₹6,550
Yes
21 Aug 2026
7 Aug 2026
21 Aug 2026
7 Aug 2026
21 Aug 2026
7 Aug 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work excavation in all parts of soils except hard rock requiring blastering etc. with initial lead and life and as directed by the departmental officers etc., complete as per standard specification SS 20. | 18.5 | M3 | 10 | ₹185 |
| 2 | Supplying and filling in foundation and basement with Crushed Stone Sand (M- Sand) in layers of not more than 15cm thick well rammed watered and compacted etc., complete complying with standard specification. | 3 | M3 | 10 | ₹30 |
| 3 | Plain Cement Concrete 1:4:8 (one part of cement, four part of Crushed Stone Sand (M- Sand) and Eight part of coarse aggregates) using 40mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges and all incidential charges such as water providing etc., complete as per standard specification | 3 | M3 | 10 | ₹30 |
| 4Centering for sofits of RCC slabs of Plane surface like lintels, beams etc., including strutting 3m high using mild steel sheets of size 90cm x 60cm and B.G. 10 stiffened with M.S. angles of size 25mm x 25mm x 3mm laid over silver Oak (CW) joists of size 10cmx 6.5cm (spaced at about 90cm c/c) complying with standard specification. | |||||
| 4.1 | Grade Beam | 12 | M2 | - | - |
| 4.2 | Column | 21 | M2 | - | - |
| 4.3 | Slab & Beam | 30.5 | M2 | - | - |
| 5Providing and laying in position Standardised Concrete Mix M-20 Grade in accordance with IS 456 - 2000 using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement contenet of 325Kg/ cum and maximum water cement ratio of 0.55 including admixture (Plasticiser / super plasticiser) in recommended proportions as per IS 9103 to accelerate, related setting of concrete, improve workability without imparing strength and durability with about (5.0cum), 7730Kg of 20mm machine crushed stone jelly and with about (3.3 cum), 5156kg of 10 - 12mm machine crushed stone jelly and with about (4.79cum) 7670 kg of Crushed Stone Sand (M- Sand), but excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary without claiming extra cost etc., complete complying with standard specification and as directed by the departmental officers - | |||||
| 5.1 | Basement | 4.75 | M3 | - | - |
| 5.2 | Above Basement | 5.75 | M3 | - | - |
stage.html
html • 0.02 MB
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.10 MB
BOQ_832206.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .